Sie sind auf Seite 1von 53

HES3112 Urban Water Resources

Module 5
Estimation and Analysis of
Runoff from Urban Catchments

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Peak Runoff, Qp

Runoff Hydrograph

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

The Rational Method


Qy = 0.278 Cy ITc

Where;
Qy

Peak discharge (m3/s)

Cy

Runoff coefficient (y year ARI)

ITc
A
y

Average rainfall intensity (mm/h)


Catchment area (km2)
ARI (years)

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Urban Catchments
A R & R Chapter 14 (Book Eight)
Impervious Fraction Most Important Factor
In Defining C10
1987 - p 307, 2001 p 19

Impervious Fraction
Fraction of Catchment Covered in Impervious
Surfaces
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Australian Rainfall & Runoff


http://www.engaust.com.au/bookshop/arr.html

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Runoff Coefficient, C10

'
C10 0.9 f C10
1 f

C10' 0.1 0.0133 I110hryr 25

I = 70

I = 25

Cy C10 Fy

Impervious Fraction
Impervious Area
f
Catchment Area

Estimating Runoff in Urban Catchments Monzur Imteaz

Cy C10 Fy

HES3112 Urban Water Resources

Urban Frequency Factors


ARI (years)

Frequency Factor
Fy

1
2
5

0.8
0.85
0.95

10
20
50

1.0
1.05
1.15

100

1.2
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Time of Concentration
Estimate Travel Time
Overland Flow and Gutter Flow

Overland Flow
Kinematic Wave Equation
Assumes Homogeneous Surface
Combine Travel Time for Individual Homogeneous Surfaces

Gutter Flow
Manning Equation

2
1
1
3
Q A R So 2
n

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Overland Flow

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Kinematic Wave Equation

T 6.94 L n
T
L
n*
I
S

* 0.6

0.4

0.3

Overland Flow Time (mins)


Flow Path Length (m)
Surface Roughness Coefficient
Rainfall Intensity (mm/hr)
Slope (m/m)
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Surface Roughness Coefficients


Surface Type

Roughness
Coefficient

n*
Concrete or Asphalt

0.010-0.013

Bare Sand

0.010-0.016

Gravel Surface

0.012-0.030

Bare Soil

0.012-0.033

Sparse Vegetation

0.053-0.130

Grass Prairie

0.100-0.200

Lawns

0.170-0.480

From Australian Rainfall & Runoff, A R & R (2000)


Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

6
.
94
L
n
T

* 0.6

0.4

S 0 .3

L, n*, S known
I ??

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

T 6.94 L n
T I 0 .4

* 0.6

I
6.94 L n

Example

0 .4

* 0 .6

S 0 .3

S
0 .3

T*I0.4 = 43.3

Length, L = 60 m
Slope, S = 2% = 0.02 m/m
Roughness, n* = 0.05
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Time of Concentration

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Flow along the Kerb


Most of the urban
streets are
designed to carry
stormwater runoff
as well.

2
1
1
3
Q A R So 2
n

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Typical
Urban
Drainage
System

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Urban Drainage Systems:


Lot/house drainage
- Piped drainage
- Surface drainage
Street drainage
- Pipe drainage
- Kerb (channel) drainage
Open channel drainage
Detention basin

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

House Drainage

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Street Drainage

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Non-Homogeneous Catchment
Different Urban Land Uses
More than One Land Use Type in Catchment

Equivalent Impervious Area


For Each Land Use Type
Measure Area of Each Land Use, Ai
Define Fraction Impervious for Each Land Use, fi
Determine Runoff Coefficient for Each Land Use, Ci

CAtotal C1 A1 C 2 A2 ... C n An
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Non-Homogeneous Catchment
Different Travel Times in Each Land Use
Tc is Travel Time to Catchment Outlet

Depends on Drainage Network


Where Areas Drain Independently of Each Other
Stream Tributaries
Piped Drainage of Paved Areas etc

Partial Area Effect


Short Duration Storm MAY be Critical
(ie Storm with Duration < Tc)
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Partial Area Effect


Must Check Both Storm Durations
Longer Storm Duration
All of Catchment Contributes Runoff
Duration Equal to Time of Concentration, Tc

Shorter Storm Duration


Only One Sub-catchment Contributes Runoff
Plus Part of Second Sub-catchment
Duration Equal to Travel Time from One Sub-catchment

Peak Runoff is the Maximum Calculated


Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Example of Partial Area Effect


An urban catchment has an area of 3.25 km2. One
tributary drains an area of 1.2 km2, with a fraction
impervious of 85% and a travel time of 17 minutes.
The second tributary has a fraction impervious of 15%
with a travel time of 50 minutes.
Calculate the Peak runoff for the 10 year ARI when
I10yr,17min = 60 mm/hr, I10yr,50min = 32.0 mm/hr and I10yr,60min
= 28.6 mm/hr.
Repeat where the first sub-catchment f = 65%, travel
time is 30 minutes and I10yr,30min = 39.1 mm/hr.

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Pipe Drainage Design


Underground Street Drainage Pipes
Minor Drainage System
Runoff from Minor Storms
Low ARI (2 to 5 year ARI)

Streets and Drainage Reserves


Major Drainage System

High ARI (100 year ARI)

Pipe Network

Follows Natural Drainage Layout


Generally Conforms with Street Layout
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Minor and Major Drainage Systems

Fig. 1.3, Book VIII, Australian Rainfall & Runoff (2000)


Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Minor and Major


Drainage Systems

Fig. 1.2, Book VIII,


Australian Rainfall & Runoff
(2000)

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Overland Flowpath

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Design
Chart

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Analysis of Urban Drainage System


Pre-developed
Post-developed

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Locating Pits
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Design rainfall intensity, I = 90 mm/hr


Runoff co-efficient, C = 0.85
Longitudinal slope = 2%
Allowable street flow width = 2.1 m
From chart, allowable Q = 0.08 cumec
Using Rational Formula Q = C.I.A/360 = 0.85X90X(45XL0/10,000)/360
Q = 0.000956L0
L0 = 84 m

Locating Pits

Estimating Runoff in Urban Catchments Monzur Imteaz

Kerb Flow Design Chart


HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Bypass Flow

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Pit Capture Rate

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Locating Pits

Assume, first pit has a capture rate of 76%


Bypass flow = (1 - 0.76)x0.08 = 0.019 cumec
Allowable flow from second sub-catchment =
0.08 - 0.019 = 0.061 cumec
Using Rational Formula Q = C.I.A/360 = 0.85X90X(45XL1/10,000)/360
0.061 = 0.000956L1
L1 = 64 m
Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Pit/Pipe
Design

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Flow Paths

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Pit design in a car park


Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Postdeveloped
Drainage

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Detention Basin

Estimating Runoff in Urban Catchments Monzur Imteaz

HES3112 Urban Water Resources

Detention Basin

Estimating Runoff in Urban Catchments Monzur Imteaz