Sie sind auf Seite 1von 17

Technology Solutions Company

Capacity Requirements
Planning (CRP)

1
Copyright 2006 Technology Solutions Company
Objectives

Define Capacity Requirements Planning (CRP) and describe


how it relates to priority planning (MRP)
Describe how the Load Profile and Load Detail reports are used
to identify capacity problems in the priority plan generated by
MRP
Distinguish between Planned Capacity and Actual Load
Describe what steps can be taken to ensure that shop capacity
is efficiently utilized

2
Copyright 2006 Technology Solutions Company
CRP answers the question. . .

What do we need to get and when?


Man Hours
Machine Hours

BOM

PM

INV Material Capacity


Requirements Requirements
Planning Planning
RTGs

WCs
3
Copyright 2006 Technology Solutions Company
Capacity Management

HIGH
Capacity
Requirements
Planning
SHOP FLOOR
OPERATIONS
D
E Rough Cut
T Capacity
A Planning
MASTER
I SCHEDULING
L
S Resource
Requirements
Planning
PRODUCTION
PLANNING

LOW
Operational Tactical Strategic

CURRENT RESOURCE PLANNING HORIZON FUTURE 4


Copyright 2006 Technology Solutions Company
Capacity Requirements Planning

The function of establishing, measuring, and adjusting


limits or levels of capacity. The term capacity
requirements planning in this context is the
process of determining how much labor and
machine resources are required to accomplish the
tasks of production. Open shop orders, and
planned orders in the MRP system, are input to
CRP which "translates" these orders into hours of
work by work center by time period.

....APICS DICTIONARY
5
Copyright 2006 Technology Solutions Company
Capacity Requirements Planning

MRP generates a priority DEMAND SUPPLY


plan based on supply and
demand
MRP
The MRP plan is oblivious to
the capability to execute the
plan
Time & In House
Quantity Out House
An effective MRPII system NEED CAPACITY
requires an effective capacity
planning system

CRP
6
Copyright 2006 Technology Solutions Company
Capacity Requirements Planning

CRP is both a function and a tool


As an organizational function, CRP establishes, measures,
and adjusts the limits (or levels) of capacity
As a Capacity Management tool, CRP is used to determine
how much labor and machine resources are required to
accomplish the tasks of production
CRP is a short range analytical tool which determines if the
MRP generated plan is achievable

7
Copyright 2006 Technology Solutions Company
Capacity Requirements Planning

The mechanics of CRP are straightforward


The planned orders from MRP are "blown through the
routings for each order to generate a capacity load profile
and details at each work center defined in the routings

8
Copyright 2006 Technology Solutions Company
Routings

Start Due

Operation
OP 1 OP 2 OP 3 OP 4 OP 5
Sequence

.5 Hrs 1 Hr 3 Hrs .5 Hrs 4 Hrs Standard


Hours

Paint Work
Lathes Drilling Milling Deburr
Shop Center

Load
Profiles

9
Copyright 2006 Technology Solutions Company
Load Profile

A Load Profile is generated for each work center

Average Available
Capacity
H
O PLANNED ORDERS
U
R
S
RELEASED ORDERS

TIME
Planned Orders + Released Orders x WC Standard = Load
10
Copyright 2006 Technology Solutions Company
Load Profile

Load Released and MRP Planned Orders


A single work center may be used in many different routings
The resulting load profile is a sum of all the work actually at
and planned to be at that work center

Order 4,
Order 3, Part D
Part A
Order 5,
Order 2,
Part A
Part B
Order 2, Part B

Order 1, Order 6,
Part C Work Center No. 5100 Part B
Dept 82
11
Copyright 2006 Technology Solutions Company
Load Leveling

Under loaded Work Centers may be just as much of problem as


over loaded Work Centers
Ideally, a Work Center should be "level loaded" and with MRP
there are several things a planner can do to achieve this

Over
Capacity
Under

Work Center No. 5100


Dept 82
12
Copyright 2006 Technology Solutions Company
Load Details

This report tells the planner what a specific order is contributing


to the problem
Other information
which could be Work Center No.: 5100 FINISHING
on this report Ave Daily Cap: 40
Due Date ORDER ST OP ST DT HRS
Load (%) C1RWK1 WIP 031698 15
Operation C2MFG1 REL 031698 10
Number C3MFG1 REL 031698 15
Part Number
C4MFG1 REL 031798 22
C1MFG2 PLN 032398 6
Quantity
C1MFG3 PLN 032498 15
Time
C3MFG1 PLN 032498 11
Remaining
Data 13
Copyright 2006 Technology Solutions Company
Planned Capacity

Planned Capacity may be based on standards or on


demonstrated capacity
Capacity can vary due to vacation periods, holidays, planned
plant shutdowns, new machine acquisition, etc.
The database must be periodically updated with the planned
capacity numbers
Demonstrated Capacity

Planned Orders

Released Orders

Actual Load The sum of released and/or planned shop orders


14
Copyright 2006 Technology Solutions Company
Capacity Requirements Planning

Does Projected load match Available Capacity?

CHANGE SCHEDULE
Split a released order
Use the firm planned order

ADJUST CAPACITY
Subcontract
Off load to a substitute
resource

15
Copyright 2006 Technology Solutions Company
Capacity Requirements Planning

Performance Measurement
What is being measured? Capacity Plan Accuracy

What is the target? 100% +/- 5%

How is the % calculated? Planned Input


Actual Input
x 100
Planned Output
x 100
Actual Output
Performance Criteria:
Standard hours planned to be received
Standard hours actually received
Standard hours planned to be earned
Standard hours actually earned 16
Copyright 2006 Technology Solutions Company
Technology Solutions Company

End of Capacity
Requirements Planning

17
Copyright 2006 Technology Solutions Company

Das könnte Ihnen auch gefallen