Beruflich Dokumente
Kultur Dokumente
FOUNDATIONS
ORIGIN
Origin in India
have been used for hundreds of years.
Initially masonry wells sunk for
drinking water in ancient times
Later on same technique was used for
construction of foundation wells
Freely used during the Moghal period,
many Moghal monuments including the
Taj Mahal have got well foundations
The Moghal used well foundations for
bridges across major river also
HISTORY
MS Angle
OR 60 LB
MS RAIL
Plate
Fillet Weld
WELL CURB
WELL STEINING
COMMON SHAPES
CIRCULAR
Most commonly used
Advantages:
Strength, simplicity, ease in sinking, minimum
steining thickness due to minimum flexural stresses
It requires only one dredger for sinking
The distance of the cutting edge from the dredge hole
is uniform and the chances of tilting are minimum
Disadvantages:
Generally adopted for piers of single line railway
bridges
9 m is considered as the max. dia. Allowing cantilever
of 1m on either side, the maximum length of pier is
about 11 meters
It offer relatively less resistance against lateral
forces.
Double D well
Advantages:
Long piers for multiple lines can be accommodated
greater lateral stability.
Simple shape
Easy to sink but greater effort than circular well
Disadvantages:-
Considerable bending moments in the straight portion
of steining.
Four square corners at either end of the partition wall
offer considerable resistance to sinking
Steining is relatively thick
More prone to tilt and shift due to unsymmetrical shape
and possible unequal dredging
Double Octagonal
Advantages:
Free from short comings of double D
well
Blind corners are eliminated
Bending stresses in the steining are
also reduced considerably
Disadvantages:
Greater resistance against sinking on
account of increased surface area
Concreting in steining is more difficult
than in case of double D wells.
Rectangular Wells
Advantages:
Can be adopted where the bridge is
designed for open foundations and a
change to well foundation , become
necessary. Rectangular well can be
designed exactly of the same size as of
open foundation
Generally adopted for depth up to 7.5m
Disadvantages:
Bending stresses in the steining are the
maximum.
Twin Circular Well
Consist of two independent circular
wells placed very close to each other
with a common well cap. Has tendency
to tilt
If the depth of sinking is small say up to
7m, the clear space between the two wells
may be kept 0.6 to 1m to avoid tilting
For greater depth of sinking spacing of 2 to
3m may be necessary
Differential settlement may be there
during service
Depth of wells
Decided by
Scour
Stability
Normal scour
D = 0.473 (qf/f)1/3
IF
(a) Design flood continues for sufficient time
(b) River is flowing straight through
incoherent alluvium and are free to adjust
their width of flow and their depth with
equal ease and acquire an elliptical cross
section in the straight reaches
(c) The width of the river is not less than the
Lacys regime width i.e L= 4.85 Qf.
f is the silt factor = 1.76m
Normal scour
Where the width is less than Laceys regime
width
dc/d = (w/wc)0.61
Type of bed Weighted mean dia of Value
materials particle (mm) of f
(i) Coarse 0.04 0.35
silt
(ii) Fine 0.08 0.50
sand 0.15 0.68
(iii) Medium 0.3 0.96
sand 0.5 1.24
(iv) Coarse 0.7 1.47
sand 1.0 1.76
2.0 2.49
Local scour
Bridges are generally located on straight
reaches and even where the river is on curve
suitable guide bunds are provided to ensure
straight flow
Bridge pier cause obstruction to the normal flow
of the river. This causes additional local scour
The scour depends on the shape of the piers, its width,
the direction of flow the silt factor, the velocity and
depth of flow etc.
No rational formula has been evolved so far for
working out the additional scour round the pier
The normal practice on the Indian Railways is to
double the scour depth calculated by the Laceys
formula to arrive at the maximum scour depth below
H.F.L. i.e. local scour depth is taken as D
The depth calculated shall be increased as
indicated in next slide
Local scour
Nature of the river Depth
of
scour
- In a straight reach 1.25D
- At the moderate bend conditions e.g. 1.5D
along apron of guide bund
- At a severe bend 1.75D
- At a right angle bend or at nose of piers 2.0 D
- In severe swirls e.g. against mole head 2.5 to
of a guide bund 2.75D
Local scour
Lacey equations are valid for rivers
which are in regime and flow in
completely incoherent material
There conditions are satisfied in Indo-
Gangetic plains and southern rivers flowing
towards east coast
These conditions are not satisfies elsewhere
Scour depth should be ascertained in
other cases as per spring method given
in RDSO technical paper no. 153 River
training and control on guide bund
system
Grip Length
The well should be sunk below the maximum
scour level to such a depth that
the bearing capacity of the soil is sufficient
resistance from the sides is sufficient to resist lateral
forces
As per Para 6.91 of Substructure Code, we
provide a grip length of 1/3 the maximum
scour depth below the HFL i.e. 2D/3
Well depth can be reduced if non-scourable
material is met with at a shallow depth,
however clay should not be considered as non-
scourable material.
Grip Length
GALES TABLE
SPRINGS TABLE
DESIGN OF WELLS
DESIGN OF WELL
Structural design
Well size and depth
Cutting edge
Curb
Steining
Bottom and top plug
Cap
Stability analysis (As per appendix in
sub-structure code)
WELL SIZE AND DEPTH
Depends on size of piers ; max. 1
m overhang is taken
Proper founding level from bore log
and also satisfying depth of scour
and grip length criteria
Preliminary design based on
vertical and horizontal loads AND
bearing capacity
CUTTING EDGE/CURB
It should cut through hard strata even
if as per bore log there is no rock
It should be able to stand on sloping
rock/boulder/tree trunk
It should be able to withstand
occasional blast forces
No detail design is possible
Typical old successful sections are followed
Steel plate or 60 lbs rail in cutting edge
and M 25 concrete with adequate
reinforcement in curb is used
ZZ ZZ
Cutting Edge
D
E
T
AX
IL
O
F
R
A
M
E
"-5
6
N
O
S
. (C
U
TD
E
T
A
I
L
O
F
R
IN
G
EY
A
M
E
"
B
IN
T
D-6
N
O
S
.
