PLANNING AND

MONITORING
PROCUREMENT PROJECTS

PROCUREMENT PLANNING
Philippine Procurement Paradigm
Legal Basis
Importance/Advantages

Philippine Procurement
Paradigm
HOPE

Assess

BAC
BAC Sec

Review studies
Consolidate into APP
Decide procurement
method
Approve APP
Determine readiness

Post/Advertise
opportunity
Open and evaluate
bids
Post-qualify
Award and enter into
contract

Selection

HOPE
BAC
TWG

Budget

BAC Sec

End User

End User

Identify

NEEDS

Cost-benefit analysis
Feasibility study
Market study
PPMP

Oversee
implementation
Inspect and accept
deliveries
Release payment

Implement

SATISFACTIO
N

A
GOAL
without
a PLAN
is
simply
a wish

Legal Basis

All procurement should be meticulously and


judiciously planned by the procuring entity (PE)
(Section 7.1 IRR of R.A. 9184)

Only procurement projects considered crucial to


the efficient discharge of governmental functions
shall be included in the Annual Procurement Plan
(APP).
Included in the approved GAA
In line with the priority programs of the
GOCC

Legal Basis

NO
procurement
shall
be
undertaken
unless
it
is
in
accordance with the approved
annual procurement plan of the
procuring entity.
(Section 7.2 IRR of R.A. 9184)

Legal Basis

End-user units or Project Management Office


(PMO) shall prepare Project Procurement
Management Plan (PPMP) for their programs,
activities, and projects (PAPs). (Section 7.3.2)

Budget Office evaluates PPMPs and includes in


budget proposal for HOPE approval. (Section
7.3.3)

BAC Secretariat reviews and consolidates PPMPs


approved by the budget office into a proposed
APP. (Section 7.3.4)

PROCUREMENT PLANNING

Involves identifying which


project/program/activity needs of the
procuring entity can best be met by
procuring products or services. It includes
deciding:

Whether to procure

What to procure

How to procure

Where to procure

How much to procure

When to procure

PROCUREMENT PLANNING
Advantages

Effective and efficient achievement of project


goal.

Precludes
occasions
for
unnecessary
government purchases and circumventions of
the prescribed procurement procedures, such as

advance deliveries,
suki system, or
unwarranted resort to alternative methods
procurement (AMP).

PROCUREMENT PLANNING

Done within budgetary context reflecting the


Procuring Entity (PEs) priorities and objectives
for the budget period.

It
is
the
governments
fiduciary
responsibility to protect the taxpayers
interests and to safeguard the resources
allotted to each department.

PROCUREMENT PLANNING

The following competencies are required:

knowledge of the items to be procured


accounting,
warranty and contract laws, and
scheduling.

PREPARATION OF THE
PROJECT PROCUREMENT
MANAGEMENT PLAN
Procedures and Components of the
PPMP
Legal Basis
Importance/Advantages
12

PROJECT PROCUREMENT
MANAGEMENT PLAN
Shall be prepared by the
PMO/End-user Units
Serves as a guide
document in procurement
and contract
implementation process.
It is a vital reference in
procurement monitoring
Important tool in resource
and financial management
13

PROJECT PROCUREMENT
MANAGEMENT PLAN

When is the PPMP prepared?


PPMP is prepared simultaneously with the budget
proposal

Why is the PPMP prepared?


PPMP is important in determining and projecting
the quantity and quality of the expected outputs of
the PAPs.

14

Program / Project / Activity


Structure
PROGRAM
homogenous group of activities necessary for
the performance of a MAJOR PURPOSE for
w/c the PE is established, for basic
maintenance of the PEs administrative
operations or for the provision of staff
support to the PEs administrative operations,
or PEs line functions.

Program /Project/ Activity


Structure
PROJECT
special undertaking w/c is carried out w/in a definite
time frame and which is intended to result in some
pre-determined measure of goods and services.

ACTIVITY
work process which is designed to contribute to the
accomplishment of specific objectives and to the
implementation of a program or project.

PROJECT PROCUREMENT
MANAGEMENT PLAN
Project Procurement Management Plan
Info whether contracted out/by admin/consigned

Contents

Name/Title and General Description of the Project


Extent/Size of Contract Scopes/Packages
Type and Objective of Contract
Procurement Method
Time Schedule / Procurement Milestones
Estimated Budget for the Contract

18

The Project Procurement Management Plan (PPMP)

Column 1: CODE

PROJECT PROCUREMENT
MANAGEMENT PLAN

CODE serves as reference number for projectspecific procurement

OPS1-001
Office code Offices under the
Office of the Planning Service
Office code Division under the
OPS

