Sie sind auf Seite 1von 76

11th Edition

Chapter 4

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Systems Design:
Process Costing
Chapter Four

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Similarities Between Job-Order and Process


Costing
Both
Both systems
systems assign
assign material,
material, labor
labor and
overhead
overhead costs
costs to
to products
products and
and they
they provide
provide aa
mechanism
mechanism for
for computing
computing unit
unit product
product cost.
cost.
Both
Both systems
systems use
use the
the same
same manufacturing
manufacturing
accounts,
accounts, including
including Manufacturing
Manufacturing Overhead,
Raw
Raw Materials,
Materials, Work
Work in
in Process,
Process, and
and Finished
Finished
Goods.
Goods.
The
The flow
flow of
of costs
costs through the manufacturing
accounts
accounts is
is basically
basically the same in both
both systems.
systems.
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Differences Between Job-Order and Process


Costing
Process
Process costing
costing is
is used
used when
when aa single
single product
product is
is produced
produced on
on
aa continuing
continuing basis
basis or
or for
for aa long
long period
period of
of time.
time. Job-order
Job-order
costing
costing is
is used
used when
when many
many different
different jobs
jobs are
are worked
worked on
on each
each
period.
period.
Process
Process costing
costing systems
systems accumulate
accumulate costs
costs by
by department.
department.
Job-order
Job-order costing
costing systems
systems accumulated
accumulated costs
costs by
by individual
individual
jobs.
jobs.
Process
Process costing
costing systems
systems use
use department
department production
production reports
reports to
to
accumulate
accumulate costs.
costs. Job-order
Job-order costing
costing systems
systems use
use job
job cost
cost
sheets
sheets to
to accumulate
accumulate costs.
costs.
Process
Process costing
costing systems
systems compute
compute unit
unit costs
costs by
by department.
department.
Job-order
Job-order costing
costing systems
systems compute
compute unit
unit costs
costs by
by job.
job.
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Quick Check

Process costing is used for products that are:


a. Different and produced continuously.
b.
c.

Similar and produced continuously.


Individual units produced to customer
specifications.
d. Purchased from vendors.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Quick Check

Process costing is used for products that are:


a. Different and produced continuously.
b.
c.

Similar and produced continuously.


Individual units produced to customer
specifications.
d. Purchased from vendors.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

What is a Processing Department?


Any location in an organization where materials,
labor or overhead are added to the product.
The activities performed in a processing
department are performed uniformly on all
units of production. Furthermore, the output of
a processing department must be
homogeneous.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Sequential vs. Parallel Processing


Sequential
Sequential processing
processing means
means that
that units
units
flow
flow in
in aa sequence
sequence from
from one
one
department
department to
to another.
another.
Parallel
Parallel processing
processing is
is used
used when
when
after
after aa point,
point, some
some units
units go
go through
through
different
different processing
processing departments
departments
than
than others.
others. For
For example,
example, aa
petroleum
petroleum refinery
refinery separates
separates crude
crude
oil
oil into
into products
products like
like gasoline,
gasoline, jet
jet
fuel,
fuel, and
and heating
heating oil.
oil.
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Comparing Job-Order
and Process Costing

Direct
Direct
Materials
Materials
Direct
Direct Labor
Labor

Manufacturing
Manufacturing
Overhead
Overhead
McGrawHill/Irwin

Work in
Process

Finished
Finished
Goods
Goods
Cost
Cost of
of
Goods
Goods
Sold
Sold
Copyright2006,TheMcGrawHillCompanies,Inc.

Comparing Job-Order
and Process Costing
Costs
Costs are
are traced
traced and
and
applied
applied to
to individual
individual
jobs
jobs in
in aa job-order
job-order
cost
cost system.
system.

Direct
Direct
Materials
Materials
Direct
Direct Labor
Labor

Manufacturing
Manufacturing
Overhead
Overhead
McGrawHill/Irwin

Jobs
Jobs

Finished
Finished
Goods
Goods
Cost
Cost of
of
Goods
Goods
Sold
Sold
Copyright2006,TheMcGrawHillCompanies,Inc.

