REB 670

Busbar Protection Training


ABB Power Technologies AB, 2006

2006-09-25
1
Application Areas for REB 670

Centralized Busbar
Protection from 4 up to 24
CT inputs

Differential, BFP & Non-Dir


OC Protection for:

Busbars
Meshed corners,
T-protection
ABB Power Technologies AB, 2006

2006-09-25
2
Experience from RADSS and REB 103
Instantaneous measuring of power system quantities
Incoming (iin), Outgoing (iout) & Differential (id) Currents

LA L LX

REB 670
A-bus Very
Other R R R
relays Important
Breaker BFR BFR BFR
failure
N
Quantities
N
UA3
SR I R1

TMD
RZ1 RZ2 TMZ AR RD3 Ud3
I A3 I B3 I X3 IL
UZ1 D2
iout DR
Id1 id
US
RD11
IT3 iin
ABB Power Technologies AB, 2006

I R2

2006-09-25
3
RADSS & REB analogue predecessors
RADSS
First low impedance relay to be
introduced in the world market
Percentage restraint bus differential
relay for phase and earth faults
1-3 ms fault detection, 8-13 ms to trip
Requires SLCE auxiliary CTs to match
main CT ratios
12000 Zones world-wide

REB 101/103
More compact, uP based
ABB Power Technologies AB, 2006

Short operating time


Fault detection within 1ms
2000 Zones world-wide

2006-09-25
4
RED 521 & REB 670 numerical successors

RED 521
High speed differential algorithm
Open CT detection
800 units sold over period of 5 years
(2001-2006)

REB 670
Software driven zone selection
More differential zones
ABB Power Technologies AB, 2006

Disturbance recorder
Graphical configuration tool
IEC 61850 communication

2006-09-25
5
REB 670 Training

REB Variants and their Hardware Description


ABB Power Technologies AB, 2006

2006-09-25
6
REB 670*1.0 Available Versions

3-Phase Version*
Two measuring zones
Breaker Failure, Overcurrent,
End Fault & Autorecloser
4 or 8 bays

1-Phase Version*
Two measuring zones
Breaker Failure, Overcurrent,
*Phase segregated End Fault & Autorecloser
ABB Power Technologies AB, 2006

measurement One terminal per phase


Summation available
12 or 24 bays

2006-09-25
7
REB 670*1.0 Available Variants

12I + max 3*IO Cards 12I/24I + max 11*IO Cards

Used for small, fixed zones like Not Applicable


3Ph, 4 bays, 2 zone
T protection, meshed corner,
BFP & OC protection optional!
ring bus etc.
A20

Not Applicable
3Ph, 8 bays, 2 zone Used for substations/zones
BFP & OC protection optional! with up to 8 CT inputs.
A31

Used for substation with up to


Used for substation with up to
12 CT inputs. Only three IO
1Ph, 12 bays, 2 zone 12 CT inputs.
cards available. No extension
(three IEDs required) Possible to extend to 24 CT
possibilities to 24 CT inputs!
BFP & OC protection optional! inputs. Optional LDCMs can be
Good solution for stations with
used to share binary IO.
fixed zones (i.e. 1 breaker).
ABB Power Technologies AB, 2006

B20 B21

1Ph, 24 bays, 2 zone Not Applicable Used for substation with up to


(three IEDs required) 24 CT inputs. Optional LDCMs
BFP & OC protection optional! can be used to share binary IO.

B31

2006-09-25
8
Available I/O-modules 19 case

IOM
(max 3st)

BOM
of 19 Case
(max 3st)
10+2 binary outputs
1 TRM 12I only! and 8 binary inputs
BIM
up to 3 I/O modules (max 3st)
24 binary outputs
(12*2contacts)
ABB Power Technologies AB, 2006

16 binary inputs

2006-09-25
9
Available I/O-modules 1/1 19 case

IOM
(max 11st)

BOM
Full of 19 Case
(max 4st)
10+2 binary outputs
1 or 2 TRM 12I only! and 8 binary inputs
BIM
up to 11 I/O modules (max 11st)
24 binary outputs
(12*2contacts)
ABB Power Technologies AB, 2006

16 binary inputs

2006-09-25
10
Communication Capability

Front connection:
RJ45 Ethernet port
Protocol: TCP/IP (transparent
SPA)
Rear Communication
IEC61850
IEC103
SPA
LON
ABB Power Technologies AB, 2006

