Beruflich Dokumente
Kultur Dokumente
Chapter 16
Materials
Requirements
Planning
McGraw-Hill/Irwin The McGraw-Hill Companies, Inc.,
3
OBJECTIVES
Material Requirements Planning
(MRP)
MRP Logic and Product Structure
Trees
Time Fences
MRP Example
Material Requirements
Planning
Materials requirements planning (MRP)
is a means for determining the number
of parts, components, and materials
needed to produce a product
MRP provides time scheduling
information specifying when each of
the materials, parts, and components
should be ordered or produced
Dependent demand drives MRP
MRP is a software system
First,
First, the
the number
numberof of units
units of
of A
A are
arescheduled
scheduled
backwards
backwards to to allow
allowfor
fortheir
theirlead
lead time.
time. So,So, in
in the
the
materials
materials requirement
requirement planplan below,
below,we wehavehavetotoplace
place
an
an order
orderfor for50
50 units
units of
of A
A onon the
the 99th day
th
day to
to receive
receive
them
them onon day
day 10.
10.
Day: 1 2 3 4 5 6 7 8 9 10
A Required 50
Order Placement 50
LT = 1 day
LT = 2
Spares
A 4x50=200
B(4) C(2)
A
Part D: Day 6
B(4) C(2) 40 + 15 spares
MPS
(Specific End Items)
Exhibit
Exhibit15.5
Example of Time Fences 15.5
Moderately
Frozen Firm Flexible
Capacity
Forecast and available
capacity
Firm Customer Orders
8 15 26
Weeks
System
Aggregate Forecasts
Firm orders product of demand
from known plan from random
customers
customers
Material From
FromExhibit
Exhibit15.6
15.6
planning
Bill of (MRP Inventory
material computer record file
file program)
Secondary reports
Primary reports
Exception reports
Planned order schedule for Planning reports
inventory and production Reports for performance
control control
The McGraw-Hill Companies, Inc.,
14
Components
Production sequence
Modular BOM
Subassemblies
Super BOM
Fractional options
Pegging
Identify each parent item that created
demand
Gross Requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
McGraw-Hill/Irwin 2006 The McGraw-Hill Companies, Inc., All
19
MRP Example
Requirements
Requirementsinclude
include95
95units
units(80
(80firm
firmorders
ordersand
and15
15forecast)
forecast)of
ofXX
in
inweek
week10
10
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
ItIttakes
takes
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
22As
Asfor
for On-
hand
Net requirements
Planned order receipt
20
20
each
eachXX 25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
ItIttakes
takes Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
11BBforfor hand Planned order receipt 20
each
eachXX
25
C
Planner order release
Gross requirements 45
20
40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20
On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes33
C
LT=2
Gross requirements
Scheduled receipts
45 40
Cs
Csforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachAA
hand
10
Planned order receipt
Planner order release 35
35
40
40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes22
C
LT=2
Gross requirements
Scheduled receipts
45 40
Cs
Csforfor On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
each
eachBB
hand
10
Planned order receipt
Planner order release 35
35
40
40
Day: 1 2 3 4 5 6 7 8 9 10
X Gross requirements 95
X LT=2 Scheduled receipts
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
A(2) B(1) LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75
On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
C(3) C(2) D(5) B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20
ItIttakes
takes55
C
LT=2
Gross requirements
Scheduled receipts
45 40
Ds
Dsforforeach
each On-
Proj. avail. balance
Net requirements
10 10 10 10 10
35 40
BB hand
10
Planned order receipt
Planner order release 35
35
40
40
No
Realistic? Feedback
Feedback
Yes
Execute:
Capacity Plans
Material Plans
Planning
(MRP II)
End of Chapter 16