Chronological order of Proc


Project

Indicate Code in the Authority to Procure


20

9/5/16

PROJECT PROCUREMENT
MANAGEMENT PLAN
OFFICE OF THE PLANNING SERVICE
Code

OPS

OPS1

Planning and Programming Division

OPS2

Research and Statistics Division

OPS3

Project Development and Evaluation Division

OPS4

Physical Facilities and Schools Engineering Division

Complete List of Code Assignment

21
9/5/16

The Project Procurement Management Plan (PPMP)

Col. 2: Title of
Program/Activity/Project

22
9/5/16

PROJECT PROCUREMENT
MANAGEMENT PLAN
Title of Program, Activity or Project

Procurement Project
CODE

TITLE OF PROGRAM, ACTIVITY OR PROJECT


CY 2013 School Furniture Program

OPS04001

Procurement of School Furniture for Public


Elementary and Secondary Schools under the
10% National Reserved Fund 2013

OPS04002

Procurement of School Furniture for Public


Elementary and Secondary Schools under the 10%
Unallocated Portion for Cooperatives formed by
PWD
23

9/5/16

PROJECT PROCUREMENT
MANAGEMENT PLAN
CODE

TITLE OF PROGRAM, ACTIVITY OR PROJECT


Procurment of Test Materials (Printing, Processing &
Forwarding Services)

NETRC001
NETRC002
NETRC003

Philippine Educational Placement Test (PEPT)


2014 National Career Assessment Examination
(NCAE)
2014 Educational Management Test

Should be based on the entries in the WFP


must be specific, clear and concise

The Project Procurement Management Plan (PPMP)

Col. 3: Type of Contract

PROJECT PROCUREMENT
MANAGEMENT PLAN

Types of Contract
A.

Goods

Items, supplies, materials & general


services, except consulting services
projects, which may be needed
transaction of public businesses or
pursuit of any government undertaking.

support
& infra
in the
in the

Includes, but is not limited to the following:


a)
equipment, furniture or stationary
b)
Construction materials
c)
personal property of any kind,
26
9/5/16

PROJECT PROCUREMENT
MANAGEMENT PLAN

Types of Contract
A. Goods

d)

non-personal or contractual services,


i. repair & maintenance of equipment/
furniture
ii. trucking, hauling, and courier
iii. janitorial, security and manpower
Can be classified into
1.
Expendable
2.
Non-Expendable
3.
General Support Services
27
4.
Related
or
Analogous
Services
9/5/16

PROJECT PROCUREMENT
MANAGEMENT PLAN

Types of Contract - Goods

9/5/16

Related or analogous services shall include, but not


limited to the following:
a) lease or purchase of office space
b) media advertisements
c) health maintenance services
d) other services essential to the operation of the
procuring entity
e) rental of venues and facilities
f) catering services
g) lease of computers, copiers and other
28
information technology equipment

Common Use Supplies and Equipment

All ordinary and regular office supplies and equipment


shall be procured from DBM-Procurement Service

Inventory Items
Non-common use/non-inventory supplies
To be included in the Annual Procurement Plan for
Common-use Office Supplies and Equipment (APPCSE), and included under the PPMP of Property
Division (PD).
Procurement of items not available at DBM-PS, to be
undertaken by the BAC, subject to a certification issued
by PD that item is not available at DBM-PS and
included in the APP-CSE.
29

Annual Procurement Plan for Common Use Supplies and


Equipment (APP-CSE)

Letter of Instructions 755 Series of 1978, Executive Order No.


359 Series of 1989 and Administrative Order No. 17 Series of
2011,
implementation of a government wide integrated procurement
system for supplies, materials and other items needed by the
government by the Procurement Service.

Department of Budget and Management Circular No. 2011-

06
and 2011-6A,
directs the preparation and submission of the procuring entitys
(PEs) Annual Procurement Plan for Common Use Supplies and
Equipment (APP-CSE), consistent with the objective of
strengthening the service delivery of the DBM-Procurement
Service.
DBM CL No. 2013-14, Nov. 29, 2013

30

B. Infrastructure Projects
Includes the following

Construction
Improvement
Rehabilitation
Demolition
Repair
Restoration
Maintenance

Roads and bridges/ Railways


Airports and seaports
Communication facilities
Civil works components of IT projects
Irrigation/ Water Supply
Flood control and drainage/ Sanitation
Sewerage and solid waste management systems
Shore protection
Energy/power and electrification facilities
Buildings (National, School, Hospital)
Other related construction projects

34

PROJECT PROCUREMENT
MANAGEMENT PLAN
C. Consulting Services (CS)
- services requiring adequate external technical and
professional expertise beyond the capability and/or
capacity of the agency to undertake

Advisory and Review Services


Pre-investment and Feasibility Studies
Design (For Infra Projects)
Construction Supervision
Management and Related Services
Other technical services or special studies

35

The Project Procurement Management Plan (PPMP)