Comparing Job-Order
and Process Costing

Direct
Direct
Materials
Materials
Direct
Direct Labor
Labor

Manufacturing
Manufacturing
Overhead
Overhead
McGrawHill/Irwin

Costs
Costs are
are traced
traced and
and
applied
applied to
to departments
departments
in
in aa process
process cost
cost
system.
system.
Processing
Processing
Department
Department

Finished
Finished
Goods
Goods
Cost
Cost of
of
Goods
Goods
Sold
Sold

Copyright2006,TheMcGrawHillCompanies,Inc.

T-Account and Journal Entry Views of Cost Flows

For purposes of this example,


assume there are two
processing departments
Departments A and B.
We will use T-accounts and
journal entries.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in T-account form)
Raw Materials
Direct
Materials

Work in Process
Department A
Direct
Materials

Work in Process
Department B
Direct
Materials

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in journal entry form)

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in T-account form)
Wages Payable
Direct
Labor

Work in Process
Department A
Direct
Materials
Direct
Labor

Work in Process
Department B
Direct
Materials
Direct
Labor

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing
(in journal entry form)

GENERAL JOURNAL
Date

Description

Post.
Ref.

Page 4
Debit

Work in Process - Department A

XXXXX

Work in Process - Department B

XXXXX

Salaries and Wages Payable

Credit

XXXXX

To record direct labor costs.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in T-account form)
Work in Process
Department A
Manufacturing
Overhead
Actual
Overhead

Overhead
Applied to
Work in
Process

Direct
Materials
Direct
Labor
Applied
Overhead

Work in Process
Department B
Direct
Materials
Direct
Labor
Applied
Overhead

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing
(In journal entry form)

GENERAL JOURNAL
Date

Description

Post.
Ref.

Page 4
Debit

Work in Process - Department A

XXXXX

Work in Process - Department B

XXXXX

Manufacturing Overhead

Credit

XXXXX

To apply overhead to departments.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in T-account form)
Work in Process
Department A
Direct
Transferred
Materials
to Dept. B
Direct
Labor
Applied
Overhead

McGrawHill/Irwin

Work in Process
Department B
Direct
Materials
Direct
Labor
Applied
Overhead
Transferred
from Dept. A

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing
(in journal entry form)

GENERAL JOURNAL
Date

Description
Work in Process - Department B
Work in Process - Department A

Post.
Ref.

Page 4
Debit

Credit

XXXXX
XXXXX

To record the transfer of goods from


Department A to Department B.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in T-account form)
Work in Process
Department B
Direct
Cost of
Materials
Goods
Direct
Manufactured
Labor
Applied
Overhead
Transferred
from Dept. A

McGrawHill/Irwin

Finished Goods
Cost of
Goods
Manufactured

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing
(in journal entry form)

GENERAL JOURNAL
Date

Description
Finished Goods
Work in Process - Department B

Post.
Ref.

Page 4
Debit

Credit

XXXXX
XXXXX

To record the completion of goods


and their transfer from Department B
to finished goods inventory.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Cost Flows


(in journal entry form)
Work in Process
Department B

Finished Goods

Direct
Cost of
Cost of
Cost of
Materials
Goods
Goods
Goods
Direct
Manufactured
Manufactured
Sold
Labor
Applied
Overhead
Transferred
Cost of Goods Sold
from Dept. A
Cost of
Goods
Sold
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing
(in journal entry form)

GENERAL JOURNAL
Date

Description
Accounts Receivable

Post.
Ref.

Page 4
Debit

Credit

XXXXX

Sales

XXXXX

To record sales on account.


Cost of Goods Sold
Finished Goods

XXXXX
XXXXX

To record cost of goods sold.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units of Production


Equivalent units are the product of the number of
partially completed units and the percentage
completion of those units.

We need to calculate equivalent units because a


department usually has some partially completed units
in its beginning and ending inventory.
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units The Basic Idea


Two half completed products are
equivalent to one completed product.

