KBR STANDARD PROJECT

IPMS CHAINS
ELECTRICAL

Chain D-KDEL: Engineering Deliverable


Electrical Specifications, Studies & Drawings

100%

DD-STT

CPM
CHAIN

DD-ICM

Prepare & Issue Deliverable

DD-STT

DD-PRC

10%

IPMS
CHAIN

75%

Prepare
Duration_15_

MILESTONES:
DD-STT
DD-PRC
DD-IST
DD-ICM

Start Document
Complete Prep
Start Document Issue
Complete Issue

DD-IST

DD-ICM

75%

100%

Finalize & Issue


Duration_5_
Work Package Sub Types: ELC, ELL, ELP
IPMS Document Sub Types: ELC1, ELC2, ELC3, ELC4,
ELC5, ELC6, ELC7, ELC8, ELC9, ELL1, ELP1, ELP2, ELP3,
ELP4

Chain D-KFPD: Electrical


DD-STT

DD-CID

DD-SIC

80%

CPM
CHAIN

20%

Issue For
Construction

Internal & Client Review/ IFD

DD-STT
5%

IPMS
CHAIN

DD-TDC
45%

Develop

IDC

Duration__20_
MILESTONES
DD-STT
DD-TDC
DD-FDC
DD-CIA
DD-FCA
DD-CID
DD-SIC
DD-CIC

Start Document
To Discipline Check
From Discipline Check
Issue For Client Approval
From Client Approval
Issue for Design
Start IFC Issue
Issue for Construction

DD-FDC
45%

DD-CIC

DD-CIA
60%

Prepare
Client
Approval

ICA

Duration__7___

DD-FCA
60%

DD-CID
80%

Prep Issue
For Design

IFD

Duration_7__

DD-SIC

DD-CIC

80%

100%

Issue For
Construction
Duration_30_

IFC

Work Package Sub Types: ELA, ELD, ELE, ELF


IPMS Document Sub Types: ELA1, ELD0, ELE0, ELF0

Chain D-KDCP: Electrical Physical Design

DD-STT

DD-FFC
100%

CPM
CHAIN

Extract/Review/Issue

DD-STT

DD-DRC

10%

IPMS
CHAIN

MILESTONES:
DD-STT
DD-DRC
DD-TDC
DD-FDC
DD-IST
DD-FFC

20%

DD-TDC

DD-FDC

20%

85%

Extract

Review/Approv
e

Duration 5d

Duration 10d

Start Document
Document Ready for Review
To Review
From Review
Start Document Issue
Document Issued for Construction

DD-IST

DD-FFC

85%

100%

Issue

Duration 5d

Work Package Sub Types: ELL, ELM


IPMS Document Sub Types: ELL1, ELL2, ELL3, ELL4, ELL5,
ELL6, ELL7, ELL9, ELM1, ELM2, ELM3, ELM4

Chain D-KCRS: Cable Schedules

DD-STT

100%

CPM
CHAIN

Prep/Check/Issue

DD-STT

DD-IPL
10%

0%

IPMS
CHAIN

DD-FFC

Specification
Files
Duration_10__

MILESTONES:
DD-STT
DD-IPL
DD-SPA
DD-IFA
DD-SPR
DD-IAR
DD-SPP
DD-IAP
DD-SPC
DD-FFC

DD-SPA

DD-IFA

10%

25%

Power Cable
Assignments
Duration_10__

Start Specification Files


Complete Specification Files
Start Power Cable Assignments
Complete Power Cable Assignments
Start Document
Complete Document
Start Check
Complete Check
Start Issue
Complete Issue