Col. 4: Procurement Method

PROCUREMENT
METHODS

General Rule: Public Bidding

APP provides sufficient lead


time for bidding

Resort to Alternative Methods


allowed
Highly exceptional cases

To promote economy and


efficiency

Justified by conditions specified


in IRR

Recommended by BAC

Approved By HOPE

Bidding Process for


of
Goods/InfraDistribution
Bid Docs
Advertise/ Post
Invitation to Bid

Bid Submission

Bid Evaluation

Opening of
Technical Proposal
(incl. eligibility docs)

Post-qualification

Contract Signing

3 months

Pre-Bid
Conference

Opening of
Financial Proposal

Issuance of NOA

Issuance of
NTP

Bidding Process for Consulting Services


Quality-Based
Evaluation

PreProcurement
Conference

from 1st day of


posting

not to exceed 20 c.d.

Opening of
Submission
Eligibility
of
Envelope
Eligibility
and
Requirements
Eligibility
Check

Issue
Eligibility
Requirements

Advertisement/Posting
7 c.d.

Shortlisting HOPE Approval

Submission of bid: Maximum 75 c.d. from last day of posting

Deadline for
Submission
of
Proposals
1 c.d.

Opening of
Technical
Proposal
& Preliminary
Examination

Technical Proposal
Evaluation
& Ranking
not more than 21 c.d.
+ 2 c.d. for HOPE approval
of ranking

Pre-Bid
Conference

Issue Bidding
Documents

at least 12 c.d.
before bid opening

from issuance of LIB

Notification for
Opening of
Financial
Proposal and
Negotiation w/
First-in-Rank
3 c.d. from HOPE approval

10 c.d. <

3 c.d. from notice

Negotiation

Submission
of Additional
Requirements

Award of
Contract

Post-qualification
7 c.d.

Bidding Process for Consulting Services


Quality-Cost Based
Evaluation
PreProcurement
Conference

from 1st day


of posting

not to exceed 20 c.d.

Opening of
Submission
Eligibility
of
Envelope
Eligibility
and
Requirements Eligibility
Check

Issue
Eligibility
Requirements

Advertisement/Posting
7 c.d.

Shortlisting HOPE Approval

Submission of bid: Maximum 75 c.d. from last day of posting

Deadline for
Submission
of
Proposals
1 c.d.

Opening of
Technical
Proposal
& Preliminary
Examination

Technical Proposal
Evaluation & Ranking
Notification & Opening
of Financial
Proposal & Ranking
not more than 21 c.d. + 2 c.d
for HOPE approval of HRB

Pre-Bid
Conference

Issue Bidding
Documents

at least 12 c.d.
before bid opening

from issuance of LIB

3 c.d. from HOPE approval

Notification for
Negotiation

10 c.d. <

3 c.d. from notice

Negotiation

Submission
of Additional
Requirements

Award of
Contract

Post-qualification
7 c.d.

PROCUREMENT
METHODS

5 Alternative Methods of
Procurement:

Limited Source Bidding

Direct Contracting

Repeat Order

Shopping

Negotiated Procurement

The Project Procurement Management Plan (PPMP)

Col. 5 & 6: Estimated Budget


&
Source of Funds

The Project Procurement Management Plan (PPMP)

Columns 7 to 18: Schedule/Milestones of


Activities
January to December
INCLUDE DATE OF PRE-PROCUREMENT
CONFERENCE
(at least 15 c.d. prior to advertisement )

43
9/5/16

Procurement Timelines for


Earliest Possible Time
Goods
Advertisement/Posting of ITB

Issuance and availability of bid


docs
Pre-bid Conference
Submission/Opening of Bids
Bid Evaluation
Post-qualification

19
12
1
1
1

BAC Recom. Approval/NOA


Issuance

Contract Preparation and


Signing

Approval by Higher Authority

Issuance of NTP

TOTAL TIME

28 calendar days

Procurement Timelines for


Latest Possible Time
Goods
Advertisement/Posting of
ITB
Issuance/availability of bid
docs
Pre-bid Conference
Submission/Opening of
Bids
Bid Evaluation
Post-qualification
Approval of BAC Recom.
For Award/Issuance of NOA
Contract Prep. and Signing

7
52
12 30
1
7
30
7
10

Approval by Higher
Authority

15

Issuance of NTP
9/5/16

3
45

Procurement Timelines
Timelines for the Procurement of Infrastructure Projects
with an ABC of above Php. 50 Million (Annex C)
Latest Allowable Time

Procurement Timelines
Timelines for the Bidding Process of Infrastructure
Projects with an ABC of Php. 50 Million and below
(Annex C) Latest Allowable Time

Procurement Timelines
Timelines for the Bidding Process of Infrastructure
Projects (Annex C) Earliest Possible Time

