SNP Production Horizon

Horizon in which Supply Network Planning (SNP) and Capable-to-Match


(CTM) do not plan production.
Use in CTM
CTM does not generate or delete any planned orders within this
production horizon. The horizon starts on the system date (or the date
you specified as the planning start in the CTM profile). If no value has
been specified here, CTM takes into account the PP/DS Horizon in the
planning version.
Use in PP/DS
If you do not enter any value for the PP/DS horizon or if you enter the
duration '0', the system automatically uses the SNP production horizon as
the PP/DS horizon. Therefore, the PP/DS horizon is as long as the SNP
production horizon. This means the planning intervals for SNP and PP/DS
are sequenced with no gaps or overlaps.