Commissioning Sample

1. Service Entrance
Item Items for Inspection and Testing Remarks
# Yes No

1 Size of wire & Type of Insulation (8.0 sq. mm THW


wire)
2 Type & Size of pipe (3/4 dia.RSC Pipe)
3 Rating of Main Circuit Breaker (30 A.T)
2. Distribution Board & Circuit protection

Item Items for Inspection and Testing Remarks


# Yes No

1 Circuit Breaker Rating & Type (30A.T, bolt on)


2 Type & Size of pipe (1/2 FMT)
3 information of panel board are correctly, adequately &
legibly provided. (ratings, frame #, ect.)
Commissioning Sample
Cont..

Item Items for Inspection and Testing Remarks


#
Yes No

4 No visible damage to impair safety.


5 All protective devices are functioned properly and correctly
set.
6 A warning notice DANGER is provided on
the front panel of every distribution board.
7 Distribution boards securely mounted on suitable supports.
8 Circuits connected to MCB in accordance with
the schematic diagram.
9 Homeruns are properly harness
10 Earthing system effectively connected.
11 Operation of circuit breakers and disconnecting switches
checked.
Commissioning Sample
3. Lighting
Circuits
Item Items for Inspection and Testing Remarks
# Yes No

1 The continuity of conductor /earth termination network has


been checked and found satisfactory.
2 Size of wire & Type of Insulation (2.0 sq. mm)
3 The insulation resistance to earth is NOT less than 1 M.
4 All lamps are the correct wattage and voltage ratings
5 Circuits protection connected to MCB in accordance with
the schematic diagram.
6 All conductors and joints for lightning protection system
are electrically, mechanically and correctly connected.
7 Homeruns are properly harness
8 All lighting circuits have been verified through switching
operation that they are installed in accordance with the
design plan.
Commissioning Sample
3. Power Circuits
Item Items for Inspection and Testing Remarks
#
Yes No

1 No visible damage to impair safety.


2 Size of wire & Type of Insulation (3.5 sq. mm TW wire)
3 Type & Size of pipe

4 Outlets are tested and securely mounted according to plan.


5 Circuits protection connected to MCB in accordance with
the schematic diagram.
6 All wiring has been correctly connected to socket outlets
7 Homeruns are properly harness
8 All power circuits have been verified through testing that
they are installed in accordance with the design plan.
Commissioning Sample
3. Auxiliary
Circuits
Item Items for Inspection and Testing Remarks
#
Yes No

1 No visible damage to impair safety.


2 Size of wire & Type of Insulation
3 Type & Size of pipe

4 Outlets are tested and securely mounted according to plan.


5 Circuits protection connected to MCB in accordance with
the schematic diagram.
6 Proper ventilation provided to avoid excessive
temperature rise.
7 A local switch was provided to control every motor
8 Loads outputs are tested according to plan
Commissioning Sample

Findings:

Recommendations:

Inspected by: Checked by:


_______________ _______________
Lead man Foreman

Witnessed by:
______________
Project Engineer