So,
So, 10,000
10,000 units
units 70%
70% complete
complete
are
are equivalent
equivalent to
to 7,000
7,000 complete
complete units.
units.
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Quick Check
For
For the
the current
current period,
period, Jones
Jones started
started 15,000
15,000
units
units and
and completed
completed 10,000
10,000 units,
units, leaving
leaving
5,000
5,000 units
units in process 30 percent complete.
How
How many
many equivalent
equivalent units
units of
of production
production did
did
Jones
Jones have
have for
for the
the period?
period?
a.
a. 10,000
10,000
b.
b. 11,500
11,500
c.
c. 13,500
13,500
d.
d. 15,000
15,000
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Quick Check
For
For the
the current
current period,
period, Jones
Jones started
started 15,000
15,000
units
units and
and completed
completed 10,000
10,000 units,
units, leaving
leaving
5,000
5,000 units
units in process 30 percent complete.
How
How many
many equivalent
equivalent units
units of
of production
production did
did
Jones
Jones have
have for
for the
the period?
period?
a.
a. 10,000
10,000
10,000 units + (5,000 units 0.30)
b.
b. 11,500
11,500
= 11,500 equivalent units
c.
c. 13,500
13,500
d.
d. 15,000
15,000
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Calculating Equivalent Units


Equivalent
Equivalent units
units can
can be
be calculated
calculated two
two
ways:
ways:

The
The First-In,
First-In, First-Out
First-Out Method
Method FIFO
FIFO is
is
covered
covered in
in the
the appendix
appendix to
to this
this chapter.
chapter.

The
The Weighted-Average
Weighted-Average Method
Method This
This

method
method will
will be
be covered
covered in
in the
the main
main portion
portion of
of the
the
chapter.
chapter.
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units of Production


Weighted-Average Method
The weighted-average method . . .
Makes no distinction between work done in prior or
current periods.
Blends together units and costs from prior and
current periods.
Cost per
equivalent

Costs for the period


Equivalent units of production
for the period

unit
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing and Direct Labor

Dollar Amount

Direct
Materials

Direct
Labor

Direct
Direct labor
labor costs
costs
may
may be
be small
small
in
in comparison
comparison to
to
Conversion
other
other product
product
costs
costs in
in process
process
cost
cost systems.
systems.

Type of Product Cost

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Process Costing and Direct Labor

Dollar Amount

Direct
Materials

Direct
Direct labor
labor costs
costs
may
be
small
may
be
small
Conversion
in
in comparison
comparison to
to
other
other product
product
costs
costs in
in process
process
cost
cost systems.
systems.

Type of Product Cost

Direct
Direct labor
labor and
and manufacturing
manufacturing overhead
overhead may
may be
be
combined
combined into
into one
one product
product cost
cost called
called conversion
conversion..
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example

Smith Company reported the following activity in


Department A for the month of June:
Percent Completed
Units
Work in process, June 1

300

Units started into production in June

6,000

Units completed and transferred out


of Department A during June

5,400

Work in process, June 30


McGrawHill/Irwin

900

Materials Conversion
40%

20%

60%

30%

Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example
The first step in calculating the equivalent units is
to identify the units completed and transferred
out of Department A in June (5,400 units)
Materials
Units completed and transferred
out of Department A in June

McGrawHill/Irwin

5,400

Conversion
5,400

Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example
The second step is to identify the equivalent units of
production in ending work in process with respect to
materials for the month (540 units) and add this to the
5,400 units from step one.
Materials
Units completed and transferred
out of Department A in June

5,400

Conversion
5,400

Work in process, June 30:


900 units 60%
Equivalent units of Production in
Department A during June
McGrawHill/Irwin

540

5,940
Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example
The third step is to identify the equivalent units of
production in ending work in process with respect to
conversion for the month (270 units) and add this to the
5,400 units from step one.
Materials
Units completed and transferred
out of Department A in June

5,400

Conversion
5,400

Work in process, June 30:


900 units 60%

540

900 units 30%


Equivalent units of Production in
Department A during June
McGrawHill/Irwin

270
5,940

5,670

Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example
Equivalent
Equivalent units
units of
of production
production always
always equals:
equals:
Units
Units completed
completed and
and transferred
transferred
++ Equivalent
Equivalent units
units remaining
remaining in
in work
work in
in process
process
Materials
Units completed and transferred
out of Department A in June

