Sie sind auf Seite 1von 34

PROJECT MANAGEMENT

Using
Microsoft Project 2010

Presentation on Critical path method for managing


Bangladesh Bridge Authoritys (BBA) Resettlement Project

Development Design Consultants Ltd.


Founded in the year 1972

ISO 9001:2008
Certified
Company
Critical path method for managing Bangladesh Bridge Authoritys (BBA)
Resettlement Project

Contents
BBA projects information according to the
network diagram introduced by director sir
Theoretical knowledge up to critical path
Practical knowledge
Advanced uses
We are
GROUP 3
CPM Planner : Md. Khairul Alam
1. Md. Moshiuir Rahman
2. Md. Mehedi Hasan
3. AKM Mahmud-ul-Hasan
4. Mst Mariam Akthar
5. Ms Johana Sharmin
6. Shaolin Ferdousi (New member)
BBA PROJECTS DATA
BBA PROJECTS DATA
Task Name Date
M 1 Contract Signing Sun 11/22/15
M 2 Letter to Proceed Thu 11/26/15
M 3 End Preliminary Activities Sat 11/28/15
M 4 Submission of Inception Report Thu 12/17/15
M 5Final Submission of Inception Report Thu 12/31/15
M 6 Submission of Preliminary Design Report Sun 2/28/16
M 7 Submission of Detailed Design Report Sat 5/28/16
M 08 End Building Permission Fri 8/26/16
M 9 Submission of PQ Document Mon 3/21/16
M 10 Submission of Tender Document and Review by Client Mon 6/27/16
M 11 Starts Construction Thu 8/18/16
M 12 Submission of Completion Report Mon 8/6/18
M 13 Project Completion Report Thu 8/1/19
Critical path of BBA Project:
Task Duration
T 1.1 Kickoff Meeting 1 Days
T 1.2Review of Resettlement Plan/Report 4 Days
T 2.1Engineering Survey 7 Days
T 2.5Action Area Plan 7 Days
T 2.6Conceptual Architectural Design 7 Days
T 2.8 Presentation of Inception Report & Discussion with Client 7 Days
T 2.9Incorporation of Comments 7 Days
T 3.1Preliminary Architectural Design Including Finish Schedule 30 Days
T 3.2Preliminary Structural Design 15 Days
T 3.10Preliminary Cost Estimate 7 Days
T 3.11Presentation and Discussion on Preliminary Design & Cost Estimate 2 Days
T 3.12Incorporation of Suggestion & Modification of Preliminary Design Report 5 Days
T5.1 Land use Clearance from RAJUK 90 Days?
T5.2 Special Project Permit for Large & Specialized Project from RAJUK 90 Days?
T5.3Preparation of RAJUK Drawing 90 Days?
T5.4Permission from Fire Services and Defense 90 Days?
T5.5Permission from WASA 90 Days?
T5.6Permission from Electric Authority 90 Days?
T5.7Permission from Gas Authority 90 Days?
T5.8Permission from DMP 90 Days?
T5.9Permission from Local Ward Commissioner 90 Days?
T5.10Permission from Dhaka City Corporation 90 Days?
T5.11Permission from DTCA 90 Days?
T5.12Permission from KPIDC 90 Days?
T5.13Permission from Civil Aviation 90 Days?
T5.14Permission from Department of Environment 90 Days?
T 5.15Permission from RAJUK 90 Days?
T 7.1Supervision for Quality Control 710 Days
T 7.2Supervision for Time Control 710 Days
T 7.5Defect Liability 360 Days
What is Project management ?
Project management is a methodical approach to planning and guiding project
processes from start to finish. According to the Project Management Institute, the
processes are guided through five stages: initiation, planning, executing,
controlling, and closing. Project management can be applied to almost any type of
project and is widely used to control the complex processes of software
development projects.
Why Project Management?
Why Project Management?
Why Project Management?
What is a Project?
A project is a (temporary) sequence of unique,
complex, and connected activities that have one goal or
purpose and that must be completed by a specific time
within budget, and according to specification.

A Project may contain a series of activities designed to


achieve a specific outcome with a set of budget and
time-scale
Scheduling
A schedule is the conversion of a project action
plan into an operating timetable
It serves as the basis for monitoring and
controlling project activity
work changes daily, so this is essential
With the plan and budget, it is the major tool
for the management of projects
most scheduling is at the WBS level (tasks), not the
work package level
only the most critical work packages may be shown
on schedule
Network Scheduling Techniques
PERT was developed in 1958 for the Polaris
missile/submarine project
The Critical Path Method (CPM) was developed by
DuPont during the same time period
Initially, CPM and PERT were two different
approaches
CPM used deterministic time estimates and allowed project crunching
PERT used probabilistic time estimates
Microsoft Project (and others) have blended CPM
and PERT into one approach
Terminology
Activity - A specific task or set of tasks that
are required by the project, use up
resources, and take time to complete
Event - The result of completing one or
more activities. An identifiable end state
occurring at a particular time. Events use
no resources.
Network - The combination of all activities
and events that define a project
Drawn left-to-right
Connections represent predecessors
Terminology Continued

Path - A series of connected activities


Critical - An activity, event, or path which, if
delayed, will delay the completion of the
project
Critical Path - The path through the project
where, if any activity is delayed, the project
is delayed
There is always a critical path
There can be more than one critical path
Terminology Continued

Sequential Activities - One activity must be


completed before the next one can begin
Parallel Activities - The activities can take place at
the same time
Immediate Predecessor an activity that must be
completed before a particular activity can begin
An activity can be in any of these conditions:
It may have a successor(s) but no predecessor(s) -
starts a network
It may have a predecessor(s) but no successor(s) -
ends a network
It may have both predecessor(s) and successor(s)
- in the middle of a network
Gantt Charts

Developed by Henry L. Gantt in 1917


Shows planned and actual progress
Easy-to-read method to show current status
Gantt Charts: Advantages and
Disadvantages
Easily understood
Provide a picture of the current state of a
project

Difficult to follow with complex projects


Simple Schedule Gantt Chart

2006 John Wiley and Sons,


Inc.
Critical Path Method (CPM)

Critical path method is a project modeling technique


used by project planners worldwide for developing the
project schedule in types of projects; e.g. IT, research,
construction, etc.
Benefits of the Critical Path Method

It shows the graphical view of the project.


It discovers and makes dependencies visible.
It helps in project planning, scheduling, and controlling.
It helps in contingency planning.
It shows the critical path, and identifies critical activities
requiring special attention.
It helps you assign the float to activities and flexibility to
float activities.
It shows you where you need to take action to bring project
back on track.
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
Critical Path
THANKS

Das könnte Ihnen auch gefallen