MANUFACTURING

PROCESS SEQUENCE
PUP JOINT
CROSS OVER
X-OVER

DETAIL OF WORKS
1.
2.
3.

4.

Received Order
Material Preparation
Turning Process
(Refer to Lathe Machine Work
Instruction)
QC Check
(Refer to QA Work Instruction)

PRODUCTION WORK INSTRUCTION


LATHE MACHINE

PRODUCTION WORK INSTRUCTION


CALIPER

PRUDUCTION WORK INSTRUCTION


MICROMETER

PUP JOINT

SIZE 2 3/8

SIZE 3

CROSS OVER

SIZE 7

SIZE 9 5/8

CROSS OVER

SIZE 11

SIZE 13 5/8

MAIN CUSTOMER

PT.CITRA TUBINDO TBK


PT.CITRA TUBINDO ENGINEERING
PT.CATERPILLAR INDONESIA BATAM
PT.CAMERON SYSTEMS
PT.RADIANT UTAMA INTERINSCO
PT.RISEA PROPULSION INDONESIA

THANK YOU