Beruflich Dokumente
Kultur Dokumente
Numbering Tasks
Level 1
Task 1
Level 2
Subtask 1.1
Level 3
Work Package 1.1.1
Why WBS?
A WBS provides the following
information structure:
A description of all significant work.
A clear task decomposition for
assignment of responsibilities.
A framework for scheduling,
budgeting, and expenditure tracking.
Estimating Effort
While A number of more accurate
methods exist for estimating cost and
effort here you will simply make your
best guess for the effort in person
hours requires to complete each work
package, subtask and task in your WBS.
Try to be as realistic as possible in
estimating what you can do in what
time.
Estimating Available
Resources
Try and determine how much time, in
person-hours, you can as a team
devote to the project.
Once again, be realistic.
Less Is More
You will be assessed on the quality of
the work you submit, NOT the
quantity.
Scheduling
Precedence of tasks. Some tasks cannot be
undertaken before others have been completed.
The set of relationships between the dependencies
for these tasks are called precedence relations.
To depict project tasks, their duration, and precedence
you are likely going to want to use some type of
chart that shows timeframes and scheduling. The
Gantt chart, otherwise known as a bar chart is
commonly used to do this. A Gantt chart is "a
graphic display of schedule-related information. In
the typical bar chart, activities of other project
elements are listed down the left side of the chart,
dates are shown across the top, and activity
durations are show as date-placed horizontal bars."
(Newell, 2002, p. 391).
Scheduling Exercise
Consider the scenario below and map it to Gantt Chart.
The requirements specification of an IT application is estimated to take two
weeks to complete. When this activity has been completed, work can start
on three software modules, A, B and C. The design/implementation of A, B
and C will need five, ten and ten days respectively. Modules A and B can
only be unit-tested together as their functionality is closely associated. This
joint testing should take two weeks. Module C will require eight days of unit
testing. Once all unit-testing has been completed, the planning of
integrated
system testing must take place and it would require a ten days. The activity
itself would take three weeks.
The project manager has decided not to allow any holiday for the duration
of this project.
(Excercise by: L. Eshkevari, P. Frem)
Activity
Duration
Precedence
Specification (S)
14 days
Design/Coding A
(DCA)
5 days
Design/Coding B
(DCB)
10 days
Design/Coding C
(DCC)
10 days
14 days
DCA,DCB
8 days
DCC
UTAB,UTC
Implementing
Integrated System
Test (IST)
21 days
Risk Management
2) Risk Control
21
UCM
source:http://en.wikipedia.org/wiki/Use_case_diagram
Domain Models
source: http://nubyonrails.files.wordpress.com/2007/07/domain-model.jpg