Beruflich Dokumente
Kultur Dokumente
4.1 Acres
11.0864 cfs Storm Water
2.5 cfs Process Water
1.89 Acres
4.72 cfs Storm Water
11.55 Acres
21.62 cfs Storm Water
5.5 cfs Process Water
5.07 Acres
8.44 cfs Storm Water
Seven Systems
System #1. The gravity system for the yellow drainage area which
flows directly to Limestone creek behind Burgess.
System #2. The pressurized system which is located in the Orange
area and pumps to the gravity sewer beginning at Burgess. A retention
pond located on KTs property is part of this system.
System #3. This system is located in the blue area and is a gravity
system which flows thru Burgess and Huber then thru an open ditch to
the waste pond. This system has several bottlenecks. Both the blue
and red drainage areas contribute to this area.
System #4. This is the drainage area on Burgesss property (Red). This
transports water to the blue gravity system.
System #5.The storm drainage for the R&D area (green area).
System #6. The process and storm drainage for the main plant (pink
area).
System #7.The pressurized system that returns waste to the Avant and
Hall Mines via two Hazleton 4J pumps.
SYSTEM #1
SYSTEM #3
SYSTEM #7
SYSTEM #2
SYSTEM #4
SYSTEM #6
SYSTEM #5
Reject Pump to Avant Mine
SV- AM System Curves For Various Reject Line Combinations
2000
System Curve for 6in and 8in combo
2 Hazleton 4J @1490
1500
1000
Head(ft)
500
0
0 100 200 300 400 500 600 700 800 900
-500
GPM
Reject to Hall Mine
SV-HM 6" REJECT SYSTEM CURVE
2000
500
0
0 100 200 300 400 500 600 700
-500 GPM
Problem Areas
Catch Basin at Burgess
Sewer Pipe by Beck Blvd. and thru
Huber
Open Drainage Ditch behind Huber
Drainage Summary Chart
-17.02
Possible Solutions
Presentation of Options
Pros and Cons of Options
Economic Analysis of Options
Miscellaneous
Presentation of Options
1. Install a parallel gravity sewer
through Burgess parking area,
along Beck Blvd., and through
Huber. Clean the open ditch
improve slopes and concrete
bottom or install pipe.
Option #1
30 Sewer Pipe
Stream-Line Sewer
Ditch Behind Huber
Presentation of Options
2. Install Clarifier and route all
process water and all storm water
with exception to the yellow area
to a larger pond at KT. Clarified
water will be released to creek and
solids will be pumped to mine.
1 Acre
1000GPM; 6 DAY RECOVERY
4.5 Acres
8.7MG
2400 GPM @2%
Presentation of Options
3. Install a high level overflow at the
upper gravity catch basin in
Burgess parking lot. Reroute any
storm water which exceeds the 18
pipe capacity to the lower existing
KT pond. The lower KT pond will
need to be dredged to
accommodate additional storm
water.
Presentation of Options
4. Send all of the blue area process
and storm water to the sump
pumps located in the orange area.
Pump the total flow across the plant
to the upper 42 sewer.
Pros and Cons of Options
Option 1 30 Parallel Sewer
Advantages Disadvantages
No additional Still in Joint Pond
pumping Initial Costs
Maintenance
Friendly
Prevents Overflow
to Creek
Option 2 Clarifier
Advantages Disadvantages
Free of Joint Waste Highest Initial
Pond Costs
Minimal Dredging Highest
@ KT Maintenance
Prevents Overflow Overall Reliability
to Creek
Option 3 Storm Water to KT
Advantages Disadvantages
Lowest Initial Cost Still in Joint Pond
Catches Additional Additional Volume
Pollution Point Required @KT
Ditch Needs Less Pond
Initial Cleaning Still Need to
Allows Full Pipe Maintain Ditch
Flow to Waste
Pond
Rainwater Only to
KT
Option 4 Blue Area to Sump
Advantages Disadvantages
No Ditch Still in Joint Pond
Maintenance Additional Volume
Prevents Overflow Reqd. @ KT Pond
to Creek Additional
Pumping Cost
3rd Pump Reqd.
Reliability on
Pumps
Miscellaneous
Line to Mines for Dredge
16 ID allows 3500gpm
Pump Solids Directly to Mine
Est. Cost at $3,000,000