DD-SPR

DD-IAR

25%

70%

Prepare
Document
Duration_10__

DD-SPP

DD-IAP

70%

95%

DD-SPC

DD-FFC

95%

100%

Check
Duration_10_

Issue

IFC

Duration_10__

Work Package Sub Types: ELN


IPMS Document Sub Types: ELN0

Chain E-KGEN: Load List & Plant Layout Support


DD-STP

100%

DD-CMP

General
Activity

CPM
CHAIN

DD-CMP

DD-STP
0%

IPMS
CHAIN

MILESTONES:
DD-STP
DD-CMP

100%

General
Activity

Work Package Sub Types: ELB, ELH, ELK


Start
Complete

IPMS Document Sub Types: ELB0, ELH1, ELH2, ELH3

Chain D-KOLD: One-Line Diagrams


DD-STT

DD-IFA

DD-TCR

DD-IAR

50%

CPM
CHAIN

5%

IPMS
CHAIN

DD-IPL
20%

Prepare
Preliminary/
Contract Basis

Duration_10__
MILESTONES:
DD-STT
DD-IPL
DD-SPA
DD-IFA
DD-TCR
DD-FCR
DD-SPR
DD-IAR
DD-SPP
DD-IAP
DD-SPC
DD-FFC

20%

Start Preliminary Electrical One


Lines & Issue for Client Approval

DD-STT

DD-SPP

DD-SPA

DD-IFA

20%

50%

Prepare
For
Approval

Duration_20__

Start One-Lines
Complete Preliminary
Start Approval One-Lines
Issue for Approval
To Client Review
From Client Review
Start Approved One-Lines
Issue Approved One-Lines
Start As-Purchased One-Lines
Complete As-Purchased One -Lines
Start Construction Issue
Issue For Construction

Client Approve & Issue


Electrical One Line

DD-TCR
50%

DD-FCR
50%

Client
Approve

ICR

Duration_10__

Prepare
As-Purchased

Prepare
for
Construction

DD-SPP

50%

70%

70%

Duration_10__

DD-FFC

20%

DD-IAR

IFD

DD-SPC

10%

DD-SPR

Prepare
Approved

DD-IAP

DD-IAP
80%

Prepare
As-Purchased

Duration_10__

Work Package Sub Types: ELA


IPMS Document Sub Types: ELA0

DD-SPC
80%

DD-FFC
100%

Prepare
for
Construction

IFC
Duration_10__

Chain P-TPK:
Procurement (Acquisition) Chain
Tags and Equipment

CPM
CHAIN

AW-INT
DD-STT
DD-RFQ

DD-RFQ

Issue
Eng.
Scope

FQ-ISS

FQ-ISS

Issue
Inquiry

10%

FQ-REC

Evaluate Bids /
Make
Recommendation

0%

30%

FQ-REC

AW-ISS

AWINT

Issue
Interim
Award
(NOC)

15%

0%

Transport
& Deliver

PP-REL
PP-DES

Assemble
& Issue
ERW
5d

(5-20d)

DD-RFQ
10%
RF-ISS
10%
Prep &
Issue
RFQW
2d

RF-ISS
10%
FQ-ISS
10%
Prep &
Issue
RFQ
2d

FQ-BID
FQ-ISS
10%
10%
FQ-BID
FQ-TEC
10%
40%
Supplier
Prep
Bids
20d

Technical
Evaluation
10d

(10-20d)

PP-PHY

Receive & Accept


Initial
Supplier Data
20%

Issue
Formal
Award

Fab &
Ship

DD-STT
0%
DD-RFQ
10%

AW-ISS

FQ-TEC
FQ-REC
AW40%
40%
INT
FQ-REC
AW-INT
DD-REQ
40%
40%
40%
55%
Issue
Issue
Eval Bids
Interim
ERW for
& Issue
Award
Purchase
Recomend
(NOC) 2d
10d
2d

(10-15d)

PP-DES
MM-RAS

DD-REQ
55%
RQ-ISS
55%
Issue
REQ for
Purch
7d

PP-REL
100%
PP-DES
100%

RQ-ISS
55%
AW-ISS
55%
Issue
Forma
l
Award7d

PP-DES
100%
MM-RAS
100%

MILESTONES:
DD-STT
Start Document
RQ-ISS
Req Issued to Purchase
DD-RFQ
Issue ERW, RFS, or MTO
AW-ISS
Award Issue External
RF-ISS
Issue RFQW
DD-ISC
Supplier Prep Initial Data
Transport
Fab &
FQ-ISS
RFQ (Inquiry) Issued
PP-PHY
Receive Initial Supplier Data
& Deliver
Ship
FQ-BID
Bids Return
DD-FSC
Supplier Prep Final Data
60d
10d
FQ-TEC
Engineering Tech Review Complete
PP-CRT
Receive Final Supplier Data
AW-INT
Issue Interim Award
PP-REL
Fab & Ship
FQ-REC
Recommend Issue
PP-DES
Materials Shipped
Work Package Sub Types: ELJ, ELL
DD-REQ
Update Reqmts for Purchase
MM-RAS
Receipt At Jobsite
NOTES:
IPMS Document Sub Types: ELJ1, ELJ2, ELJ3
1. Percentages shown are for Engineering Progress Only.
ELJ4, ELJ5, ELJ6, ELJ7, ELL0
2. Dotted boxes represent non-Engineering responsibilities only.
3. International projects may require Consolidation yard milestone.
4. Activity content & durations must be reviewed and modified to fit each projects requirements.

