Beruflich Dokumente
Kultur Dokumente
Scheduling
Useful Abbreviations
CPM
8-2
Background
Schedule
Background Continued
Most
8-4
framework
Shows interdependences
Shows when resources are needed
Ensures proper communication
Determines expected completion date
Identifies critical activities
8-5
Shows
Microsoft
Terminology
Activity
Drawn left-to-right
Connections represent predecessors
8-8
Terminology Continued
Path
Terminology Continued
Sequential
Terminology Continued
Activity
8-11
Figure 8-2
Figure 8-3
8-12
Add
by Henry L. Gantt
Shows planned and actual progress
Easy-to-read method to know the current
status
8-14
Easily understood
Provide a picture of the current state of a
project
Disadvantage
8-15
Figure 8-11
8-16
Figure 8-12
8-17
Table 8-1
8-18
Figure 8-13
8-19
a 4m b
TE
6
b a
8-20
The Results
Table 8-2
8-21
Figure 8-15
8-22
Figure 8-16
8-23
Slack
Figure 8-16
8-24
Slack Values
Table 8-3
8-25
Precedence Diagramming
Finish
to start
Start to start
Finish to finish
Start to finish
8-26
Figure 8-17
8-27
Microsoft Projects
Table 8-4
8-28
Gantt Chart
Figure 8-18
8-29
AON Network
Figure 8-19
8-30
Figure 8-23
8-31
8-32
Example
(D )
50 43
33
7
1.22
5.745
D Z 43 5.7451.645 52.45
8-33
8-34