2006-09-25
11
Remote End Communication Capability

LDCM with direct fiber (multi mode)


Max 3 km w ith LDCM and
multimode fibre

CM CM
LD LD

CM DCM
LD L

192 Binary Signals


in each direction
ABB Power Technologies AB, 2006

2006-09-25
12
View from rear side, 1/1-box, with Comms Ports

11*CAN
3*PCI
OEM

PSM
SLM

TRM

LDCM
(4 pieces)
ABB Power Technologies AB, 2006

I/O GSM CPU AD2 AD1

2006-09-25
13
REB 670 Training

Application Possibilities
ABB Power Technologies AB, 2006

2006-09-25
14
Three-Phase Terminal; 4/8 Bays- Double Zone

Application Areas:
Smaller Buses (up to 8 CTs per zone)
REB 670; 3Ph Single Busbar Stations (with Transfer Bus)
2 Zones (A & B);
1 Breaker Stations
8 Bays
Double Busbar Stations (with Transfer Bus)
Zone Interconnection included in the design

No switching in CT secondary circuits


ABB Power Technologies AB, 2006

2006-09-25
15
REB 670 3- Ph; BBP, BFP & EnFP for single buses

ZA ZB
ZA

Single Busbar Single Bus with bus tie CB


up to 4/8 feeder bays up to 3/7 feeder bays on each side

ZA

ZA ZB

ZB

H type station with bus-section CB


or sectionalizing disconnector
ABB Power Technologies AB, 2006

T connections
Alternative CT Location

2006-09-25
16
REB 670 3- Ph, BBP, BFP, EnFP for 1 CB stations

ZA

ZB

1 Breaker Stations
up to 4 diameters

ZA

.. .
ZB
ABB Power Technologies AB, 2006

1 Breaker Stations
up to 8 diameters

2006-09-25
17
REB 670 3- Ph; BBP, BFP & EnFP for Double CB stations

ZA

.. .

ZB

Double Breaker Station


up to 8 feeders

Alternative CT Location
ABB Power Technologies AB, 2006

2006-09-25
18
REB 670 3- Ph; BBP, BFP & EnFP for double buses
ZA
.. .
ZB

Double Bus with bus-coupler CB


and up to 6/7 feeder bays

ZA
.. .
ZB
.. . Transfer Bay
Transfer Bus
.. . Isolator replica in REB 670*1.0
by CAP 531 Configuration
ABB Power Technologies AB, 2006

Double Busbars with bus coupler CB and Transfer Bus


up to 6/7 feeder bays

2006-09-25
19
Optional Measuring Point
Scheme Layout for Double Busbar; 2 Zones/7 feeders
700

EQUIPMENT INCLUDED in the PANEL:


ABB

1 pcs 3 phase, Busbar protection terminal REB 670*1.0


- two differential zones
- check zone
- eight BFP relays
- eight OC feeder backup protection (EnFP)
- internal disconnector replica logic
- internal individual bay tripping logic
- disconnector status supervision
ABB Power Technologies AB, 2006

2006-09-25
20
Single-Phase Terminal; 12/24 Bays- Double Zone
Application Areas:
REB 670; Ph-L1 Bigger Buses (up to 12/24 bays per zone)
2 Zones (A & B); Single Busbar Stations (with Transfer Bus)
24 Bays 1 Breaker Stations
Double Busbar Stations (with Transfer Bus)
REB 670; Ph-L2 Load Transfer is included into the design
2 Zones (A & B); 3 Terminals required for complete scheme
24 Bays LDCM available to share binary IO

REB 670; Ph-L3 No switching in CT secondary circuits


2 Zones (A & B);
24 Bays
ABB Power Technologies AB, 2006

2006-09-25
21
REB 670 1- Ph; BBP, BFP & EnFP for single buses

ZA
.. . ZA
.. . .. .
ZB

Single Bus
Single Bus with bus-section disconnector
up to 12/24 feeder bays
up to 12/24 feeder bays (i.e. 12+12; 16+8 etc.)