Procurement Timelines for


Earliest Possible Time
Consulting
Advertisement/Posting of REI

Eligibility Check and Shortlisting


Issuance and availability of bid
docs
Pre-bid Conference
Submission/Opening of Bids
Bid Evaluation/Approval of
ranking
Notification for Negotiation
Negotiation
Post-qualification
BAC Recom. Approval/NOA
Issuance
Contract Preparation and
Signing

3
23
12
1
2
1
1
1
2
2

Procurement Timelines
Latest Possible Time
Advertisement/Posting of
REI
Eligibility Check and
Shortlisting
Issuance/availability of bid
docs
Pre-bid Conference
Submission/Opening of
Bids
Bid Evaluation/Ranking
Approvl
Notification for Negotiation
Negotiation
Post-qualification
Approval of BAC
Recom./Issuance of NOA
Contract9/5/16
Prep. and Signing

7
20
82
12
1
23
3
10
30
7
50
10

http://www.gppb.gov.ph/

The Project Procurement Management Plan (PPMP)

NOTE: Technical Specifications, Scope


of Work, or Terms of Reference for
each Item/Project shall be submitted as
part of the Authorities to Procure.

PROCUREMENT PLANNING

PPMP is transformed into Bidding Documents


End-user and TWG provides BAC Secretariat all
the necessary documents and information
relative to the procurement request

Authority to Procure with budget allotment


(Purchase Request or Requisition Voucher)
Market Analysis, containing the specification
of the items and estimated cost,
validated/analyzed by TWG, if any
Clearance or recommendation from Clearing
House and Justification

PREPARATION OF THE
ANNUAL PROCUREMENT
PLAN
Procedures and Factors to Consider in
Developing the APP
Components of the APP
Revision/Updates
55

ANNUAL PROCUREMENT
What is an APP? PLAN

APP is the document that consolidates the various


PPMPs submitted by the various PEs end-user
units/PMOs.

Who prepares the APP?


APP is prepared by the BAC, through the BAC
Secretariat

Who approves the APP?


APP should be approved by the HOPE or its duly
authorized 2nd ranking official

56

Preparation of APP

APP

Budget Office

End-User Unit

Submit to
Budget
Office for
evaluation
Prepare
Project
Procurement
Management
Plan (PPMP)

Submit
Budget
Proposal to
HOPE

Upon
approval of
HOPE, Budget
Office will
forward
PPMPs to
BAC
Secretariat for
Consolidation
and Review

When GAA,
Corporate
Budget or
Appropriation
Ordinance
becomes final,
PPMPs will be
finalized and
submitted to
BAC Secretariat
for
consolidation
and approval of
the HOPE.

BAC Secretariat

ANNUAL PROCUREMENT
PLAN
Factors to consider
in developing an APP?

Inclusion of all procurement activities planned


for the year;
Include provisions for a lump sum to cover
foreseeable
emergencies
or
contingencies
usually indicated by historical records;
Scheduling of procurement activities in the APP
should be done in such a manner that the BAC
and the other offices/units involved in the
procurement process in the procuring entity are
able to efficiently manage the conduct of
procurement transactions.

58

ANNUAL PROCUREMENT
How is the APP prepared
PLAN & maintained?

APP should be maintained and updated


regularly

In the consolidation of PPMPs, BAC may adopt


a strategy through which similar items of
procurement
are
packaged
into
one
procurement undertaking and under a single
PPMP, in which the original PPMPs shall be
consolidated and revised.

A review and updating of the individual PPMPs


and the APP shall be done regularly, at least
once every 6 mos. or as often as necessary.

Revisions on APP
End-user Unit
BAC Secretariat
HOPE

Update PPMP

Consolidate
PPMP to APP

Approve
Supplemental
APP

Annual Procurement Plan


(APP)

APP & PPMP


Upon confirmation of
availability of budget,
BAC Secretariat will
consolidate information
from PPMP to the APP
Similar projects shall be
consolidated into one
(1) entry in the APP

APP & PPMP

Procurement Delivery Schedule shall be as is with PPMP


However, other procurement activity schedules shall be merged to take
advantage of volume discounts.

APP & PPMP


Source funds shall
be identified.
Similar items with
different source of
funds shall be
separate entries
For items in the
PPMP that were
consolidated, the
budget shall be
totaled

TIPS IN CONSOLIDATING
PPMPs INTO AN APP AND
COA GAP CHECKLIST

65

Tips in consolidating PPMPs


1.

2.

3.

All procurement shall be separated whether


goods, civil works or consulting.
Civil works or consulting services are usually
distinct entries in the APP, unless PE finds merit
in merging infrastructure project scopes (civil
works) or deliverables (consultants)
Goods procurement can be separated into three
categories: common-use supplies (CSE) for the
Procurement Service (PS), common-use supplies
(non-PS), other goods procurement

Tips in consolidating PPMPs


4.