5,400

Conversion
5,400

Work in process, June 30:


900 units 60%

540

900 units 30%


Equivalent units of Production in
Department A during June
McGrawHill/Irwin

270
5,940

5,670

Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example

Materials
Materials
Beginning
Work in Process
300 Units
40% Complete

6,000 Units Started

5,100 Units Started


and Completed

5,400 Units Completed


540 Equivalent Units
5,940 Equivalent units
of production
McGrawHill/Irwin

Ending
Work in Process
900 Units
60% Complete

900 60%

Copyright2006,TheMcGrawHillCompanies,Inc.

Weighted-Average Example

Conversion
Conversion
Beginning
Work in Process
300 Units
20% Complete

6,000 Units Started

5,100 Units Started


and Completed

5,400 Units Completed


270 Equivalent Units
5,670 Equivalent units
of production
McGrawHill/Irwin

Ending
Work in Process
900 Units
30% Complete

900 30%

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Weighted-Average


Production Report

Section 1
Section 2

AA quantity
quantity schedule
schedule

showing
showing the
the flow
flow of
of units
units
and
and the
the computation
computation of
of
equivalent
equivalent units.
units.

AA computation
computation of
of

cost
cost per
per equivalent
equivalent unit.
unit.

Section 3
McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report
Production Report

Section 1
Section 2
Section 3
McGrawHill/Irwin

Cost
Cost Reconciliation
Reconciliation

section
section shows
shows the
the
reconciliation
reconciliation of
of all
all cost
cost
flows
flows into
into and
and out
out of
of the
the
department
department during
during the
the
period.
period.
Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example

Assume
Assume that
that Double
Double Diamond
Diamond Skis
Skis uses
uses the
the
weighted-average
weighted-average method
method of
of process
process costing
costing to
to
determine
determine unit
unit costs
costs in
in itit Shaping
Shaping and
and Milling
Milling
Department.
Department.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Work
Work in
in process,
process, May
May 1:
1: 200
200 units
units
Materials:
Materials: 55%
55% complete
complete
Conversion:
Conversion: 30%
30% complete
complete

9,600
9,600
5,575
5,575

Production
Production started
started during
during May
May
Production
Production completed
completed during
during May
May

5,000
5,000 units
units
4,800
4,800 units
units

Costs
Costs added
added to
to production
production in
in May
May
Materials
Materials cost
cost
Conversion
Conversion cost
cost

$$ 368,600
368,600
350,900
350,900

Work
Work in
in process,
process, May
May 31
31
Materials:
40%
Materials:
40% complete
complete
Conversion:
Conversion: 25%
25% complete
complete
McGrawHill/Irwin

$$

400
400 units
units

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step1: Prepare Quantity Schedule with Equivalent Units.
Units to be accounted for:
Work in process, May 1
Started into production
Total units

200
5,000
5,200
Equivalent units
Materials
Conversion

Units accounted for as follows:


Completed and transferred
Work in process, May 31

McGrawHill/Irwin

4,800
400

4,800

4,800

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step1: Prepare Quantity Schedule with Equivalent Units.
Units to be accounted for:
Work in process, May 1
Started into production
Total units

200
5,000
5,200
Equivalent units
Materials
Conversion

Units accounted for as follows:


Completed and transferred
Work in process, May 31
Materials 40% complete

4,800
400

4,800

160
5,200

McGrawHill/Irwin

4,800

4,960
Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step1: Prepare Quantity Schedule with Equivalent Units.
Units to be accounted for:
Work in process, May 1
Started into production
Total units

200
5,000
5,200
Equivalent units
Materials
Conversion

Units accounted for as follows:


Completed and transferred
Work in process, May 31
Materials 40% complete
Conversion 25% complete

4,800
400

4,800

160
5,200

McGrawHill/Irwin

4,800

4,960

100
4,900

Copyright2006,TheMcGrawHillCompanies,Inc.

