Beruflich Dokumente
Kultur Dokumente
401
Project Management
Spring 2006
Risk Analysis
Decision making under risk and uncertainty
Preliminaries
Announcements
Remainder
FEASIBILITY
DESIGN
PLANNING
DEVELOPMENT CLOSEOUT
Financing&Evalua
tion
Risk
Analysis&Attitude
OPERATIONS
DESIGN
PLANNING
DEVELOPMENT CLOSEOUT
OPERATIONS
RISK MNG
Decision making
Some Risks
Weather changes
Different productivity
(Sub)contractors are
Unreliable
Lack capacity to do work
Lack availability to do
work
Unscrupulous
Financially unstable
Community opposition
Infighting &
acrimonious
relationships
Unrealistically low bid
Late-stage design
changes
Unexpected subsurface
conditions
Soil type
Groundwater
Unexpected Obstacles
Settlement of adjacent
structures
High lifecycle costs
Permitting problems
Importance of Risk
General conditions
Payment Terms
Delivery Method
Selection mechanism
Outline
Risk and Uncertainty
Risk Preferences, Attitude and
Premiums
Examples of simple decision trees
Decision trees for analysis
Flexibility and real options
Decision modeling
Decision making under uncertainty
Tool: Decision tree
Fault trees
Introduction to Decision
Trees
Represent
Flow of time
Decisions
Uncertainties (via events)
Consequences (deterministic or stochastic)
Risk Preference
Risk preference
Categories of Risk
Attitudes
Decision Rules
= 1 pessimistic
= 0.5 neutral
= 0 optimistic
repair
$0.55
$1.43
Investment PV
Pessimistic rule
min (1, 1.61) = 1 replace the bridge
The optimistic rule (maximax)
max (1, 0.55) = 0.55 repair and hope it
works!
0.5
$1.61 M
$0.55
Investment PV
0.25
$1.43
of probabilities change
risk attitude
Other criteria
Buy later
-100
-100-30+5 = -125
-100+5 = -95
-100+5+30 = -65
Buy later
-100
0. 5
0.25
-125
-95
0.25
-65
Adding a Preference
function
1.35
1
.7
125
100
65
70
Notion of a Risk
Premium
.25
Certainty equi
of investment
.5*$20,000+.5*$0=$10000
.50
.5*f($20,000)+.5*f($0)=.25
Mean valu
Of investm
$5000
Certainty Equivalent
Example
Consider a risk averse
individual with
Certainty Equivalent
Consider
Risk averse individual A for whom f1(E[f(c)])<E[c]
Less risk averse party B
EMV
(0.5)(-1) + (0.5)(1) = 0
Multiple Attribute
Decisions
C3
MTTF 6.6667
Cost 0.30
C4
MTTF
Cost 0.00
5.7738
Pareto Optimality
03/06/06 - Preliminaries
Announcements
Reading questions/comments?
Multiple objective
The students dilemma
Bidding
Example Bidding
Decision Tree
Time
Decisions
Events
Arrival time (On time, early, late)
Theft or damage (only if arrive early)
Consequences: Cost
Procurement Tree
Monetary Value of
$6.75M Bid
Larger Uncertainties in
Cost
(Monetary Value)
Large Uncertainties II
(Monetary Values)
Optimal Strategy
Delaying decision
Extra time
Cost to pay for extra fat to allow for
flexibility
Ways to Ensure of
Flexibility
in Construction
Alternative Delivery
Clear spanning (to
allow movable walls)
Extra utility
conduits (electricity,
phone,)
Larger footings &
columns
Broader foundation
Alternative
heating/electrical
Value engineering
Geotechnical conditions
Procurement strategy
Additional elevator
Larger electrical
panels
Property for expansion
Sequential
construction
Wiring to rooms
Adaptive Strategies
Real Options
Considerations
Tradeoffs
Readings
Required
More information:
Recommended:
Meredith Textbook, Chapter 4 Prj
Organization
Risk management and insurances Stellar