Beruflich Dokumente
Kultur Dokumente
By
Upali Fernando
(Chartered Quantity Surveyor, Independent Adjudicator/
Arbitrator, Cost Engineer & Chartered Builder)
WHAT IS DISPUTE
WHAT IS RESOLUTION
SUBCONTRACT
Only the Contractor and Nominated/Domestic
Subcontractors are parties to the Contract.
SUPPLY CONTRACT
Only the Contractor/ or Employer and
Nominated / Domestic Supplier are parties to
the contract.
CONSULTANCY CONTRACT
Only the Employer and the Consultant/the
Engineer are parties to the contract.
LITIGATION- (Adversarial)
Ultimate legal method for settling controversies or disputes
between and among persons, organizations, and the State.
In litigation process, a case (called suit or lawsuit) is brought
before a court of law suitably empowered (having the
jurisdiction) to hear the case, by the parties involved (the
litigants) for resolution (the judgement).
.
ARBITRATION (contd)
The following chart explain the way of commencing arbitration as
indicated in the FIDIC red book
Dispu
te
Exists
Yes
no
time ?
Determines no
yes
Agreeable
no
Yes
Resolved
Ask for
E's decision
Cl.67.1
84 days
70
days
56
days
If notice of intention to
commence Arbitration
is not given within 70 days
then the Engineer's
Decision becomes final
and
binding on the parties
E gives
yes
satisfied
decision
no
no
attempt
amicable
settlement
Attempted
yes
satisfied
no
no
yes
Resolved
yes
Resolved
ARBITRATION (CONTD)
Clause 2.3
Any communication given by the Engineers
representative to the contractorshall have the
same effect as though it had been given by the Engineer .
Provided that:
a).
b)If the Contractor questions any communication of the
Engineer s Representative he may refer the matter to the
Engineer who shall confirm , reverse or vary the contents
of such communication
ARBITRATION (CONTD)
Clause 67.1
If a dispute of any kind whatsoever arises
between the Employer and the
Contractor..including any dispute as to
any opinion , instruction ,determination , certificate or
valuation of the Engineer ,t he matter in dispute shall ,in
the first place be referred in writing to the Engineer with
a copy to the other party . Such reference shall
state that it is made pursuant to this clause. No
later than the eighty fourth day after the day on
which he received such reference the Engineer shall
give notice of his decision to the Employer and to the
Contractor. Such decision shall state that it is made
pursuant to this clause.
.
ARBITRATION (contd.)
Clause 67.2
Where notice of intention to commence arbitration as to a dispute
has been given..the parties shall attempt to settle
such dispute amicably before the commencement of arbitration .
Provided that unless the parties otherwise agree
,arbitration may be commenced on or after the fifty sixth day
.even if no attempt at amicable settlement thereof has
been made
Clause 67.3
Any dispute in respect of which:
a)the decision ,if any of the Engineer has not become final and
binding pursuant to Sub-Clause 67.1,and
b)amicable settlement has not been reached within the period
stated in Sub-Clause 67.2,
Shall be finally settled..under the Rules of Conciliation and
Arbitration of the International Chamber of Commerce by one or
more arbitrators appointed under such Rules
Procedure in Arbitration
Refer
ADJUDICATION-(Adversarial)
Adjudication is an Alternative Dispute
Resolution(ADR) process within the
construction industry has taken off with many
disputes now being resolved using the
Adjudication process as set out in the standard
forms of contract, sub-contract and consultant
agreements. It is intended to be quicker and
more cost effective than litigation or arbitration.
It is normally used to ensure payment (although
most types of dispute
can be adjudicated)
.The Adjudicator must generally decide the
dispute in less than 42 days. Dispute shall be
adjudicated by a recognized Dispute Adjudications Board
Procedure in adjudication
*Notice of reference to for adjudication to the
other party in dispute
*Appointing/invoking the adjudication to prior
agreement
*Submission of the written claim
*Giving the defending party a chance to answer
the complaint
Obtaining evidence/submission
*Once heard the parties to the dispute
Adjudicator will issue the decision (after
performing site visit If necessary)
Procedure in DAB
Similar to Adjudication.
A COMPARISON OF DISPUTE
RESOLUTION BOARDS AND
ADJUDICATION
The construction industry has always
had a special need for mechanisms to
resolve construction project disputes
promptly. The two newest and most
promising devices for providing real
time dispute resolution on construction
projects are the Dispute Resolution Board,
developed in the United States, and the
adjudication process, developed in
England.
Procedure in Minitrial
As per the organizational
procedures
MEDIATION (Non-adversarial)
This is an Alternate Dispute Resolution (ADR)method in which
an independent third party (mediator) assists the parties involved
in a dispute or negotiation to achieve a mutually acceptable
resolution of the points of conflict .The mediator who may be a
lawyer or a specially trained non-lawyer ,has no decision-making
powers and cannot force the parties to accept a settlement.
Mediation is widely used in all sorts of disputes, ranging from
divorces to civil lawsuits to very complex public policy problems to
international conflicts. Many disputes that have not responded to
an initial attempt at negotiation can still be settled through
mediation. Mediation is of particular importance in long-running,
deep-rooted conflicts, as this type of conflict is rarely resolved
without such outside assistance. Even if the full range of
grievances cannot be resolved, mediation is often useful for
dealing with particular limited aspects of the wider conflict.
Procedure in Mediation
Conciliation- (Non-adversarial)
Conciliation is an Alternative Dispute Resolution (ADR)
process whereby the parties to a dispute (including future interest
disputes) agree to utilize the services of a conciliator, who then
meets with the parties separately in an attempt to resolve their
differences. He does this by lowering tensions, improving
communications, interpreting issues, providing technical
assistance, exploring potential solutions and bringing about a
negotiated settlement.
Procedure of peaceful settlement of international disputes . The
matter of dispute is referred to a standing or ad-hoc commission
of conciliation ,appointed with the parties agreement. The
eventual report is expected to contain concrete proposal for a
settlement , which , however , the parties are under no legal
obligation to accept.
Procedure in Conciliation
There is no hard and fast procedure for
this method.
Ad-hoc procedures may adopt after
negotiating with the parties
ANY QUESTIONS
THANK YOU