5.

6.

7.

All CSE whether for procurement from PS or not


shall be consolidated into an APP-CSE which
shall be submitted to the Procurement Service
For the APP, CSE shall be separated whether to
be bought from the PS and CSE which shall be
bought outside the PS
All partitions shall again be separated into mode
of procurement (public bidding or alternative
methods)
All entries can then be grouped by source of
funds

COA GAP Checklist


3.2. Annual Procurement Plan (APP) the requisite
document that the agency must prepare to reflect
the entire procurement activity (i.e., goods,
services, civil works to be procured) that it plans
to undertake within the calendar year. This
document contains the following information:
3.2.1.
3.2.2.
3.2.3.
3.2.4.
3.2.5.
3.2.6.
3.2.7.

Name of the procurement program/project;


Project management office or end-user unit;
General description of the procurement;
Procurement method to be adopted;
Time schedule for each procurement activity;
Source of fund; and
Approved Budget for the Contract.

COA GAP Checklist


To verify if the procuring entity has an Annual Procurement Plan (APP)
2. To verify if the APP is approved by the HOPE or by a second-ranking
official designated by the HOPE to act on his behalf
3. To verify if the APP contains the following information:
a. name of the procurement program/ project;
b. project management office or end-user unit;
c. general description of the procurement;
d. procurement method to be adopted;
e. time schedule for each procurement activity;
f. source of fund;
g. approved budget for the contract.
4. To verify if the APP is supported by PPMPs prepared by the respective
end-user units
5. To verify if the items in the approved APP were included in the PPMPs
6. To verify if the APP matches the budget per GAA, corporate budget,
appropriation ordinance, as the case may be
1.

Submission/Posting Requirements

In preparing the APP, use the GPPB prescribed


format

Post a copy of the APP in the PEs website and


the On-Line Monitoring Evaluation System
(OMES) in the GPPB website

www.philgeps.net philgeps website


www.gppb.gov.ph gppb website

70

PROCUREMENT
MONITORING
Procurement Monitoring Report
Procedures, Timelines and Other
Considerations for Developing a
Procurement Monitoring Report
Components of a Procurement
Monitoring Report
Legal Basis
Importance/Advantages
71

PROCUREMENT MONITORING
What is Monitoring?
Tracking of inputs, activities, outputs, and
outcomes of the procurement activity; and
Tracking results of current operations on a
regular basis.

PROCUREMENT MONITORING

What is a PMR?
PMR is the document that reflects all of the
procurement activities undertaken by the
procuring entity, whether completed or on-going

Who prepares the PMR?


PMR is prepared by the BAC, through the BAC
Secretariat

Who approves the PMR?


PMR shall be approved by the HOPE & submitted
to the GPPB.

73

PROCUREMENT MONITORING

What does the PMR cover?


PMR shall cover all procurement activities specified
in the APP, whether on-going and completed from
holding of the pre-procurement conference to the
issuance of the notice of award and approval of
the contract, including the actual time for each
major procurement activity.

When will the PMR be submitted?


After HOPE approval, the PMR shall be submitted
to the GPPB in printed & electronic format w/in 14
cd after the end of each semester.

74

PROCUREMENT MONITORING
Why Monitor?

Compliance to R.A. 9184 and its IRR

Performance
Efficiency
Effectiveness

Aid GPPB in crafting policies that address


weaknesses and uphold strengths of the
Philippine Procurement System

Proc. Monitoring Report

PMR Project Description &


Mode of Procurement
These are the projects
in the APP that were
procured in the year.
Ongoing projects shall
still be included.
Reminders:
1. It is advised that the
PAP code from the
APP shall be the same
PAP code in the PMR.
2. Mode of procurement
in the APP should be
the same in the PMR

PMR Proc. Schedule

While it is not prescribed that the procurement schedule the APP


should match the procurement schedule in the PMR, a comparison
of the two may indicate the effectiveness of the planning activity.

PMR Budget/Contract Cost


This portion shows the
difference (if any) of
the ABC and the
contract amount and
shall be a good
indicator on capability
of the entity in setting
of the ABC amount
An additional column
should be added for
the winning bidder.

PMR - Observers

As mandated in Section 13 of the IRR, Observers shall be


invited in all stages of procurement.
This section of the PMR monitors the compliance of procuring
entities to this provision.

