Sie sind auf Seite 1von 30

FIELD TRAINING AT GAIBAN

BUILDERS AND DEVELOPERS, ICHALKARA

PRESENTED BY :
YASIN MUJAWAR
ARTI JAWALE
PRESENTED BY-POOJA APRADH
YASIN MUJAWAR
ABOUT PROJECT
ABOUT PROJECT
CURRENT PROJECT
AREA STATEMENT FOR 1BHK
AREA STATEMENT FOR 2BHK
AREA STATEMENT FOR RB
TABLE OF CONTENT
Procedure

Excavation:
Excavation was carried out mechanically.
P.C.C:
After the process of excavation, laying of plain
cement concrete that is PCC is done. A layer of 100
mm was made in such a manner that it was not mixed
with the soil.
It provides a solid base for the stepped footing and a
mix of 1:3:6 that is, 1 part of cement to 3 parts of fine
aggregates and 6 parts of coarse aggregates by
volume were used in it.
LAYING OF FOOOTING
Stepped footing is used
as the strata was hard.
The 10mm dia. Of bar is

used for footing mesh.

The depth of first step

is 200 to 300mm and

second is 300 to 450mm .


REINFORCEMENT OF COLUMN

16, 20 mm dia. Bars are used for column.


8mm dia. Rings are used for column.
Double rings are provided alternately.
For earthquake resistant construction ring ends
are bend inside properly.
FORM WORK

Forms or moulds or shutters are the receptacles in


which concrete is placed, so that it will have the
desired shape or outline when hardened.
Once the concrete develops adequate strength, the
forms are removed. Forms are generally made of the
materials like timber, plywood, steel, etc.
CONCRETING

Type of Cement Used : ULTRATECH


Grade of concrete in slabs and beams :M-20
Grade of concrete in coloumns:M-20
Grade of concrete in P.C.C work:M-10
Transit mixer is used for concreting.
BEAMS

The width of beam is 230mm and depth is varying


from 450mm to 600mm.
The grade of steel is Fe500
Stirrup was of dia. 8mm
Stirrups were provided for the shear reinforcement.
Spacing of End shear reinforcement 100mm to
200mm middle shear 150mm to 200
Bottom bar of 10mm,12mm,16mm were used.Curtail
bar of dia. 10mm,16mm,12mm used.
Top bar of 10mm,8mm,12mm were used.
Extra top bar ,springs are used.
BEAM SHUTTERING
Reinforcement Of Beam
SLAB

The thickness of slab is varying between 100mm to


125mm.
The steel of 8mm ,10mm and 12 mm diameter is used
for slab.
The grade of steel is Fe500.
SLAB SHUTTERING
SLAB DETAILS FOR
ROW BUNGLOW
BRICKWORK
wall of having width of 230 mm 100 mm and 150 mm used
cement mortar of 1:4 proportion shall be used
band of 100 mm thick of concreate shall be used for wall of
150 mm and 100 mm.
Lintel of having thickness 150 are used with reinforcement.
Sill of 100 mm thick shall provided below window with 150
mm horn for bearing.
PLASTERING

Plastering of both cement plaster and gypsum


plaster were used according to the owner
requirement.
Cement plaster of 20mm thick were used having
proportion of 1:4.
Fall ceiling, jamb work also carried out in site
CONCLUSION

This training is comprehensive in filling the gap


between the theoretical & practical studies
At the site there was a good management system
between the contractor, the consultant, and the
client.
I found that there was good understanding between
the supervisor and the workers, though works are
interdependent but there were no contradiction
between them.

Das könnte Ihnen auch gefallen