Agenda
Support Information
Test cases
Cluster unloaded and loaded
Market loaded
Acceptance KPIs
Access Fails
Drops
DL/UL Quality
Target
2.0 %
2.0 %
95 % 2 %
Call Setup
Time
95 % 6
sec
Value from
drive
Target
Access Fails
Drops
Green
2.5%
Green 2.5%
Yellow
5.0%
Yellow 5.0%
Red > 5.0%
Throughput (DL/UL)
Latency
R99 210/180 kbps
HS 600 kbps
Call Setup
Time
95 % 5
sec
Target
HS 120 ms
Value from
drive
GSM Voice
UMTS Cluster
Access Fails
Drops
DL/UL Quality
2.0 %
2.0 %
95 % 2 %
GSM or Better
GSM or Better
Better than
IRAT Off
Call Setup
Time
95 % 6
sec
95 % 6
sec
NA
NA
NA
NA
NA
NA
NA
NA
NA
GSM Voice
UMTS Market
Metric
Access Fails
Drops
Call Setup
Time
Target
X.X %
X.X %
X.X%
NA
NA
NA
Green GSM
Yellow > GSM
Red > UMTS
Target
Agenda
Support Information
Summary
Laptop 1
Device
Cluster
Unloaded Test
Cases
Type of Call
Mode
Comments
Up to 2 unloaded tests.
Scanner
Voice Short
Voice Long
DUAL
UMTS
UMTS
MS4
PS DL/UL 2MB
UMTS
PS R99 test
Device
Type of Call
Mode
Comments
MS1
Scanner
DUAL
MS2
Voice Short
UMTS
MS3
Voice Long
UMTS
1800sec duration
MS4
PS DL/UL 2MB
UMTS
MS1
Setup 1
MS2
MS3
Laptop 1
Setup 1
Cluster Loaded
Test Cases
Device
Type of Call
Mode
Comments
MS1
PS R99
UMTS
MS2
PS HSDPA
UMTS
Laptop 1
Late sites
Loaded Test
Cases
Setup 1
Device
Type of Call
Mode
Comments
MS1
Scanner
DUAL
MS2
Voice Short
UMTS
MS3
Voice Long
UMTS
1800sec duration
MS4
PS DL/UL 2MB
UMTS
PS R99 test
Summary
Setup 1
Device
Type of Call
Mode
Comments
MS1
Scanner
DUAL
MS2
Voice Long
DUAL
MS3
PS DL 10MB
DUAL
MS4
Idle
DUAL
Device
Type of Call
Mode
Comments
MS1
Scanner
DUAL
MS2
Voice Medium
UMTS
MS3
Voice Medium
DUAL
MS4
Voice Medium
GSM
Market Loaded
Test Cases
Laptop 1
Setup 2
Entry Criteria
At least 85% of the sites in cluster have been accepted
Sites are alarm free
Exit Criteria
KPIs have been met and reported including exclusion areas if applied
Full/provisional approval has been granted
10
11
Entry Criteria
All clusters in the market have been accepted
No crucial sites pending for integration
Sites are alarm free
Exit Criteria
KPIs have been met and reported
Full/provisional approval has been granted
12
Agenda
13
Support Information
13
14
Laptop 1
Device
MS1
Setup 1
MS2
MS3
MS4
15
Type of Call
Mode
Comments
Scanner
Voice Short
Voice Long
DUAL
UMTS
UMTS
PS DL/UL 2MB
UMTS
PS R99 test
Voice
PS R99
Quality (MS3)
DL Throughput (MS4)
UL Throughput (MS4)
Agenda
16
Support Information
16
17
Setup 1
Device
MS1
MS2
MS3
MS4
Type of Call
Scanner
Voice Short
Voice Long
PS DL/UL 2MB
Laptop 1
Mode
Comments
DUAL
Scanning both UMTS and GSM
UMTS
15sec duration and 10sec gap
UMTS
1800sec duration
UMTS
PS R99 test. The final drive will do
HSDPA DL of 10MB and no UL test
Voice
PS R99
HSDPA
Quality (MS3)
DL Throughput (MS4)
DL Throughput (MS4)
UL Throughput (MS4)
Notes:
1-HSDPA will be tested replacing R99 when HS capable UE is available for the last drive
18
Device
MS1
Setup 2
MS2
PS R99
HSDPA
Latency (MS2)
19
Agenda
20
Support Information
20
21
Device
MS1
MS2
MS3
Setup 1
MS4
Voice
IRAT HO Failure (MS2)
IRAT CC Failure (MS3)
IRAT CC Interruption Time (MS3)
Time spent in CM (MS2)
Number of CM activations versus IRAT
HO from UTRAN commands (MS2)
Idle mode phone service map (MS4)
22
Laptop 1
Setup 2
Device
Type of Call
Mode
Comments
MS1
Scanner
DUAL
MS2
Voice Medium
UMTS
MS3
Voice Medium
DUAL
MS4
Voice Medium
GSM
UMTS Only
GSM Only
23
Agenda
24
Support Information
24
6- Timeline
NOTES
If in any stage there is a justifiable requirement for an additional drive this needs to be approved by the UMTS
Market manager
Late site optimization will be executed if required. If the cluster is already passing the KPIs without the missing site
and integrating the site will delay the market drives a decision by the UMTS Market manager can be done to proceed
to market acceptance and integrate the site after the Market launch. If the site will help an exclusion area to improve
than it should be integrated into the cluster.
The timeline indicates areas where the stationary tests can be done, but it does not necessary implies that all the
days are required. These days can also use to troubleshoot small areas for example
Timeline
25
Cluster drive is more dense than market. The route should also cover part of the intercluster area.
Market drive is less dense but covers more area.
26
If the market drive route is divided in day routes, IRAT and stationary test can be done in parallel
in the rest of the Market area.
Free resources from cluster can be deploy for market mobile and stationary test
27