COA GAP Checklist


1. To verify if the BAC:
a. prepared a PMR in the GPPB prescribed form;
b. covering all procurement activities specified in
the APP, whether on-going and completed, from
the holding of the pre-procurement conference
to the issuance of the notice of award and the
approval of the contract, including the standard
and actual time for each major procurement
activity;
c. submitted the monitoring report to the HOPE
for approval and submission to the GPPB in
printed and electronic format within 14 days
after the end of each semester

COA GAP Checklist


2. To verify if the HOPE:
a. approved the Procurement Monitoring Report
and
b. submitted it to the GPPB in printed and
electronic format within 14 days after the end
of each semester
3. To verify if appropriate actions have been taken
by the HOPE in case of instances of
noncompliance committed by the BAC, BAC
TWG, BAC Secretariat and/or bidders
4. To verify what actions have been taken by the
GPPB in regard to instances of noncompliance

Submission/Posting Reqts

PMR
Submission to the GPPB (Section 12.2 of IRR of
RA 9184) and posting in the procuring entity's
website of its approved Procurement Monitoring
Report every semester, following the form and
format downloadable from the GPPB website
(Section 1.2 of the IRR of EO 662)

GPPB Website

PROCUREMENT MONITORING

Why is the PMR prepared?

Monitoring entails tracking of inputs, activities,


outputs, and outcomes of the procurement activity
Ex-post evaluation examines the project outcomes
and impacts. It is a determination of the benefits
derived from the project, the attainment of
specific targets for key indicators, and the
sustainability of the project.

84

PROCUREMENT MONITORING

Why is the PMR prepared?

It monitors the results of current operations on a


regular basis.
BAC shall ensure that the procuring entity abides
by the standards set forth under R.A. 9184 and its
IRR.

85

FACTORS TO CONSIDER IN
PREPARING TECHNICAL
SPECIFICATIONS AND
DETERMINING THE ABC
FOR THE PROCUREMENT
OF GOODS

86

Factors to Consider in Planning

1.

Nature of the Goods to be Procured.


Goods may be classified into different categories,
such as:
a.
Common-use supplies;
b.
Inventory items;
c.
Non-common use supplies (which may
include equipment or supplies that are
project-specific); or
d.
General Support Services or Other Related
and Analogous Services.

Factors to Consider in Planning

2.

Availability of the Goods or Services in the


Market.
.

Identification of the procurement method is


dependent on the supply market.

Goods that are universally available should be


procured through public bidding.

Factors to Consider in Planning

2.

Availability of the Goods or Services in the


Market.
.

Goods that are available seasonally, or to be


manufactured specially for the PE, would
require more intensive planning in terms of
timelines
for
procurement,
taking
into
consideration manufacturing lead time, e.g.
textbooks, school furniture.

Factors to Consider in Planning


3.

Obsolescence, operation, and maintenance


of equipment/non-consumable Goods.
In buying equipment, consider the operation
and maintenance requirements of the goods.
availability and cost of spare parts in the local
market,
If spare parts
and maintenance services
are not available locally, or, if available, are
very expensive, the PE may consider
buying,
instead,
the
substitute
or
equivalent product.

Factors to Consider in Planning

Skills required in operating and maintaining the


equipment, and similar considerations.

For high-technology items w/c cannot be


satisfactorily substituted by other products, PE
may
include
supply
of
spare
parts,
consumables and/or maintenance services for
a specified period of time, as part of the
contract package.

Factors to Consider in Planning

Obsolescence could also be a factor in deciding


whether to lease or to buy equipment.

It may be more economical to lease


equipment that are easily rendered
obsolete, like IT equipment.

Setting the technical specifications


PMO or end-user unit must consider the ff:
1.

Objectives of the project or the procurement


at hand,

Supply and Delivery;

Supply, Install and Training;

Procurement of Unit, cabling and


installation;

Servicing and Maintenance

Setting the technical specifications


1 (a) Goods: Supply only
Goods are supplied and delivered to
a designated place or site.
1 (b) Goods: Supply and install
Goods are supplied, delivered, installed, run,
and tested at a designated place or site.
1 (c) Goods: Supply, install and maintain
Goods are supplied, delivered, installed and
maintained at the designated place or site.

Evaluation and award per item


FINANCIAL PROPOSAL
(Item & Specifications)

Bidder 2

Bidder 1

Bidder 3

Refurbishment of
Conference
Room
1. 24-seater
Conference Table

199,244

188,044

190,153

2. 100 sq.m. Carpet

358,647

475,669

435,555

3. 50 pieces upholstered
chairs with arm rest
4. Ceiling mounted
Projector and
Interactive Board

180,000

204,000

170,000

1,266,186.38

No bid

No bid

Php1,624,833.38

Php188,044

Php170,000

Lowest calculated &


responsive bid for item
1

Lowest calculated &


responsive bid for item
3

Possible Contract
Award to 3 bidders

Lowest calculated &


responsive bid for items 2
&4

Setting the technical specifications

PMO or end-user unit must consider


the following:

Standards that should be met by the


goods in terms of

function,

performance,

environmental interface, and/or

design.

