Agenda
Implementation Approach Phase Wise
Technical Process Flow
Functional Process Summary P/L
Detailed Evaluation P/L
Technical Evaluation Integration (SAP & Cognos)
Implementation Approach
Phase I : Custom Development of P & L and Revenue Format
28 Man Days
5 Man Days
BBP/FS Sign
of
15 Man Days
Realizati
on
Scope
Consolidated* P&L format
month wise
All feasible data(Finance & Non
Finance) will be built in
revenue report from FI & SD
5 Man Days
Unit
Testing
2 Man Days
UAT
1 Man Day
Go Live
Phase I
Assumptions
Common Cost Bifurcation is
outside SAP and uploaded
manually
Payroll Data will be manual
upload as followed currently
Implementation Approach
Phase II :Automation of Manual Common Cost Allocation Cycles
32 Man Days
5 Man Days
7 Man Days
BBP Sign of
Realizati
on
5 Man Days
Unit
Testing
10 Man Days
UAT
5 Man Days
Go Live
Phase II
Scope
Project wise P&L will be avl. for
direct / indirect cost bookings in
FI
Assumptions
Statistical keys to be finalized
and entered before running the
allocation cycle
Non Financial
Data (Like Seats,
FTE etc:) via BDC
Upload in Z Table
Preceda
Payroll Data
via
Flat File BDC
Upload
FICO
SD
Account
Determination
Configuration
ABAP Development
(Custom Tables)
Allocation Cycle
Intra
Compa
ny
Common
Cost
Report Output
1) P & L
2) Revenue
** - Australia is not on SAP HCM platform and hence the HCM data will be populated via an excel upload from legacy system
Revenue
a
a
Unidentified
No Changes Required
Facility Cost
Admin Overheads
Local SGA
Corporate SGA
Taxation
a
6
Revenue
Data to be maintained in the SAP tables to be Upload of all data in SAP for the same to be
pulled in the MIS
maintained in the tables
* Project Allocation strategies/accounting flows to be confirmed with business for each cost line of P/L.
Technical Architecture
SAP<>CSV Flat
File<> TM 1
Pros
Quick Deployment
SAP<>SQL
Server<> TM 1
-
Faster Deployment
Reconciliation is
system driven
Track and Trace avl
SAP<>SAP
BI<> TM 1
-
Cons
Preferenc
e
Manual in nature
File Format Verification
is mandatory
Transaction Reversals
& Accounting are time
consuming
Unstable Environment
No Track and Trace
Duplicate Data Storage
in manual format
Least Preferred
File Format
verification is
mandatory
Duplicate Data
Storage apart from
SAP
Best Option
Stable
Environment
Real time
reconciliation
possible
Real time track
and trace
Implementation
Lead time is high
TCO is higher
compared to
other two
options
Recommended
Annexures
10
11
12
Project Charter
Project Name
(Description)
Project Sponsor
Business Project
Leader
MIS Automation in SAP & Integration of Actuals to Cognos for Variance Reporting
CM Sharma
Project Champion
Reena Shah
Mandeep Singh
Landscape
Problem Statement
Goal Statement
across Aegis
Standardization of processes
Higher reliability and controllership with enhanced
compliance.
Project Scope
In-scope: All Aegis Geos which are in Cognos TM-1 for Budgeting Cycle. Aegis Geos which are in SAP will follow the
process defined on integration of Cognos / SAP
Out-Scope: Any Transactional Data from SAP
Any other functionality /module & custom reports if any required by business which are not a part of the BBP
13
Project Resourcing
Project Leader
Team Member Name
Paresh Pitroda
Swati Shirgaonkar
Navneet Goyal
Sandeep Verma
Project Milestones
Project
Start Date:
Role
Enter Start
Date
Target
End Date
<MS1>
Enter MS Date
<MS2>
Enter MS Date
<MS3>
Enter MS Date
<MS4>
Enter MS Date
Project Category
SAP Financial Implementation
Project
End Date:
Actual
End Date
June 2013
Status
Project Methodology
Business
Transformation
14
Project Milestones
DESIGN PHASE
PHASE
- Technical Setups &
Configs
- Unit Testing
- User Acceptance test
GO LIVE PHASE
Data Migration /
Cleansing
Parallel run
Handover to Operations
Team
Go live
15
Project Team
16
Level
2
Level 1
Executive
Steering
Committee
Project
Management
Office
PMO
Level
3
Project Team
Steering
Committee
Fortnightly Meetings
Review of Progress against Plan
Project Issues Resolution
Mentoring to Functional Teams
Communication to stakeholders
Mandeep Singh
CM Sharma
Saugata Basu
Purushothaman
Paresh Pitroda
Swati Shirgaonkar
Reena Shah
Purva Oka
PMO Team
Functional , IT ,
Business and
Accounting Team