Beruflich Dokumente
Kultur Dokumente
Introduction
concept to roadster.
Needed to develop new 8.0-litter V-10
aluminum engine and new high performance
six-speed transmission.
Comparable projects usually require five years
at Chrysler.
project
develop.
Transmission developed in 1.5 years
compared to the usual 5 to 6 years.
Many important innovations in the frame,
body, and brakes were incorporated .
Zeneca Pharmaceuticals
Mission is the development of new drugs
physical product.
Long duration, extreme costs, and high
chances for failure.
10
Background
Project management concerned with
11
Examples of Projects
Constructing highways,
12
Technology
Better-Educated Citizens
More Leisure Time
Increased Accountability
Higher Productivity
Faster Response to
Customers
Greater customization for
customers
Chapter 12: Project
Management
13
14
15
16
17
the project.
Those that the PM will need to
communicate with closely.
Those with rare skills necessary to project
success.
18
19
20
Complexity of Scheduling
Project Activities
Large number of activities
Precedence relationships
Limited time of the project
21
22
23
Terminology
Activity
Event
Network
Path
Critical Path
Critical Activities
Dummy Activities
Chapter 12: Project
Management
24
Inputs
activity completion times
activity precedence relationships
Outputs
graphical representation of project
time to complete project
identification of critical path(s) and activities
activity and path slack
earliest start, earliest finish, latest start, and latest finish times
for each activity
25
Example
Activity Time Preceded By
A
10
-B
7
-C
5
A
D
13
A
E
4
B,C
F
12
D
G
14
E
Chapter 12: Project
Management
26
Network Diagram
A(10)
4
D(13)
F(12)
C(5)
B(7)
E(4)
3
Paths
G(14)
Time Slack
A-D-F
35
A-C-E-G
33
B-E-G
25
10
critical path
27
28
29
30
Path Slack
31
ES
0
0
10
10
15
23
19
EF LS LF Slack
10 0 10
0
7 10 17
10
15 12 17
5
23 10 23
0
19 17 21
2
35 23 35
0
33 21 35
2
32
33
t o 4t m t p
6
t p to
34
Example
Activity Preceded By to
tm
tp
te
--
5.50
.694
--
7.00
.444
4.83
.250
10
10
10
10.0
0.000
B,C
4.0
.111
12
13
11.5
.913
4.33
1.000
35
1
[7.0,
0.444]
A
B
2 [10, 0.0]
[11.5, 0.913]
C [4.83,
0.250]
6
E
G
[4.33, 1.0]
[4.0,
0.111]
36
37
Expected
Standard
Time
Variance Deviation
A-D-F
27
1.607
1.27
A-C-E-G
14.66
2.055
1.43
B-E-G
15.33
1.555
1.25
38
Probabilities of Completion
39
25 27
z
157
.
1.27
From standard normal table in Appendix A,
there is a 5.82% chance of completing
project on or before time 25.
Chapter 12: Project
Management
40
5.82%
41
42
43
44
45
Mean (days)
32.1
Standard
Deviation
1.2
24.6
3.1
22.2
2.2
26.1
5.2
34.4
6.2
34.5
4.1
46
Activity
F
Path1 Path 2
(A-C-F) (B-D-F)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Chapter Minimum
12: Project
Maximum
Management
Path 3
(B-E)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Project
Finish Time
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
47
48
49
Activity
F
Path1 Path 2
(A-C-F) (B-D-F)
30.80
0.00
31.91
0.00
32.21
0.00
32.65
0.00
31.91
0.00
34.78
0.00
32.07
0.00
29.27
0.00
30.26
0.00
30.55
0.00
32.17
0.00
31.74
0.00
32.15
0.00
33.23
0.00
31.05
0.00
34.07
0.00
32.81
0.00
30.39
0.00
33.99
0.00
31.18
0.00
32.17
0.00
32.94
0.00
30.94
0.00
31.15
0.00
32.25
0.00
29.27
0.00
34.78
0.00
ChapterMinimum
12: Project
Maximum
Management
Path 3
(B-E)
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
Project
Finish Time
30.80
31.91
32.21
32.65
31.91
34.78
32.07
29.27
30.26
30.55
32.17
31.74
32.15
33.23
31.05
34.07
32.81
30.39
33.99
31.18
32.17
32.94
30.94
31.15
32.25
29.27
34.78
50
Activity
F
28.68
35.16
34.91
35.08
29.13
33.23
34.28
40.94
33.54
30.46
34.60
28.96
35.27
26.21
32.37
31.79
41.62
39.79
38.59
45.35
32.37
34.34
32.73
30.14
31.98
Minimum
Maximum
Path1 Path 2
(A-C-F) (B-D-F)
82.48
77.83
92.06
87.45
88.09
92.14
84.26
85.79
84.55
77.30
89.00
79.10
87.11
92.95
91.15
89.75
88.80
71.66
79.66
64.36
90.96
77.55
83.45
76.56
88.06
81.72
82.13
65.86
85.29
87.40
86.82
86.28
95.07
92.76
91.28
93.51
93.87
91.98
97.72
92.39
86.74
74.21
87.82
85.29
90.20
78.68
84.25
91.71
88.29
89.32
79.66
64.36
97.72
93.51
Path 3
(B-E)
57.70
65.30
52.73
43.87
49.21
59.86
64.29
70.40
63.09
56.40
57.47
48.08
63.85
72.62
55.72
66.97
58.12
65.74
53.68
53.95
51.72
38.72
58.94
65.78
59.50
38.72
72.62
Project
Finish Time
82.48
92.06
92.14
85.79
84.55
89.00
92.95
91.15
88.80
79.66
90.96
83.45
88.06
82.13
87.40
86.82
95.07
93.51
93.87
97.72
86.74
87.82
90.20
91.71
89.32
79.66
97.72
51
52
53
54
55
56
Variance Report
Cost standard determined using engineering
57
Cost-Schedule Reconciliation
Charts
58
59
60
Introduction
Similar issues that trouble people about working on
trade-offs
To what extent are these problems caused by human
decisions and practices?
Chapter 12: Project
Management
61
62
Average
Std Dev
Max
Min
Median
63
Observations
Average Completion Times
Implications of Assuming Known Activity
Times
Shape of the Distribution
Worker Time Estimates
Impact of Inflated Time Estimates
Student Syndrome
Chapter 12: Project
Management
64
Multitasking
65
66
project
67
deadlines
Hidden safety time complicates task of
prioritizing project activities
Lack of clear priorities results in poor
multitasking
Chapter 12: Project
Management
68
69
individual
Schedule start of new projects based on
availability of bottleneck resources
Reduce amount of safety time added to individual
tasks and then add some fraction back as project
buffer
activity durations set so that there is a high probability
the task will not be finished on time
Chapter 12: Project
Management
70
events
considers both precedence relationships and
resource dependencies
Project Buffer
Feeding Buffer
71
72
73
Copyright
Copyright John Wiley & Sons, Inc. All rights reserved.
Reproduction or translation of this work beyond that named in Section
117 of the United States Copyright Act without the express written
consent of the copyright owner is unlawful. Requests for further
information should be addressed to the Permissions Department, John
Wiley & Sons, Inc. Adopters of the textbook are granted permission
to make back-up copies for their own use only, to make copies for
distribution to students of the course the textbook is used in, and to
modify this material to best suit their instructional needs. Under no
circumstances can copies be made for resale. The Publisher assumes
no responsibility for errors, omissions, or damages, caused by the use
of these programs or from the use of the information contained herein.
74