Functional Description
is the description of the functions for which the
Goods are to be utilized.
Example:

light bulb output = 315 lumens

voltage = 150V to 250V

Performance Description
refers to the manner that the Goods are
required to perform the functions expected of
them
Example:

light output = 750 lumens without flicker

efficacy = at least 50 lumens per watts

energy saving = up to 80% over


standard incandescent bulbs

Environmental Interface
refers to the environment in which the required
functions are to be performed at the desired level
Example:

Minimum starting temperature = 0C (32F)

Do not use in damp, water splashed areas

Not suitable for use with enclosed downlights

Not suitable for use with dimmers, electronic


switches or remote controls

Design
refers to the technical design of the goods being procured
Antique
Nostalgic

Heat
Lamp

Yellow
Bug

Twist
& Lock
Coil

Appliance
Ceiling
Fan

Decorative
Globe

Amusement
Light Bulb

3-way
Screwin

Standard
Colored
Party

Decorative
Chandelier

Medium
Base
Stringers

Air
Purifying

Reflector

S 14
Design

PictureExit

Nondimmable

Product Life
refers to the useful life of a product
Example:
average life = at least 6,000 hours

Setting the technical specifications

Engage services of technical experts/consultants,


if necessary.

Description should be clear and specific to avoid


confusion, facilitate evaluation and help Bidders
respond realistically and competitively to the PEs
requirements of without qualifying their bids.

Description should be generic and flexible, not


product-specific or seemingly tailored for a
particular
brand,
product,
contractor,
or
consultant, unless it involves intellectual property
rights or exclusively offered.

Setting the technical specifications

Specifications should require that all items,


materials and accessories are
1. New and unused,
2. Most recent or current models, and
3. include or incorporate all recent improvements
in design and materials unless otherwise
provided

Samples of specifications from previous similar


procurements are useful.

Care must be taken and ensure that specifications


are not restrictive.

Setting the technical specifications

Specifications must be prepared to permit the


widest possible competition and present a clear
statement
of
the
required
standards
of
workmanship, materials, and performance of the
goods and services to be procured.
1. Production/delivery schedule,
2. Manpower requirements, and
3. After-sales service/parts

Standardize General Technical Specifications and


incorporate them in a separate subsection
depending on the goods complexity and the
repetitiveness of the type of procurement

Setting the technical specifications

Conduct a market survey


industry developments or standards, product
or service standards specified by the
authorized government entity like the Bureau
of Product Standards, ISO9000 or similar local
or international bodies.
For products where there are no specified
Philippine standards, the standards of the
country of origin or other international body
may be considered.
Product brochures, technical publications,
industry newsletters, the industry itself, as
well as the Internet, are good sources of
product information.

Setting the technical specifications

Conduct a market survey

study of the available products or services,


The conduct of a comparative study of the
options available in the market and their
relevance to the requirements of the Project is
highly recommended.

Setting the technical specifications

Where appropriate, drawings, including site


plans as required, may be furnished by the PE
with the Bidding Documents.
Similarly, the
Supplier may be requested to provide drawings
or samples either with its Bid or for prior review
by the Procuring Entity during contract
execution.

Determine the ABC

ABC refers to the budget for the contract duly approved by


the HOPE, as provided for in the GAA, the corporate
budget for the contract approved by the governing board,
pursuant to E.O. No. 518, s.1979, in case of GOCCs and
GFIs (Section 5.b) and executive budget duly approved by
the local sanggunian, case of LGUs

ABC should not exceed approved budget.

Determine the ABC


Factors to consider in determining ABC:
1.

2.

3.

4.

Appropriation for the project or procurement;


The cost or market price of the product or
service itself;
Incidental expenses like freight, insurance,
taxes, installation costs, training costs, if
necessary, and cost of inspection;
The cost of money, to account for government
agencies usually buying on credit terms;

Determine the ABC


Factors to consider in determining ABC: (Cont.)
1.

2.

3.

Inflationary factor, since the planning phase is


usually done one year ahead of the actual
procurement date;
Quantities, considering that buying in bulk
usually means lower unit prices; and
The supply of spare parts and/or maintenance
services, if these are part of the contract
package.

Packaging the Contract

Most common types of contracts provide for payments on


the basis of a lump sum, unit price, or combinations thereof.

Size and scope of individual contracts will depend on the


magnitude, nature, and location of the project, for example:

1.

Projects requiring a variety of goods and works, separate


contracts may be awarded for the supply and/or
installation of different items

2.

Project requiring similar but separate items of equipment


or works, bids may be invited under alternative contract
options that would attract the interest of both small and
large firms, which could be allowed, at their option, to
bid for individual contracts (slices/items) or for a group
of similar contracts (package).