Step 2: Calculating the Costs Per Equivalent


Unit
To calculate the cost per equivalent unit
for the period:
Cost per
equivalent

Costs for the period


Equivalent units of production
for the period

unit

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step 2: Compute the cost per equivalent unit.
Total
Cost
Cost to be accounted for:
Work in process, May 1
Costs added in the Shipping
and Milling Department
Total cost
Equivalent units

15,175

Materials

Conversion

9,600

5,575

719,500

368,600

350,900

$ 734,675

$ 378,200

$ 356,475

4,960

4,900

Cost per equivalent unit

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step 2: Compute the cost per equivalent unit.
Total
Cost
Cost to be accounted for:
Work in process, May 1
Costs added in the Shipping
and Milling Department
Total cost

15,175

Materials

Conversion

5,575

719,500

368,600

350,900

$ 734,675

$ 378,200

$ 356,475

4,960

4,900

Equivalent units
Cost per equivalent unit

9,600

76.25

$378,200 4,960 units = $76.25


McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step 2: Compute the cost per equivalent unit.
Total
Cost
Cost to be accounted for:
Work in process, May 1
Costs added in the Shipping
and Milling Department
Total cost
Equivalent units

15,175

Materials

Conversion

9,600

719,500

368,600

350,900

$ 734,675

$ 378,200

$ 356,475

4,960

4,900

Cost per equivalent unit


$ 76.25
Total cost per equivalent unit = $76.25 + $72.75 = $149.00

McGrawHill/Irwin

5,575

$356,475 4,900 units = $72.75

72.75

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step 3: Prepare a Cost Reconciliation
Total
Cost
Cost accounted for as follows:
Transferred out during May
Work in process, May 31:
Materials
Conversion

Equivalent Units
Materials Conversion
4,800

4,800

160
100

Total work in process, May 31


Total cost accounted for

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step 3: Prepare a Cost Reconciliation
4,800 units @ $149.00
Cost accounted for as follows:
Transferred out during May
Work in process, May 31:
Materials
Conversion

Total
Cost
$ 715,200

Equivalent Units
Materials Conversion
4,800

4,800

160
100

Total work in process, May 31


Total cost accounted for

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Production Report Example


Step 3: Prepare a Cost Reconciliation
160 units @ $76.25
Cost accounted for as follows:
Transferred out during May
Work in process, May 31:
Materials
Conversion
Total work in process, May 31
Total cost accounted for

McGrawHill/Irwin

Total
Cost

Equivalent Units
Materials
100
units @ Conversion
$72.75

$ 715,200

4,800

12,200
7,275

160

19,475
$ 734,675

4,800

100

All costs
accounted for

Copyright2006,TheMcGrawHillCompanies,Inc.

Operation Costing
Operation
Operation costing
costing is
is aa hybrid
hybrid of
of job-order
job-order
and
and process
process costing
costing because
because itit
possesses
possesses attributes
attributes of
of both
both approaches.
approaches.
Job-order
Costing

Operation Costing
(Products produced in batches)

Material
MaterialCosts
Costscharged
charged
to
tobatches
batchesas
asin
in
job-order
job-ordercosting.
costing.
McGrawHill/Irwin

Process
Costing

Conversion
Conversioncosts
costs
assigned
assignedto
tobatches
batches
as
asin
inprocess
processcosting.
costing.
Copyright2006,TheMcGrawHillCompanies,Inc.

FIFO Method

Appendix 4A

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

FIFO vs. Weighted-Average Method


The FIFO method (generally considered more
accurate that the weighted-average method)
differs from the weighted-average method in
two ways:
1. The computation of equivalent units.
2. The way in which the costs of beginning
inventory are treated in the cost
reconciliation report.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units FIFO Method


Lets revisit the Smith Company example.
Assume the following activity is reported in
Department A for the month of June:
Percent Completed
Units
Work in process, June 1

300

Units started into production in June

6,000

Units completed and transferred out


of Department A during June

5,400

Work in process, June 30


McGrawHill/Irwin

900

Materials Conversion
40%

20%

60%

30%

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units FIFO Method


Step 1:
1 Determine the number of units completed and
transferred out of Department A in June.
Percent Completed
Units
Work in process, June 1

