Beruflich Dokumente
Kultur Dokumente
Productivity studies of
Tunneling Projects
By Siddharth Patel UC3212
Guided By:- Prof. Devanshu Pandit
Contents
1.1 Need, objective, scope of work 1 - Introduction
1.2 Research methodology
1.3 Expected outcome and limitation 2 Literature Review
Literature review
Data collection
3 Data Collection
Data analysis
Conclusion
Research findings 4 Data Analysis
Work schedule
5 - Conclusion
1 - Introduction 2 Literature Review 3 - Data Collection 4- Data Analysis 5 - Conclusion
1. To find the factors affecting productivity of tunnelling work and rank the
identified importance according to their impact on performance of
tunnelling using quantitative approach.
2. To find the performance indicators, Working productivity, Efficiency and
Utilization rate of TBM and to develop a performance prediction model of
Penetration rate-PR and Advance rate-AR of TBM.
Scope of work
Studying the quantitative (questionnaire) responses on factors
affecting productivity and raking them according to their importance
Pilot survey followed by Questionnaire survey of appropriate
sample size.
Hypothesis testing by P and F-test
Time cycle, ground conditions and parametric observation study for
tunnelling using Tunnel Boring Machine being adopted at various
stretches of Delhi MRTS Phase III corridor currently under
construction or already been constructed. (5 case studies)
Research methodology
Research
methodology
Limitations
This research work is restricted to Delhi metro projects. All the data
were gathered especially from Delhi metro.
The efficiency and prediction model are applicable to ground
conditions having UCS value between 20-260 Mpa and EPB Single
shield TBM.
However, both scenario can be applied to different conditions
specified but result might vary.
According to Delhis geological conditions, ground water table is not
above the bottom of the excavation level except at very few regions.
Literature Review
From the literature review of articles, journals, periodicals, books,
pilot survey and on-site observation, total 148 factors are identified.
According to each factors characteristics and from the primary
guidance of experts, all 148 factors were divided into five groups as
shown below.
The aim of this classification is to compress all factors under
respective group so that one can identify factors in the more arranged
way. The following are the 5 classifications of factors.
Management Environmental Physical
Breakdown TBM Parameters
conditions Conditions conditions
Geological Type of TBM and
Managerial skills Lining of tunnel TBM Mechanic
Conditions technique
Technical &
Efficiency of Hydrological Alignment of
TBM Hydraulic operational
work conditions tunnel
Parameters
Geological
Maintenance Obstructions Site condition TBM Electric
Parameters
Safety Back-up Supporting
regulations Mechanic parameters
Logistics
Back-up Electric
management
Financial Back-up
parameters Hydraulic
Other
Breakdown
Productivity Productivity is defined It is the ratio of
Efficiency of time
Utilization rate
Efficiency
as the ratio of Index of AR(m/day) to
can be calculated by
output to the PR(m/day) (Jamal
dividing time spent
corresponding index for all of the Rostami & Ozdemir,
of aggregate input 1993).
excavation process
(Thomas and by the total Utilization ratio is an
mathews, 1986). excavation timeindicator of TBM
Measured in m/day (Oraee, 2012). performance in terms
and mm/min for TBM of how much TBM is
It is the ratio of
Working productivity utilized in one day
productive time to
in terms of only time doing only the
net time but here
is calculated in excavation work since
minimum delays are
percentage(%) (Kasap considered by breakdowns and
et al., 2013) delays cause negative
comparing various
impact on productivity
results of inputs and
outputs. (Frough, Torabi, &
Tajik, 2012).
Quality should not be compromised to increase the above mentioned performance
indicators of TBM.
Data Collection
Data Collection
Case study data
Secondary Data
selection
Primary data collection
Sample Data
Survey form Pilot Main
size collection
preparation survey survey
calculation of forms
Type of sampling - Stratified sampling of 3 stratum Engineers, Operators, Skilled
personnel
Total population of projects - 126 Hydro Tunnels of length 220 Km 8 projects and
Metro projects in Delhi-5, Chennai-2, Jaipur-2 are under construction. (Kanjlia et al.,
2008)
Targeted projects- 5 projects - CC 34 - HCC-Samsung JV, CC 24 J Kumar-CREG JV, CC 32
ITD-ITD Cem JV, CC 27 L&T SUCG JV, CC 23 FEMC-Pratibha JV.