Packaging the Contract


Incidental Services

performance or supervision of on-site assembly and/or


startup of the supplied Goods;

furnishing of tools required for assembly and/or


maintenance of the supplied Goods;

furnishing of a detailed operations and maintenance


manual for the supplied Goods;

performance or supervision or maintenance and/or repair


of the supplied Goods, for a period of time agreed by the
parties; and

training of the Procuring Entitys personnel.

Packaging the Contract


Spare Parts

Spare parts required are included in the Contract Price.

Supplier shall carry sufficient inventories to assure exstock supply of consumable spares for the Goods for a
period of time.

Other spare parts and components may be supplied


through ordering agreement.

Ordering Agreement
GPPB Resolution 01-2012 dated 27 January 2012

Expands the application of Ordering Agreements to the


following:
Expendable and Non-expendable Goods
Services for Hotel Accomodation, Air Travel, and
Repair and Maintenance

APP shall indicate the types of items considered for inclusion


in the Order Agreement List (OAL)

OAL shall indicate: type of item, quantity, tech specs or scope


of service, estimated contract/item or service, total ABC/
product or services, and other appropriate info.

Ordering Agreement

PPMP

APP

Competitive
Bidding

Termination

Delivery
Order
Contract

Ordering
Agreement

Packaging the Contract


Packaging
The Supplier shall provide instruction on packaging of the Goods
to prevent damage or deterioration during transit to their final
destination.
Packaging case size and weights. Consider the remoteness of
the GOODS final destination and the absence of heavy handling
facilities at all points in transit.
Marking, and documentation. Inside and outside the packages,
including additional requirements, if any, as ordered by the PE.
Example: The outer packaging must be clearly marked on at least
four (4) sides the following:

Name of the Procuring Entity


Name of the Supplier
Contract Description
Final Destination
Gross weight
Any special lifting or handling instructions
Any relevant HAZCHEM classifications

PREPARING FOR THE


PROCUREMENT OF
INFRASTRUCTURE
PROJECTS

12

Preparing for Infra. Projects

For Infrastructure Projects, the APP shall


consider the appropriate timing/phasing of
related project activities such as engineering
design and acquisition of ROW to reduce/lower
project costs

Detailed Engineering

No bidding and award should be made unless the


detailed engineering investigations, surveys and
designs, including acquisition of ROW have been
carried out
Exception: design and build schemes

Preparing for Infra. Projects

Detailed Engineering work includes:


1.
Design standards in accordance with
appropriate standards and accepted detailed
engineering practice
2.

3.

Field Surveys and Investigations include aerial,


hydrographic, topographic, hydrologic, subsurface, monumenting and other surveys, to be
carried out in accordance with the design
guidelines, criteria and standards adopted by the
agency
Contract plans incorporating site development
plan, plans and profile sheet, typical sections and
details, drainage details, structural plans, and
other details which may be required

Preparing for Infra. Projects


4.

5.

6.

7.

Quantities computed to a reasonable accuracy +/- 10%


Special provisions prepared for specific items of work or
methods of construction, measurement and payment, not
covered by standard construction and material specifications
adopted by the agency
Unit prices costs based on reasonable approved current
prices, projected over the proposed construction period
ABC projected movements in construction costs over the
period

8.

Bidding Documents

9.

Program of Work including estimates of the work, items,

Preparing for Infra. Projects

Factors to consider in Determining ABC:


1.

Cost or market price of the service

2.

Incidental expenses (taxes, training costs


if necessary, cost of inspection)

3.

Cost of money (for agencies that usually


buy on credit)

4.

Inflationary factor

PREPARING FOR
CONSULTING SERVICES

12

Preparing for Consulting

Factors to consider in Determining ABC:


1.

2.

3.

Cost or market price of the service


Cost of money (for agencies that usually buy
on credit)
Inflationary factor

Preparing for Consulting

Computing the Cost of Consultancy based on


cost to the consultant of actual services to be
rendered plus a reasonable level of management
fee. It consists of:
1. Remuneration Cost paid to the consultants
staff who are directly engaged in the service
per manning schedule. Consists of:
a. Basic Rates
b. Billing Factor or Multiplier
Overhead Cost
Social Charges
Management Fee

Preparing for the Procurement of


Consulting Services
2.

Reimbursable Costs includes all other


expenses associated with the execution of the
service. May be classified into:
a.

Based on Agreed Fixed Rates paid to the


staff and includes:

b.

Based on Actual Cost supported w/ invoices

c.

Housing Allowance
Per Diems
For foreign consultants misc. intl travel
expenses
International Travel, Domestic Travel,
Domestic Transportation, Communication
Expenses, Office/ Engineering Suppliers, Field
Office, Equipment Rental, Software Licenses,
Other necessary items

Contingency