Beruflich Dokumente
Kultur Dokumente
Project Management
Projects
JAN
FEB
MAR
APR
MAY
JUN
Build A
A Done
Build B
B Done
Build C
C Done
Build D
On time!
Ship
17-4
Project Management
How is it different?
17-5
Project Management
What are the Key Metrics
Time
Cost
Performance objectives
What are the Key Success Factors?
Top-down commitment
Having a capable project manager
Having time to plan
Careful tracking and control
Good communications
17-6
Project Management
What are the Major Administrative Issues?
Executive responsibilities
Project selection
Project manager selection
Organizational structure
Organizational alternatives
Manage within functional unit
Assign a coordinator
Use a matrix organization with a project leader
17-7
Project Management
17-8
Locate new
facilities
Interview staf
Hire and train
staf
Select and order
furniture
Remodel and
install phones
Move in/startup
17-9
Key Decisions
1710
Project Manager
Responsible for:
Work
Human Resources
Communications
Quality
Time
Costs
1711
Ethical Issues
1712
Concept
Planning
Execution
Management
Feasibility
Termination
1713
Figure 17.2
Project
Project X
X
Level 1
Level 2
Level 3
Level 4
1715
Developing a good work breakdown structure can require substantial time and
effort due to the uncertainties associated with a project and/or the size of the
project. Typically the portion of time spent on developing the work breakdown
structure greatly exceeds the time spent on actually developing a project schedule.
The importance of a work breakdown structure is underscored by the fact that the
activity list that results serves as the focal point for planning and doing the project.
Moreover, the work breakdown structure is the basis for developing time and cost
estimates.
Path
Critical path
The longest path; determines expected project duration
Critical activities
Activities on the critical path
Slack
Allowable slippage for path; the difference the length of
path and the length of critical path
AOA
Locate
facilities
4
Furniture
setup
2
Remodel
Interview
Move in
Hire and
train
1721
AON
Locate
facilities
Furniture
setup
Move in
Remodel
S
Interview
Hire and
train
4
1722
Critical activities
Slack activities
Limitations of PERT
Important activities may be omitted
4
Precedence relationships may not be correct
2
Estimates may include
a fudge factor
on critical path
142 weeks
3
17-25
Deterministic
Time estimates that are fairly certain
Computing Algorithm
Network activities Used to determine
Slack time
Critical path
Figure 17.5
Deterministic
time estimates
8 weeks
Example 1
6 weeks
4
3 weeks
Move in
11 weeks
4 weeks
1 week
9 weeks
3
17-28
Example 1 Solution
Critical Path
P a th
L e n g th
S la c k
(w e e k s )
1 -2 -3 -4 -5 -6
1 -2 -5 -6
1 -3 -5 -6
18
20
14
2
0
6
17-29
Probabilistic
Estimates of times that allow for variation
Probabilistic Estimates
Figure 17.8
Beta Distribution
to
Activity
start
Optimistic
time
tm
te
Most likely
time (mode)
tp
Pessimistic
time
17-31
Expected Time
te
to + 4tm +tp
6
te = expected time
to = optimistic time
tm = most likely time
tp = pessimistic time
17-32
Variance
(tp to)2
36
= variance
to = optimistic time
tp = pessimistic time
17-33
Example 5
Optimistic
time
Most likely
time
Pessimistic
time
2-4-6
b
3-4-5
d
3-5-7
e
5-7-9
f
4-6-8
h
17-34
4.00
b
4.00
d
5.0
e
7.0
f
6.0
h
17-35
Path Probabilities
Specified time Path mean
Z =
Path standard deviation
Z indicates how many standard deviations
of the path distribution the specified tine
is beyond the expected path duration.
17-36
Example 6
17
Weeks
1.00
a-b-c
Weeks
10.0
d-e-f
Weeks
16.0
1.00
g-h-i
Weeks
13.5
17-37
Figure 17.11
Total
cost
Expected indirect costs
Shorten
CRASH
Cumulative
cost of crashing
Shorten
Optimum
17-39
Example 7
17-40