ZA ZB ZA ZB
.. . .. . .. . .. .
ABB Power Technologies AB, 2006

Single Bus with bus-section CB, up to Single Bus with bus-section CB


11/23 feeder bays (i.e. 12+11; 10+13 etc.) up to 11/23 feeder bays on each side

2006-09-25
22
REB 670 1- Ph; BBP applications for 1 CB stations

ZA
ZA

.. . .. .
ZB
ZB
1 Breaker Stations 1 Breaker Stations
up to 6 / 12 diameters up to 12 / 24 diameters
ABB Power Technologies AB, 2006

2006-09-25
23
REB 670 1- Ph, Complete BBP, BFP & EnFP for 1 CB Stations!

ZA

.. .

ZB

Bus Diff, CB Fail & EnFP


1 Breaker Stations
up to 4/8 diameters
ABB Power Technologies AB, 2006

2006-09-25
24
REB 670 1- Ph; BBP, BFP & EnFP for Double CB stations

ZA ZA

.. . .. .
ZB ZB

Double Breaker Station Double Breaker Station


up to 6 / 12 feeders up to 12 / 24 feeders
Alternative CT Location
ABB Power Technologies AB, 2006

2006-09-25
25
REB 670 1- Ph; BBP, BFP & EnFP for double buses

ZA
.. .
ZB

Double Bus with bus-coupler CB


up to 22/23 feeder bays
ABB Power Technologies AB, 2006

Isolator replica in REB 670*1.0


by CAP 531 Configuration

2006-09-25
26 Optional Measuring Point
REB 670 1- Ph; BBP, BFP & EnFP for double bus & transfer

ZA
.. .
ZB
.. .
Transfer Bus
.. .
Combined Bus-Coupler
& Transfer Bay

ZA
.. . Bus-Coupler Bay
ZB
.. . Transfer Bay
Transfer Bus
.. .
ABB Power Technologies AB, 2006

Isolator replica in REB 670*1.0


by CAP 531 Configuration

Double Busbars with Transfer Bus


up to 22/23 feeder bays

2006-09-25
27
Scheme Layout for Double Busbar; 2 Zones/22 feeders
700

EQUIPMENT INCLUDED in the PANEL:


ABB

3 pcs 1 phase, Busbar protection terminal REB 670*1.0


- two differential zones
- check zone
- 24 BFP relays
- 24 OC feeder backup protection (EnFP)
- internal disconnector replica logic
- internal individual bay tripping logic
- disconnector status supervision
ABB Power Technologies AB, 2006

2006-09-25
28
REB 670 1- Ph; BBP, BFP & EnFP for double buses

Main 1 Main 2

.. . .. .
Reserve 1 Reserve 2

Four Zone Double Bus with two bus-coupler CBs and two
bus-section CBs and up to 20/21 feeder bays on each station side

Main 1 Main 2

.. . .. .
Reserve 1 Reserve 2
ABB Power Technologies AB, 2006

Four Zone Double Bus with two BC-CBs one BS-CB and one sectionalizing
disconnector with up to 18-20 feeder bays in the whole station

2006-09-25
29 Optional Measuring Point
REB 670*1.0; 1-ph version Summation Principle

Buses up to 24 bays per zone


REB 670; 1 Ph Single Busbar
2 Zones (A & B);
1 Breaker Systems
24 Bays
Double Busbar
Same applications possible as for 1Ph solution
Software Driven Zone Selection
+ N times BFP ???
OCP (EnFP) ???
DR, ER, EL ???
Cost effective Solution
ABB Power Technologies AB, 2006

N 8

2006-09-25
30
User-
Friendliness Pre-configured REB670 ready to use

Single zone applications


Two zone applications without
need for any zone selection
(e.g. 1 CB stations)
Double busbar stations with zone
selection using busbar
disconnectors a & b aux contacts
Double busbar stations with zone
selection using only busbar
disconnectors b aux contact
Direct replacement for RED 521
ABB Power Technologies AB, 2006

2006-09-25
31
Available Configurations X01, X02 & X03

X01 = Just BBP for simple stations layouts (i.e. 1 CB, Double
Breaker, Single Breaker, or for double busbar-single breaker
stations where Zone Selection is done by using just b contacts).
Available for all five versions A20, A31, B20, B21 & B31.
Direct replacement for RED 521
X02 = Just BBP for double busbar-single breaker stations where
Zone Selection is done by using a&b contacts from disconnectors
and breakers. Available for versions A31, B21 & B31
X03 = BBP with BFP, EnFP & OCP for double busbar-single breaker
stations where Zone Selection is done by using a&b contacts from
disconnectors and breakers. Available for versions A31, B21 & B31

For other station layouts or functionality CAP 531 configuration shall


ABB Power Technologies AB, 2006

be arranged by the end user.


