Jihar Gas Plant Rehabilitation

Phase II
object of scope of work is to develop a new de
odifying the existing one taking into accoun
modifying
mum exploitation of facilities remaining in go
itions and that could be repaired, in order to
h the optimum solution for:
Gas conditioning and exporting enhanced gas
to pipeline ( if applicable ).

Liquid separation and stabilization in


stage-2.

No LPG production in this phase of rehabilitation.


The bidder shall conduct a site visit, and
prepare his proposal for optimum solution
based on available equipment in below
units of GTP:
Manifold Area 2000
HP & Test Separator 2100
Produced Water 2250
Dehydration Unit 2400
Fuel Gas 2860
Flare System 2840
Close Drain 2920
LTS Vessel V-2501
Gas Metering System 2590
Chemical Injection Demulsifier 2890
Chemical Injection Methanol 2880
Chemical Injection Corrosion 2885
Inhibitor
Hot Oil 2700
Diesel System 2960
demethanizer reboiler E-2501
Gas metering skid stage 2 X-1221
Note:
it's CONTRACTOR obligation to recheck
mentioned working areas in order to confirm
that mentioned areas is the required areas to
perform the project and add any new areas
may it will be needed
The Contractor scope of work in plant ( GTP) shall
Include but not limited to:

Check and rehabilitate all above mentioned process units and


utilities to achieve project target and insure operability in a
safe manner (piping, control system, heat tracing, fuel gas).
Carry out all required construction required for piping
re-routing.
Connecting hydrocarbon liquid separated in plant to stage-2
crossover for further processing.
Construct a new bypass around dehydration unit.
Construct new fuel gas line from a suitable place to HP fuel
system.
Construct a new bypass around brazed aluminum exchanger.

Perform all required modification to operate dehydration unit


without compressors and divert regeneration gas to gas
export Or to any other suitable destination without flaring
the gas.
Isolate fuel gas system, hot oil distribution system,
closed drain and flare systems for all not required
units in this phase of rehabilitation.
Rehabilitate diesel system ( Pumps, Lines, Material,
Electrical Connection, Control System ) to be able to
fill the tanks and use it as required.

Provide and Construct and install control System to cover


all project requirement controlling, safe guarding, fire
system , blow down system .

Construct control building suitable to project requirements.

Rehabilitate chemical injection system (Pump, Lines,


Electrical Connection, Control System, )
Supply and install hot oil system circulating new pumps
2 x 100 % ( one working + one standby) (the contractor shall
calculate the pump capacity as per hot oil requirement for this
for phase II rehabilitation, new hot oil pumps shall be rated
voltage 380 VX3 phase.
Supply and install new pumps(as per original design datasheet
for produced water system).
Rehabilitate metering systems units (2590/X-1221) .
Connect all equipment to power supply sources accordingly
and perform all required works to use existing cables and
procure all required cables if need .
Provide and install control systems to control all required
units .

The Contractor's Detailed engineering study shall be performed


by professional specialists that have the expertise to prepare
computer generated drawings, equipment specifications,
datasheets, calculations, requisitions and technical bid
evaluations and carried out in accordance with all RFQ
specifications and International Industry Codes and Standards.