From the five targeted projects, the population size of 304 was calculated
and from that 64 respondents were targeted to get actual sample size of 32
considering response rate of 0.5.
Primary data collection
Sample Data
Survey form Pilot Main
size collection
preparation survey survey
calculation of forms
A pilot survey should be conducted of 10% of total sample projected for the main
survey to test the questionnaire. (9 respondents) (Connelly, 2008)
After pilot survey, 1 parameter Financial parameter was added.
61 personnel were approached to conduct the main survey.
The respondents were preidentified and approached in order to that. All the
respondents were from Delhi Metro projects only.
9 responses were collected by mail and 34 survey forms were being filled out by
visiting the respondents personally. (Response rate = 70.4%)
Primary data collection
Sample Data
Survey form Pilot Main
size collection
preparation survey survey
calculation of forms
Engineer Operator Skilled Engineer Operator Skilled
Sampling
Targeted population Respondents
Site Staff
Contractor 26 7 16 21 4 12
Cilent 3 2
Project Office Staff
Contractor 6
Cilent 5 4
41 7 16 27 4 12
Total Actual sample size = 32, Total responses =
64
43
Selection of Secondary data collection
case studies
Same minumum
radium of
curvature & lesser
Selection of
Type of alignment Grond water
Tunnel drive
tunneling - EPB differences table below
Single Shiled excavation
TBM level of tunnel
Data
collection
Selected
UCS value of
case study - Same cross-
geology
5 TBMs of section of
between 20 to
Data CC-27, Tunnel
260 Mpa
compilation DMRC
Selection of Secondary data collection
case studies
Drive
Case No. of Name
Drive location Length
Study TBM of TBM
Data (m.)
collection 1 TBM 1 THI 01 Munirka to R.K. Puram 1066 m
2 TBM 2 THI 02 Vasant Vihar to Munirka M.S. 1241 m
3 TBM 6 STEC Shankar Vihar to Mid shaft V.V. 712 m
4 TBM 8 CREG Vasant Vihar to Munirka 1241 m
Data 1 TBM 1 THI 01 Munirka to Munirka M.S. 350 m
compilation
5 TBM 7 Hitachi Vasant Vihar to Mid shaft V.V. 712 m
Selection of Secondary data collection
case studies
For regression analysis, Parametric observations and UCS value data
with PR and AR of respected 68 days were selected.
Coefficient of Internal
Economy
correlation Consistency
Pearsons Cronbach
Convenience
co-efficient Alpha
Spearman
Interpretability
co-efficient
Ranking of Factors affecting tunneling productivity
Hypothesis Testing
P-value is the smallest level of
significance that would lead to rejection
of the null hypothesis Ho with the given
data (Kothari, 2004).
It is clear that P-value is less than
0.05 and F-value is 8.19 which is
1 :
greater than 2.03< F, k, n-p = F0.05, 23, 22
The hypothesis testing was done at 0.05
significance level () and equal variance
< 2.07.
of each parameter is considered. Thus, it shows that there was enough
evidence to reject the null hypothesis
and accept alternate hypothesis
Ranking of Factors affecting tunneling productivity
Client
Management
conditions
5
4
Importance 3
TBM 2 Environment
Analysis of Parameters 1 al Conditions
all factors 0
Physical
Breakdown
conditions
Scenario of productivity
4000.0 70.00%
3500.0 3390.7 74.37
3032.7 60.00%
Productivity in %
3000.0 50.00%
Time in Hours
2500.0
40.00%
2000.0
1526.5 33.48% 30.00%
1500.0 1168.6
1000.0 20.00%
500.0 10.00%
0.0 0.00%
Original Efficient
Productive Time Non-productive time Productivity
Finding TBM performance indicators
Result of DEA analysis
Break- Productive Non-productive time
Management Environmen Machinery External
time Time Total Net time Productivity
Delays tal delays delays delays
Delay in hrs. 1562.37 54.01 1263.577 152.78
312.570 1526.547 4872 4559.284 33.48%
- Original 3032.737
% of each
6.42% 31.33% 32.07% 1.11% 25.94% 3.14%
category
625.049 40.782 419.768 82.966
312.570 1526.547
1168.565
Delay in hrs. Chance of
Decrease in delay
- Efficient improvement for 1864.172 61%
time in %
productive time
312.570 3390.72 1168.565 4872 4559.3 74.37%
% of each
6.42% 69.60% 12.83% 0.84% 8.62% 1.70%
category
Inefficiency 60.0% 24.5% 66.8% 45.7%
Efficient time in % of original 40.0% 75.5% 33.2% 54.3%
Finding TBM performance indicators
1800.00 Overall scenario of inefficiency of TBM 80.00%
1600.00 1562.37
70.00%
Percentage in-efficiency
67%
1400.00 1263.58 60.00%
Delay time in hrs.