IA
T
E
IN
G
)
STEINING
Thickness of steining should be such that
It should be possible to sink the well without
excessive kenteledge
The well do not get damaged during sinking
It should be possible to rectify tilts and shifts
without damaging the well
Stresses at various stages should be under
permissible limits
Resistance against sudden drop/sand blow
condition
M 15 with 0.12% bond reinforcement and
0.04% of ties are sufficient
STEINING
Sinking Effort
= Wt of Well at the design depth Buoyancy in Kg
Surface area in Sq./m
Sinking effort required (as given in
ME Tech. Inst.)
Stiff and soft clay 0.73 to 2.93 t/m2
Clay 4.88 to 19.53 t/m2
Very soft clay 1.23 to 3.42 t/m2
Dense Sand 3.42 to 6.84 t/m2
Dense gravel 4.88 to 9.76 t/m2
For alluvium deposits, minimum sinking effort
required is of the order of 5t/m2
STEINING
WL
BL
STEINING
STEINING
Appxo Values of F
STEINING
THUMB RULES
For circular shaped wells CC
T=K(D/10+H/100) IRC-21
K=1.0 for sandy strata
K=1.1 for soft clay strata
K=1.25 for hard clay strata
T=D/4 RAILWAY PRACTICE
Minimum Thickness = 1m Railway Practice
Minimum Thickness = 500mm IRC Practice
STEINING
THUMB RULES
For Rectangular or double D-shaped
Wells of CC
T = K(H/100 + L/10)
K = 1.1 for sandy & soft clay strata
= 1.15 for hard clay strata where
D = external diameter of well
L = Longer side of the rectangular well or
the distance for a double D shaped well
H = Full depth to which the well is designed
to be sunk below the bed
CONSTRUCTION
STEPS
LAYOUT
FABRICATION OF CUTTING EDGE
WELL CURB,CONSTRUCTION AND
PITCHING
CONSTRUCTION OF STEINING
MAKING OF ISLAND IF REQUIRED
WELL SINKING
PLUGGING,SAND FILLING AND
CASTING OF WELL CAP
LAYOUT
Accuracy of prime
importance
Should always be
cross checked by at
least two independent
surveys
Permanent theodolite
stations with the base
line on the bank will
be established to
mark reference points
CUTTING EDGE
MS cutting edge is made from
structural steel sections
It shall weight not less than 40 kg per
m Length
It should have proper anchoring into
well curb
MS Angle or 60 lb
MS
rail
Plate
Fillet Weld
Eccentri
c
loading
TILTS AND SHIFTS
(Correction)
Eccentri
c
loading
TILTS AND SHIFTS
(Correction)
Packing low
side of well
TILTS AND SHIFTS
A tilt of 1 in 100 and shift of D/40,
subject to a maximum of 150 mm is
taken into account in the design of well
foundation as per railway practice
As per IRC, Tilt 1in 80 and shift 150
mm is permissible.
If greater tilt and shifts occur, their
effect on bearing pressure on soil,
steining stresses, change in span etc.
should be examined.
Pneumatic Sinking of
wells
Required when open sinking cannot be
done and complete dewatering is also
not possible either due to sand blowing
or due to the inflow of water being so
heavy that pumping becomes
prohibitive in cost.
Pneumatic sinking is 5 to 6 times costlier
In India wells are so designed that open
sinking is carried out to the extent possible
The depth to which pneumatic sinking may
be done without undue risk to the lives of
the men may be taken as 33m
Pneumatic Sinking of
wells
Pneumatic sinking is done by fixing covers on
the dredge holes and pumping air into them so
that the compressed air pushes out all the
water up to the level of the cutting edge.
Men are then sent inside the well to carry out
excavation
Air locks are fitted to the wells to enable the
men and materials to move from inside to
outside of the wells and vice versa
Separate shafts are provided for the movement
of buckets full of materials and ladders for the
men
PNEUMATIC SINKING
SAFETY PRECAUTIONS
FOR WORKING
UNDER COMPRESSED AIR
IS:4188
AVERAGE RATE OF
SINKING
STRATA MEDIUM SIZE LARGE SIZE
WELL (cm) WELL (cm)
SANDY 60-90 50-60
STEP 1
DETERMINE W,H AND M UNDER COMBINATION
OF NORMAL LOADS WITHOUT WIND AND
SEISMIC LOADS ASSUMING THE MINIMUM GRIP
LENGTH
W = Downward load, H= Horz. Force at scour level
M= Moment about base including due to tilt and shift
STABILITY ANALYSIS
,
STABILITY ANALYSIS
STABILITY ANALYSIS
Where
STABILITY ANALYSIS
STABILITY ANALYSIS
ULTIMATE ANALYSIS
Ing self
ULTIMATE ANALYSIS
ULTIMATE ANALYSIS
ULTIMATE ANALYSIS
ULTIMATE ANALYSIS
CHECK FOR
THESE
COMBINATION
S WITH GIVEN
LOAD FACTOR
ULTIMATE ANALYSIS
WELLS ON COHESIVE
SOIL
References
Double D wells of
plan dimensions
18:0 m X 11.0 m:
A