Receive & Accept


Final
Supplier Data
25%
PP-PHY

PP-CRT
DD-ISC
55%
PP-PHY
75%

AW-ISS
55%
DD-ISC
55%
Supplier
Prep/
Submit
Initial Data

Review
Initial
Supplier
Data
10d

(10-60d) 30d

PP-PHY
75%
DD-FSC
75%

Supplier
Prep/
Submit
Final Data

(10-30d)

IPMS
CHAIN

20d

Review
Final
Supplier
Data 10d
DD-FSC
PP-CRT
75%
100%

Chain P-BOS:
Procurement (Acquisition) Chain
Blanket Order Bulks or Subcontracts
DD-STT DD-RFQ
DD-RFQ
30%
Issue
Scope

0%

FQ-ISS

FQ-ISS

Evaluate Bids /
Make
Recommendation

Issue
Inquiry

CPM
CHAIN

IPMS
CHAIN

DD-STT
0% DD-RFQ
30%
Issue
ERW, RFS
or MTO

MILESTONES:
DD-STT
DD-RFQ
RF-ISS
FQ-ISS
FQ-BID
FQ-TEC
FQ-REC
PP-FCR
AW-ISS

30%
30%
FQ-ISS
30%
DD-RFQ 30%
RF-ISS
RF-ISS

FQ-ISS
30%
30%
FQ-BID

PREP &
ISSUE
RFQW
5d

SUPPLIER
PREPARE
BIDS
10d

Start ERW, RFS or MTO Assembly


Issue ERW, RFS, or MTO
Issue RFQW
RFQ (Inquiry) Issued
Bids Return
Eng Tech Review Complete
Recommend Issue
Client Approval
Award Issue External

FQ-REC

70%

PREP &
ISSUE
RFQ
2d

FQ-BID
30%

AW-ISS
0%

Issue Award
(Blanket or Subcontract)

PP-FCR
100%

FQ-TEC
100%
FQ-TEC
100%

Technical
Evaluation
50d

FQ-REC

FQ-REC
100%
EVAL BIDS
& ISSUE
RECOMEN
2d

100%
FQ-REC
CLIENT
APPROVE
10d

AW-ISS
100%
100%
PP-FCR
ISSUE
BLANKET
AWARD
2d

Work Package Sub Types: G60, G80


Document Sub Types: G63, G83

NOTES:
1. Percentages shown are for Engineering Progress Only.
2. Dotted boxes represent Procurement (non-Engineering) responsibilities only.

Chain P-BOR:
Procurement (Acquisition) Chain
Blanket Order Release
DD-STT

CPM
CHAIN

IPMS
CHAIN

MILESTONES:
DD-STT
DD-REQ
RQ-ISS
AW-ISS
PP-REL
PP-DES
MM-RAS

Issue
Scope

DD-STT
70%

PP-REL

DD-REQ

100%

DD-REQ
100%

DD-REQ

PP-DES
PP-DES

AW-ISS
FAB &
SHIP

ISSUE FORMAL
AWARD

RQ-ISS AW-ISS
100%
100%
100%
DD-REQ
RQ-ISS
100%

Issue
ERW or
MTO for
Purchase

ISSUE
REQN
FOR
PURCH

ISSUE
Purchase
AWARD

5d

5d

2d

TRANSPORT,
DELIVER &
RECEIVE

PP-REL PP-DES PP-DES


100%
100%
100%
FAB &
SHIP
60d

MM-RAS

MM-RAS
100%

TRANSPORT,
DELIVER &
RECEIVE
10d

Start ERW, RFS, or MTO assembly


Issue ERW, RFS, or MTO
Req Issued to Purchase
Award Issue External
Fab & Ship
Materials Shipped
Receipt At Jobsite

Work Package Sub Types: G60


Document Sub Types: G64

NOTES:
1. Percentages shown are for Engineering Progress Only.
2. Dotted boxes represent Procurement (non-Engineering) responsibilities only.
3. International projects may require Consolidation yard milestone.