60%
1200.00
50.00%
1000.00 46%
40.00%
800.00 625.05
419.77 30.00%
600.00 19.24% 24% 17.32% 20.00%
400.00
54.01 152.78 82.97
200.00 40.78 10.00%
1.43%
0.00 0.00%
0.27%
Management Environmental Machinery External delays
Delays delays delays
Delay factors
Original Efficient Weighted Inefficiency Inefficiency
Parameter Original Efficient Parameter Original Efficient Parameter Original Efficient
Breaktime 313 313 Breaktime 313 313 Breaktime 313 313
Productive Productive
1527 2387 1527 3390.72 Productive Time 1527 66-238
Time Time
Managerial skills 319 190
Efficiency of work 141 27
Management Maintenance 659 459
1562 625
parameters Safety regulations and
284 198
Inspection-CI
Logistics management 159 134
Environ. delays 54 40.78 Environmental delays 54 40.78
Non-
TBM Mechanic 169 130
Productive 3033 2172
Back-up Mechanic 82 63
time
TBM Hydraulic 291 277
Machinery Back-up Hydraulic 171 134
1264 419.77
delays TBM Electric 103 87
Back-up Electric 63 42
Other delays 319 220
TBM Parameters 67 60
External delays 153 82.966 External delays 153 82.966
Total 4872 4872 4872 4872 4872 4872
Parameter Original Efficient Parameter Original Efficient Parameter Original Efficient
Breaktime 313 313 Breaktime 313 313 Breaktime 313 313
Productive Productive
1527 2387 1527 3390.72 Productive Time 1527 66-238
Time Time
Managerial skills 319 190
Efficiency of work 141 27
Management Maintenance 659 459
1562 625
parameters Safety regulations and
284 198
Inspection-CI
Logistics management 159 134
Environmental
54 40.78 Environmental delays 54 40.78
Non- delays
Productive 3033 2172 TBM Mechanic 169 130
time Back-up Mechanic 82 63
TBM Hydraulic 291 277
Machinery Back-up Hydraulic 171 134
1264 419.77
delays TBM Electric 103 87
Back-up Electric 63 42
Other delays 319 220
TBM Parameters 67 60
External delays 153 82.966 External delays 153 82.966
Finding TBM performance indicators
90.0%
80.5% Individual factor-wise efficiency breakup
80.0%
Inefficiency in % Contribution in % of total time Weighted inefficiency
70.0%
60.0%
Percentage
50.0%
40.4%
40.0%
30.4% 30.3% 32.7% 30.9%
28.6%
30.0%
21.6% 23.1% 23.5% 21.3%
20.0% 14.5% 15.9% 15.9%
6.4%
10.0% 7.0% 6.2% 1.4% 7.0%10.3%
3.1% 3.5% 1.2% 3.7% 1.8% 4.9% 3.7% 2.3% 1.5% 3.4%
0.6% 0.3% 0.3% 0.9% 0.1% 0.6% 0.7% 0.4% 0.7% 0.4%
0.0% 2.8% 2.5% 4.4% 1.9% 1.4%
Factors
Finding TBM performance indicators
Utilization rate Here , R2 value of AR empirical equation is
lower so that Utilization rates was found.
Utilization factor is the ratio of AR to PR Therefore by multiplying U% to PR we can
(Frough et al., 2012a) (Rostami, J.,
Ozdamir, 1993). Database of 1085 days. get AR which has higher R2 value of 0.93.