300

Units started into production in June

6,000

Units completed and transferred out


of Department A during June

5,400

Work in process, June 30


McGrawHill/Irwin

900

Materials Conversion
40%

20%

60%

30%

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units FIFO Method


Step 2:
2 Add the equivalent units of production in ending
work in process inventory (540 units for material and 270
units for conversion) to the units completed and transferred
our during June.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units FIFO Method


Step 3:
3 Subtract the equivalent units in beginning work in process
inventory (120 units for materials and 60 units for conversion) from the
sum of the units completed and transferred out and the equivalent
units in ending work in process inventory.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units FIFO Method

Materials
Materials
Beginning
Work in Process
300 Units
40% Complete

McGrawHill/Irwin

6,000 Units Started

5,400 Units Started


and Completed

Ending
Work in Process
900 Units
60% Complete

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units FIFO Method

Conversion
Conversion
Beginning
Work in Process
300 Units
20% Complete

McGrawHill/Irwin

6,000 Units Started

5,400 Units Started


and Completed

Ending
Work in Process
900 Units
30% Complete

Copyright2006,TheMcGrawHillCompanies,Inc.

Equivalent Units: Weighted Average vs. FIFO


As shown below, the equivalent units in beginning inventory are
subtracted from the equivalent units of production per the weightedaverage method to obtain the equivalent units of production under
the FIFO method.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

The Production Report - FIFO Method


Lets revisit the Double Diamond Skis Shaping and Milling
Department for the Month of May to prepare our production report.
Work
Work in
in process,
process, May
May 1:
1: 200
200 units
units
Materials:
Materials: 55%
55% complete
complete
Conversion:
Conversion: 30%
30% complete
complete
Production
Production started
started during
during May
May
Production
Production completed
completed during
during May
May
Costs
Costs added
added to
to production
production in
in May
May
Materials
Materials cost
cost
Conversion
Conversion cost
cost
Work
Work in
in process,
process, May
May 31
31
Materials:
40%
Materials:
40% complete
complete
Conversion:
Conversion: 25%
25% complete
complete
McGrawHill/Irwin

$$ 9,600
9,600
5,575
5,575
$15,
$15, 175
175
5,000
5,000 units
units
4,800
4,800 units
units
$$ 368,600
368,600
350,900
350,900
400
400 units
units
Copyright2006,TheMcGrawHillCompanies,Inc.

The Production Report - FIFO Method


Step 1:
1 Prepare the quantity schedule and compute
equivalent units.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

The Production Report - FIFO Method


Step 2:
2 Calculate the equivalent units of material and conversion
that were transferred from beginning work in process to the next
department.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

The Production Report - FIFO Method


Step 3:
3 Determine the number of units started and
completed during the period.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

The Production Report - FIFO Method


Step 4:
4 Calculate the equivalent units of material and
conversion that are in ending work in process inventory.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

The Production Report - FIFO Method


Step 5:
5 Calculate the total equivalent units for
materials and conversion.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Cost per Equivalent Unit


Notice that the costs of beginning work in process
inventory of $15,175, is not broken down by
materials and conversion components

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Cost per Equivalent Unit


We divide the costs added in the Shipping and
Milling Department by the number of equivalent
unit for materials.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Cost per Equivalent Unit


We follow the same procedure for conversion and
add the two equivalent unit costs to get the total cost
per equivalent unit.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Cost Reconciliation
Step 1:
1 Calculate the total cost from beginning
inventory transferred to the next department.

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Cost Reconciliation
Step 2:
2 Calculate the cost of units started and
completed during the period.
4,600 units $148.50

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Cost Reconciliation
Step 3:
3 Calculate the costs in ending working in process
inventory and the sum of the cost accounted for.

McGrawHill/Irwin

All costs
accounted for
Copyright2006,TheMcGrawHillCompanies,Inc.

End of Chapter 4

McGrawHill/Irwin

Copyright2006,TheMcGrawHillCompanies,Inc.

Das könnte Ihnen auch gefallen