Beruflich Dokumente
Kultur Dokumente
TECHNIQUES: DISCOUNTED
CASH FLOW AND NONDISCOUNTED CASH FLOW
METHODS
TAIABUR RAHMAN
INTRODUCTION
CERTAINTY ASSUMPTION
Decision-making
PAYBACK PERIOD
The
Cost of Project
Payback Period
Annual Cash Inflows
(500)
150
Balance:
(500)
(500) (350)
(350) (200)
(200) (50)
(50) 100
100 250
250 400
400 550
550
700
700
CFt
Cumulative
PaybackL
-100
10
60
-100
-90
-30
2.4
80
0
50
PAYBACK-DECISION CRITERIA
PB-STRENGTHS
10
PB LIMITATIONS
NPV
NPV compares the value of a dollar today versus the
value of that same dollar in the future, after taking
inflation and return into account.
If the NPV of a prospective project is positive, then it
should be accepted. However, if it is negative, then the
project probably should be rejected because cash flows
are negative.
Present Value of all costs and benefits of a project.
Concept is similar to Intrinsic Value of a security but
subtracts of cost of project.
NPV= PV of Inflows- Initial Outlay (IO)
NPV =
CF1
(1+ k )
CF2
+
(1+ k )2
CFn
CF3
++
n IO
3
(1+
k
)
(1+ k )
A
(10,000.)
3,500
3,500
3,500
3,500
B
(10,000.)
500
500
4,600
10,000
k=10%
0
(10,000)
500
455
413
3,456
6,830
$11,154
500
4,600
NPV =
PV Benefits - PV Costs
= $11,154
- $10,000
= $1,154
10,000
Accept Project
since NPV > 0
21
Time
0
1
2
3
4
k=10%
0
(10,000)
NPV =
3,500
3,500
(1+ .1 )
3,500
3,500
(1+ .1)2
3,500
3,500
3,500
3,500
+
3
4
(1+ .1 ) (1+ .1 )
10,000
22
Time
0
1
2
3
4
P R O J E C T
A
B
(10,000.) (10,000.)
3,500
500
3,500
500
3,500
4,600
3,500
10,000
k=10%
0
(10,000)
NPV =
=
3,500
3,500
(1+ .1 )
1
3,500( .10
3,500
3,500
(1+ .1)2
3,500
3,500
3,500
3,500
+
3
4
(1+ .1 ) (1+ .1 )
1
4)
.10(1+.10)
10,000
- 10,000
23
ACCEPT A & B
ACCEPT B only
Mutually Exclusive:
Means
Meansunder
underconsideration.
consideration.(You
(Youmay
mayonly
onlychoose
chooseone.)
one.)
that
thatthe
theacceptance
acceptanceof
ofone
oneproject
projectprecludes
precludesthe
theacceptance
acceptanceof
ofthe
theother
other
projects
projects
NPV-EXERCISE
Time Period
Return (8%)
IO
1,000,000
1st
450,000
2nd
400,000
3rd
350,000
4th
300,000
5th
250,000
25
CONCLUSION
We have discussed project analysis under certainty, i.e. in a norisk situation. In reality, however, the future cash flows of a
project are not certain.
Measuring the risk associated with the expected cash flows of
the project and incorporating this risk into the determination of
the net present value (NPV) is essential for any real world
project evaluation.
There are various ways in which risk can be incorporated into
the NPV computation and capital budgeting decision support.
These include the risk-adjusted discount rate, the certainty
equivalent, sensitivity and break-even analysis and simulation.
They are the risk-adjusted discount rate and certainty
equivalent methods.