Beruflich Dokumente
Kultur Dokumente
work hours
Labor
Materials
Equipment
subs
1. Objectives of Cost
Control
2. Categories of Cost In
CI
A. Estimated Cost
Established prior to start (award)
May be assembled with limited
time / knowledge
Proper scope essential
Parameter for the control budget
are the sum of cost to date,
commitments and exposure.
2. Categories of Cost
(cont.)
B. Budgeted Cost
Developed by Project
Management, and
Should embrace managements
plans for:
Productivity (cost) objectives
Time & Quality requirements, and
Organization of the project
is derived from the detailed cost
estimate prepared at the start of the
project
5
Forecasting
BAC = Budget at completion
(Original project estimate)
ETC = (BAC BCWP)/CPI=> (Estimate
to complete)
EAC = (ACWP + ETC) =>(Estimate at
completion)
Example 1
ANSWER
The BCWS and BCWP shown above
were the same since all activities
that were scheduled for completion
were completed according to the
original planned schedule.
11
contd
Exercise
contd
Contd
Clause 38:
quantities
Change
in
bill
of
Continued
Continued
Continued
Continued
Clause 42: Payment Certificates
The Contractor shall submit to the
Engineer monthly statements of the
estimated value of the work executed
less the cumulative amount certified
previously
The
Engineer
shall
check
the
Contractors monthly statement and
certify the amount to be paid to the
Contractor.
The value of work executed shall be
determined by the Engineer.
Continued
Continued
Clause 43: Payments
Payamente
shall
be
ajustad
for
deducciones for advance payamente and
retantion
If an amount certified is increassed in a
later certificate or as a result of an award
by the Adjudicator or an Arbitrator, the
Contractor shall be paid interest upon the
delayed payment as set out in this clause
Unless otherwise stated, all payments and
deductions will be paid or charged in the
proportions of currencies comprising the
Contract Price.
Items of the Works for which no rate or
23
price has been entered in will not be paid
Payments
Payments in construction projects
may be
Advance Payments
Interim Payments
Payments after taking over
certificate /final Payments
Payments after defect liability
/closing of accounts
Payments after termination
Interim Payments
26
Continued
Clause 44: Compensation event
Clause 45: Tax
Unless otherwise specified in the SCC,
the Engineer shall not adjust the
Contract Price if taxes, duties, and other
levies are changed that subsequently
affect the Contract Price.
Clause 46: Currencies
Where payments are made in currencies
other than Ethiopian Birr, the exchange
rates used for calculating the amounts
to be paid shall be the exchange rates
stated in the Contractors Bid.
28
Escalation
Continued
Clause 47: Price Adjustments
Price Adjustments formula
Ln
Mn
En
pn A b
c
d
etc.
Lo
Mo
Eo
pn is a price adjustment factor (multiplier) to be applied
to the amount in each specific currency for each payment
certificate;
A is fixed coefficient, stated in the relevant table of
adjustment data representing the non-adjustable portion
in contractual payments.
b, c, d,.are coefficients representing the estimated
proportion of each cost element related to the execution
of the works, as stated in the relevant table of
adjustment; such tabulated cost elements may be
inductive of resources such as labour, equipments and
materials;
Continued
in
the
specific
currency
of
Continued
Clause 48: Retention
The Employer shall retain from each
payment due to the Contractor the
proportion stated in the SCC until
Completion of the whole of the
Works.
On completion of the whole of the
Works,
half
the
total
amount
retained shall be repaid to the
Contractor
and
half when the
Defects Liability Period has passed
and the Engineer has certified that
all Defects notified by the Engineer
Continued
Clause 49: Liquidated damage
Continued
50.Bonus:
The Contractor shall be paid a Bonus
calculated at the rate per calendar
day stated in the Special Conditions
of Contract for each day (less any
days for which the Contractor is paid
for acceleration) that the Completion
is
earlier
than
the
Intended
Completion Date. The Engineer shall
certify that the Works are complete
by the Contractor. Interest will not
be charged on the advance payment
The
Employer
shall
make
advance
payment to the Contractor of the
amounts stated in the SCC by the date
stated in the SCC, against provision by
the Contractor of an Unconditional Bank
Guarantee in a form and by a bank
aceptable to the Employer in amounts
and currencies equal to the advance
payment.
The Guarantee shall remain effective
until the advance payment has been
repaid, but the amount of the Guarantee
shall be progressively reduced by the
amounts repaid
Continue
d
52.Securities
The Contract Security shall be provided to
the Employer no later than 15 days after
receipt of the Letter of Acceptance and
shall be issued in the form of a Bank
Guarantee, or for Ethiopian Contractors
only in the form of a Performance Bond.
The Contract Security shall be valid until a
date 28 days from the date of issue of the
Certificate of Completion in the case of a
Bank Guarantee and until one year from
the date of issue of the Certificate of
Completion in the case of a Performance
Bond.
Continued
53. Day works
If applicable, the Day works rates in the
Contractors Bid shall be used for small
additional amounts of work only when the
Engineer has given written instructions in
advance for additional work to be paid for in
that way.
All work to be paid for as Day works shall be
recorded by the Contractor on forms approved
by the Engineer. Each completed form shall be
verified and signed by the Engineer within two
days of the work being done.
The Contractor shall be paid for Day works
subject to obtaining signed Day works forms.
Continued
54.Cost of Repairs
:
Loss or damage to the Works or
Materials to be incorporated in the
Works between the Start Date and
the end of the Defects Correction
periods shall be remedied by the
Contractor at the Contractors cost
if the loss or damage arises from
the Contractors acts or omissions.
Sample of payment
certificate
and how to prepare
Question???
u
o
y
k
n
a
h
T