Beruflich Dokumente
Kultur Dokumente
management
Case Study on Kurlon limited
Submitted to
Prof.RajendraTodalb
agi
Submitted by :
Group no. 10 (Section A)
Anshuman 16008
Binka Gowda 16012
Manoj kumar 16023
Nayanashree Herale 16028
Nidhi Padmakumar 16029
KURLON LIMITED
Kurlon is the largest manufacturer of mattresses, pillows and coir mats in India.
The Company was the market leader in rubberized coir mattress market in India
with approximately 65% of market share.
Manufacturing Units
By
By 2015 The Company has increased the number of sales offices, dealers and
warehouses in India and have also started exporting their products.
Products
Romantique
each)
10% 1%
13%
76%
SDL
Apsara
Klassic
Romantiq
ue
Production Process
Fabrication - in-house.
RC PAD MANUFACTURING
For the reduction of moisture content in the fibre, coir fibres kept in rope form for 80 days.
UNTWISTING
After untwisting fibres should be atleast six inches, only then it is fed to the next operation.
Sheeting
Coir fibres are continuously fed to a conveyor in a sheet form of specific width and thickness.
This specified width is the required rc pad length with trim allowance.
During the process a chemical consisting of latex, clay and bonding chemicals is sprayed across the entire
breadth of the pad.
Sheet cutting
Computer control ensures that the effective output rates of the sheet cutting and the previous two operations
are balanced.
Pressing
Specific number of fleeces are pressed at a temperature of 120 deg C and pressure of 2.5 bar.
To obtain 2.5 inch thick rc pads, 5 fleeces are pressed and for 3.5 inches, 7 fleeces are pressed.
Pressing time for 2.5 inch pads-27 min, for 3.5 inch pads-31 min.
Vulcanizing
This operation has the least capacity among the manufacturing operations.
Cooling
Vulcanized pads are cooled before sending to the pad cutting section using overhead fans.
Pad Cutting
Sheeting and sheet cutting done in a way that the Rc pads have 2 inchtrim allowance on
all the four edges.
Foam making
Ordinary foam sheets-0.5 inch thick, bonded form sheets-1.5 inch thick.
After 24 hours of curing,form edges are trimmed to get the required foam dimensions.
Fabrication process:
On an average items are stocked for approximately three days in the fabrication shop.
Covering cloth comes in bales. Each bale is used to fabricate 150 mattresses.
30
20
10
0
Week
Process
Mode of operation
Lots size of 160 or 320 mattresses are transferred to the regional warehouses.
Kurlon has long term rate contracts with different transportation such as 14000
for ordinary truck (160 mattresses) and 24000 for jumbo truck (320 mattresses).
Continued..
If certain configurations are not available as per the indent, then some other
configuration is loaded.
Before the 25th of the previous month, work order is sent, which specifies
both size & variety of the mattress on an weekly basis.
Work order is based on demand forecast for the next month and also stocks
available at the regional warehouse.
Retailers
There are 5000 retailers spread across the country who stock kurlon products.
Kurlon retailers stock other branded mattresses hence kurlon product must
be well stocked.
Kurlon charges 100 per alteration and takes weeks time to deliver.
Future Plans
Kurlonhas planned to introduce two different types of mattresses in the Indian market.
DUPONT will provide the know-how for manufacturing core pads with imported fibrefill
using vertical fold technology.
The product range is expected to cross 200 configurations by introducing these new
products.
They are sending only full truckloads (160 or 320 mattresses). The
material needed for two or more regions never clubbed in one truck
load. It takes 3 to 10 days to reach Delhi Regional Distribution Centre.
Causes:
Some retailers are placing orders for quantity as low as six mattresses.
Month
April
May
June
July
August
September
SDL 72*35*4
Opening
Period Indent Dispatch Stock
Production
1
480
120
1956
0
2
366
540
1836
0
3
168
354
1296
0
4
120
120
942
0
5
402
696
822
150
6
774
1284
276
1038
7
552
246
30
264
8
264
372
48
1488
9
462
612
1164
438
10
1050
180
990
432
11
276
564
1242
996
12
288
686
1674
8
13
778
396
996
0
14
498
588
600
396
15
714
1146
408
1638
16
198
90
900
486
17
180
690
1296
726
18
570
522
1332
246
19
564
90
1056
54
20
78
6
1020
0
21
276
630
1014
114
22
762
762
498
468
23
840
636
204
1164
Performance Analysis
Ratio calculation
Formulae
swc
swcp=net sales/swc
swcp
2015
1997
1996
-48.04
372.42
154.1
-0.8445
3.01326
6.68332
kurlon is having low supply chain working capital productivity instead of having high sc wc productivity.It supposed to increase its
productivity.
Length of sc
DRM
rm*365/crm
dwip
sfg*365/cp
DFG
fg*365/cs
81.62238
93.54815
79.35907
110.247
130.893
113.141
21.23899
32.78326
7.385766
26.09533
4.56188
7.68689
Duration of time taken by the materials flow is minimised. Performance of the company is regarded as good.
Efficiency of scm
SCC
DC+inv*icc
icc( assume)
scc/ns
18.662
48.38
40.02
0.2
0.02331
0.04311
inefficiency is decreased compared to 1996 &97. efficiency of internal supply chain management is good.
0.03886
Continued.
Forecasting
Production Planning
Dispatch planning
No proper planning for non standard sizes even though it constitutes about 10-30 percent of total
demand.
No proper safety measures as four fires in the last fifteen years resulted in 2-3 days losses each time.
Some times the stock levels are zero even if there is demand.
4.What
Purchase new vulcanizing chamber as it was not able to cope with other processes.
Even after keeping excess inventories also, stock outs are very common and sometimes they are
dispatching the products that are not ordered by ASOs. They can classify the products based on ABC
Analysis so that it will reduce excess inventories and cost.
Purchase department orders raw materials in huge quantities owing to anticipated price fluctuation.
This leads to stock piling. They should monitor the price trends and the sourcing strategy should be
based on current prices.
The primary focus should be on total cost. Too much of importance should not be given to economies
of scale.
Thank You!