The Gas Corridor through Turkey, Greece and Italy
(ITGI)
2
Overview of the ITGI
The ITG pipeline connecting Turkey with Greece has an actual capacity of 3.5 bcm/yr that with
certain investments in compression stations can be increased up to a max capacity of 11.5
bcm/yr.
The Turkish gas network is already extended from east to west and its transportation capacity
will require some future upgrades in order to secure, in addition with growing domestic demand,
long term transit capacity.
Under the Trilateral Intergovernmental Agreement, the maximum ITG Project Capacity
(i.e. 11,5 bcm/yr) will be reserved to the Greek Market and to transit for the IGI Poseidon.
4
The Greek on-shore section
The onshore section of the IGI Project will run from Komotini to
Ionian coast and will be realized by DESFA
(Greek TSO unbundled from DEPA)
5
The off-shore section : The Poseidon Pipeline
Poseidon Pipeline
Length: 210Km
Diameter: 32’’
Max Pressure: 150 barg
Depth: max. 1370 m
Initial capacity: 8 bcm/yr
Max capacity: 12 bcm/yr
6
IGI Poseidon SA
Edison and Depa have incorporated, under the Law of Greece, IGI
Poseidon S.A.
IGI Poseidon will develop, finance, realize, own and operate the
Poseidon Pipeline Project according to applicable regulations and
legislations in Italy and Greece.
Edison 50%
IGI Poseidon
DEPA 50%
A TPA Exemption for the Poseidon Pipeline has been approved for
an Exempted Capacity of 8 bcm per year for 25 years
(Edison 6.4 bcm/y ; Depa 1.6 bcm/y)
9
Institutional Framework of the ITGI Corridor (2/2)
10
IGI Project: Commercial Activities
12
Poseidon Development Plan
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
institutional support to the ITGI Project derived by the Intergovernmental Agreement among
Italy, Greece and Turkey (July 2007).
CI S AB
The Final Investment Decision will be taken by early 2010, provided that sufficient
gas volumes for the Poseidon Pipeline are secured.
13
Summary of the ITGI Project
Development Highlights
• Completion and operation of the Turkey – Greece Interconnector, a vital part of the overall project
(300 kms, 36’’ pipeline).
• Commitment of the States of Greece, Turkey, Italy to the realization of the ITGI project via
InterGovernmental Agreements.
• Completion of Basic Engineering and Reconnaisance Marine Survey between Greece-Italy offshore
area.
• Issuance of Ministerial Decrees in Italy and Greece for inclusion of the Greece-Italy Interconnector
within the national development plans.
• Activation of authorization Procedures to build and operate the IGI Project in Italy and Greece.
• Approval of TPA Exemption by the European Commission over a 25 year period from the operation
start-up, and for 8 bcm per year capacity of the offshore part of the Interconnector Greece-Italy (IGI
Poseidon).
• Incorporation of the IGI POSEIDON S.A., a joint, 50-50% stock company between Edison and Depa
for the construction and operation of the offshore part of the Greece-Italy Interconnector.
• Completion of the procedure of the Open Season bound with the operation of the project for a yearly
gas quantity up to 1 bcm in line with EC provisions.
• Ensurance of consistent and coordinated capacity allocation in Greece and Turkey with regard to the
ITGI Project through the 3-lateral InterGovernmental Agreement among Italy, Greece and Turkey.
• Detailed Engineering and Marine Survey Contracts under tender. Planned to be awarded by 2nd half
2008.
• Finalization of transportation agreements for exempted capacity within 2nd half 2009.
The final Investment Decision will be taken by early 2010 provided that sufficient gas volumes for the
Project are secured. 14