60.00 30%
PR, AR and U% for different geology
Performance of
TBM in various
types of geology
Matrix Plot of AR in m/day, UCS, CUTTER HEAD TORQUE, SCREW CONVEYOR ROTATION
2 4 6 0 8 16
10
AR in m/day
AR in m/day 5
4
UCS in Mpa
UCS
3000
Cutter head
CUTTER HEAD TORQUE IN KNM 1500
torque -CT in KNm
0
16
Screw conveyor
8 SCREW CONVEYOR ROTATION SPEED I
rotation SC in RPM
0
0 5 10 0 1500 3000
3. Developing prediction model for PR and AR
PR - PENETRATION RATE in mm/min
Regression
Parameter 2 Regression Type Relationship
coefficient (R )
Polynomial 2nd
UCS (Mpa) 0.9145 PR = 0.4629*UCS2 -12.38*UCS+66.277
degree-Quadratic
Cutter head Polynomial 3rd PR = 1E-08*CT3 - 6E-05*CT2 +
0.3582
torque (KNm) degree-Cubic 0.0851*CT - 11.941
Screw conveyor
0.5188 Linear PR = 2.299*SC+2.3703
rotation (RPM)
AR - ADVANCE RATE in m/day
Polynomial 3rd AR = -0.0407*UCS3 + 0.5059*UCS2 -
UCS (Mpa) 0.678
degree-Cubic 3.5619*UCS + 15.368
Cutter head Polynomial 3rd AR = 2E-09*CT3 - 1E-05*CT2 +
0.3203
torque (KNm) degree-Cubic 0.0151*CT - 0.4437
Screw conveyor Polynomial 3rd AR = -0.0034*SC3 + 0.0645*SC2 +
0.2847
rotation (RPM) degree-Cubic 0.2166*SC + 2.0897
3. Developing prediction model for PR and AR
PR in mm/min 30
15 3
3000
0 2000
CT IN KNm
1000
2
4
6 0
UCS in M pa
45
PR in mm/min 30
15 1
15
10
Surface plot of PR in mm/min 0
S C in R PM
5
v/s UCS in Mpa and SC in RPM 2
4 0
6
UCS in M pa
3. Developing prediction model for PR and AR
Regression
Output Input independent Regression
coefficient Relationship
variable variables Type
(adj. R2)
UCS (Mpa)
PR = 50.4708-
PR in Cutter head torque (KNm) Linear
0.9381 7.4238*UCS+00016*CT
mm/min Screw conveyor rotation multivariable
+02464*SC
(RPM)
UCS (Mpa)
AR = 13.49026-
Cutter head torque (KNm) Linear
AR in m/day 0.785 1.7302*UCS+0.0009*C
Screw conveyor rotation multivariable
T-0.1348*SC
(RPM)
PR in UCS (Mpa)-1500 days Linear single PR = 56.3125-
0.953
mm/min data variable 7.9434*UCS
UCS (Mpa)-1500 days Linear single AR = 6.3451-
AR in m/day 0.899
data variable 0.4111*UCS
3. Developing prediction model for PR and AR
PR in mm/min
1. Model adequacy checking 40
2. Standardized ,studentized residual 30
analysis and Cooks distance
formula 20
3. Model normality check 10
4. Check for multicollinearity y = -0.0143x2 - 8.0706x + 58.02
R = 0.99
5. Normal P-P Plot of residuals 0
0 2 4 6 8
6. Line Fit plots
UCS in Mpa
Actual PR in mm/min
3. Developing prediction model for PR and AR
Regression Model Adequacy checking
Residual Analysis
A residual is the vertical
distance between a data
point and the regression
line. Each data point has
one residual.
They are positive if they
are above the regression
line and negative if they
are below the regression
line. If the regression line
actually passes through
the point, the residual at
that point is zero. (Montgomery & Runger, 2003)
Standardized residuals
The standardized residuals
are more useful than
ordinary residuals when
assessing residual magnitude.
For instance outliers
(observations that do not
appear to fit the model that
well) can be identified as
those observations with
standardised residual values
above 3.3 (or less than -3.3).
(Montgomery & Runger, Outlier
2003)
Day 64 is having standardized residual < -3.3 so this can be
called as an erroneous observation to this model. This data
should be further checked by statistical formulas
3. Developing prediction model for PR and AR
Influential observation(Montgomery & Runger, 2003)
r64 = -4.04967
It is checked by
variance inflation
factor VIFs should not
exceed 4 or 5.
(Montgomery &
Runger, 2003)
Box Plot of PR v/s UCS code range
Research Findings
1. Factor affecting tunneling productivity were found and ranking of all factors
was done.
2. Effectiveness of identified factors to the inefficiency in TBMs performance
and area of improvements were stated which helps to improve productivity
and utilization rate.
3. An empirical models to predict PR and AR related to UCS (Unconfined
Compressive strength) and significant machine parameters were developed.
Drafting
Corrections
Conclusions
Survey Forms
Literature review
Compiling of Data
Schedule of
submissions &