Beruflich Dokumente
Kultur Dokumente
in Railway Projects
ANDREW GEORGE CHERIAN CE14M102
UNDER THE GUIDANCE OF
DR. KOSHY VARGHESE
INTRODUCTION
A typical railway construction project involves the construction of embankment,
bridges, structures, railway tracks, overhead equipment and signaling systems.
The track linking activity has about 25.5% share in the overall project cost. Out of
this track linking activities, the most important is the rail welding activity which
requires the welding machine which itself is a 6.5 crore equipment and is a shared
resource across projects.
As these projects are linear in nature and highly labor intensive, there tends to be
a lot of site level issues which tends to obstruct the smooth flow of these activities.
Objective
To analyze the various factors affecting track linking activities in railway projects
To find a possible solution to the problems and improve the flow of equipment
across projects.
Methodology
Sources of data:
1)Field study
2)Semi structured interviews
3)Analyzing data from current projects
4)Questionnaires
COLLECTIN
FIELD
G
STUDY &
ATTRIBUTE
LITERATUR ANALYSIS
S
E REVIEW
GROUPING
ATTRIBUTES
INTO MAJOR
INTERVIEW FACTORS
VALIDATION
OF
PRELIMANARY LIVE SITE
DATA
OBSERVATION
S
FINDING
WAYS TO
INTERPRETI
TACKLE
NG RESULTS
THE
ISSUES
Contd.
1) Conduct field study to study the sequence of activities and to compile a list of factors affecting track
laying.
2)Conduct a series of semi structured interviews with site supervisors, site engineers and planning
engineers to get different perspectives on the list of factors complied in step 1.
3) Analyze the data from current projects
Carry out productivity analysis on various activities
Carry out cost comparison of mechanized and manual methods of track laying
Preparing a CPM based plan & comparing with actual site plan and actual progress and
interpreting results.
Contd.
4) Conducting a questionnaire survey and get more responses to strengthen the studies and
analysis done in step 1,2 and 3.
5) Compiling all the data from different sources and converge to a conclusion.
PILOT STUDY
FLASH BUTT WELDING MACHINE
For rail welding, we use Mobile FBW (MFBW) machine. This machine is a welding unit
fitted on a track chassis along with a generator. It is can be either a road only vehicle or
road and rail vehicle. These equipment in India have to be approved by RDSO before
being deployed to any IR construction site.
There are two types of welding that is carried out in site, they are:
Cess welding:
machine shifting
3%
no approach road
VA 17%
NVAN non availabilty of
44% 3% 45% tools
51% NVA
shortage of labour
7%
5% 10%
difference of
opinion between HQ
and site
The distribution of idle time was found out by counting the number of days by which the welding activity
was affected by at least 1 hour because of the respective factors.
Contd.
per weld= + subcontractor wage per joint
Cost
Cycle time for the welding process= Time for aligning the rails + Time for weld +
Time for cleaning the flash+ Time for moving the machine to the next joint
location.
= 1 +3 + 0.25 + 0.5 mins
=4.75 mins
Considering a total working duration of 6 hours, we get that a maximum of 75
weld per day and incorporating an efficiency factor of 80%, it can be brought
down to 60 joints per day.
Planned
productiviv
ity
No. of
welds
per
machi
ne
Achievable
productivity
Planned
productivity
Actual
productivity
CONTD.
It was observed that to load ,unload 34 rails from stock point to site (500m) it took 5 hours.
And to pair those rails properly with a backhoe loader and an experienced operator it took
2hours.
And extrapolating this data to a whole working day with 8 hours only 45 rails would be
unloaded to site and it would again take more time to pair them.
Analysis of work front availability
due to preceding activity
For rail pairing in terms of cost= meters of rail paired_______
per day cost of HYDRA+ Backhoe+ operators+helper
=22*13/(5000+4000+1000+300)
=0.028m/Re
For welding activity in terms of cost= meters of welded panel_____
per day cost of FBW+welders+
helpers
= 42*13/(45000+1066+1500)
=0.011m/Re
CONTD.
Even though welding activity is twice as costly as rail pairing activity ,
Welding activity is being delayed because of the less productive rail pairing.
Thus for improving the productivity of track laying activity rail pairing is to be well planned
and executed.
Efficiency of the process
Labor shortage
Less planning skills
Sub contracted
labor Poor Site Management Delays in
bridges Lack of look ahead
Fragmented Work front plan Ambiguity in equipment availability
Less training Lack of support from
subcontractor
Less Mechanization
Lack of access roads
Lack of consumables at site DPR analysis not done DELAYS IN TRACK
LINKING ACTIVITIES
Planning team
Execution Productivity is not recorded
Team
LACK OF NO PROPER
COORDINATION MONITORING
Analysis of scope of Mechanization
of track linking
By considering the equipment required for all the track linking activities like rail shifting, rail
pairing, sleeper shifting, bottom ballast, top ballast, ballast spreading & compaction, rail
laying and clipping and rail welding, total hours working hours required for finishing the scope
of work for a section of a site was found out. Using the owning and operating cost for each
equipment per hour, total equipment cost required for manual method and mechanized
method of track linking were found out.
MANUAL
METHOD