Beruflich Dokumente
Kultur Dokumente
TAJAMUL ISLAM
CE-10-51
CONTENTS
THE PROBLEM
Introduction
History and characteristics
Structure
Foundation soil profile
Motion of foundation
THE SOLUTION
Temporary foundation stabilisation measures
Permanent foundation stabilisation measures
Additional foundation stabilisation works
A GLIMPSE INTO THE FUTURE
CONCLUSION
INTRODUCTION
It is the bell tower of the cathedral.
Construction began in 1173.
Known world over for its tilt.
Efforts to fix the tower have been going on for 800
years.
HISTORY AND
CHARACTERISTICS
Work on the foundation began on 9 August 1173.
The Tower was constructed in the course of about 200 years.
The third cornice had only just been completed when, in c. 1178, the
CONSTRUCTION
TIMELINE
CHARACTERISTICS
STRUCTURE
Hollow cylinder.
Whole weight supported
by walls.
Walls are made from
stone, lime and mortar
covered with a marble
faade.
Due to the tilt there was an
inequality of pressure on the
masonry walls.
FOUNDATION SOIL
PROFILE
Plain of Pisa is composed of geologically recent lagoon marsh
deposits.
Between ground level and a depth of about 10 m (horizon A): sands
and silts with irregular stratifications, but with a prevalence of clayey
silts under the southern part of the Tower (it is maintained that this is
the cause which led to the inclination of the monument).
Between 10 and 40 m depth (horizon B): soil composed primarily of
soft clays with an interlaying layer of sand. The upper surface of the
clay, more or less horizontal over the entire square, is depressed by
more than two metres underneath the Tower; this is a deformation
induced over the centuries by the weight of the Tower. This fact leads
to the estimation that the overall subsidence of the Tower is between
2.5 and 3 metres.
Below 40m depth (horizon C): Dense sands.
FOUNDATION SOIL
PROFILE
MOTION OF
FOUNDATION
Precise measurements began in 1911.
There has been a progressive increase in the inclination, usually
MOTION CONTD...
1. Leaning instability.
2. North side steadily rising,
counterweights could be
used.
3. Seat of continuing longterm rotation lies in the
horizon A.
4. In addition to creep, the
most likely cause of the
progressive seasonal
rotation was the fluctuating
ground water level.
TEMPORARY
SOLUTION
Lead counter-weights(600t increased to 900t)
were added to the north side via a posttensioned removable concrete ring.
PERMANENT
SOLUTION
Reducing the inclination by means
of controlled ground extraction.
Large scale trails were
commenced, primarily to develop a
specialised drilling technology for
the job.
Soil extraction was continued at a
slow pace.
After the start of extraction it was
completed in 3 years. The tower
had rotated by about 1800 arc
seconds northwards during this
period.
ADDITIONAL
MEASURES
An ancient ring detected in the bottom of the catino, was
ADDITIONAL MEASURES
CONTD...
Studies showed that the seasonal fluctuating water table
DRAINAGE SYSTEM
FUTURE
Experts envisage the following two scenario's :
Optimistic scenario: Continuing rotation has been
stopped, except for minor movements caused by
ground water level fluctuations. This scenario implies
that the dominant mechanism driving the leaning
instability was fluctuations of the ground water level.
Pessimistic scenario: This scenario assumes that
the leaning instability was caused due to the
combined effects of foundation soil creep and ground
water fluctuations. Accordingly the rotation of the
tower may resume after sometime (to return to its
1993 inclination 200 years).
CONCLUSION
Most of the ideas to save the tower were
THANK YOU
(GRAZIE)