Make country/end-customer specific solution

2006-09-25
32
REB 670 Training

IED Features
ABB Power Technologies AB, 2006

2006-09-25
33
Features in REB 670*1.0

Fast differential protection (12ms)


Additional sensitive differential protection characteristic
Smart open CT detection
Check zone is available
Id and Iin level supervision
Advanced zone selection
Graphical configuration tool
Integrated zone interconnection (i.e. Load transfer)
Complete disconnector and/or CB position supervision & alarming
Proper CB failure for every CT input
4-stage backup overcurrent for every CT input
ABB Power Technologies AB, 2006

End fault protection by 4th overcurrent stage


Disturbance and event recorder

2006-09-25
34
Differential Protection in REB 670*1.0

Very fast, minimum operating time 10 ms


Extremely stable for external faults
Completely phase segregated measurement
Differential algorithm not dependent on the number of connected feeders
Very low CT requirements, only 2 ms before CT saturation
Any CT ratio difference can be accommodated
Settings entered directly in primary amperes
Id [Primary Amps]

Operate
I in
ABB Power Technologies AB, 2006

region
I=
d

Differential protection
operation characteristic
Diff Oper Level

s=0.53

2006-09-25
Iin [Primary Amps]
35
Sensitive Differential Protection in REB 670*1.0

Used in low impedance earthed power system or in other


special applications
It has the following characteristics:
Freely settable characteristic with time delay possibility
Automatically blocked for heavy ph-to-ph faults
External release via binary signal (i.e. from open delta
voltage, transformer neutral point current, etc.)
Sensitive
differential
protection
Id [Primary Amps]

Operate
ABB Power Technologies AB, 2006

I in region
I=
d

Differential protection
operation characteristic
Diff Oper Level
Sens Iin Block
Sensitive Oper Level
s=0.53

2006-09-25
36
Iin [Primary Amps]
ABB Power Technologies AB, 2006

37
2006-09-25
CT Requirements
Open CT detection for REB 670*1.0

Slow and Fast Open CT detection (same as in RED 521*1.0)


Separately Settable influence of slow and fast open CT logic:
Off (switched off)
Block (Block diff protection, same as in REB 670*1.0)
Supervise (Doesn't block, just increase minimum
differential operation level as shown below)
Blocking only of affected phase and zone

Sensitive
differential
protection
Id [Primary Amps]

Operate
ABB Power Technologies AB, 2006

I in region
I=
d

Differential protection
operation characteristic
Diff Oper Level OCT Logic Supervision Level
Sens Iin Block
Sensitive Oper Level
s=0.53

2006-09-25
38
Iin [Primary Amps]
Check Zone in REB 670*1.0

Independent check zone available


Can be switched off (default setting)
Freely settable which CTs shall be connected to check zone
Provide stability in case of problem with disconnector
auxiliary contacts ( stuck contacts or wiring problems)
Id [Primary Amps]

Operate
region
ABB Power Technologies AB, 2006

Oper Level
s=0.0-0.90 (settable)

Iout [Primary Amps]

2006-09-25
39
Zone Supervision in REB 670*1.0

Two new types of Diff Zone supervision are available


Id> traditional supervision of differential current level
with settable time delay(i.e. can be used as alarm or for
automatic reset of OCT condition)

Iin> incoming current supervision, without time delay


(i.e. can be used to trigger DR for external faults)
ABB Power Technologies AB, 2006

2006-09-25
40
Disconnector/CB supervision & alarming

For every disconnector/CB status is determined from the


status of aux contacts (i.e. a & b contacts)
Two schemes available
ABB Power Technologies AB, 2006

Position of a disconnector/CB can be forced to OPEN or


CLOSED by a parameter setting

2006-09-25
41
User Friendliness in REB 670*1.0 (3-Ph & 1-Ph)

Easy to set, configure, install & use


Very easy to adapt to simple buses
Pre-configured for most typical substation layouts

BayConnections Matrix on built-in, front HMI with User


Settable Individual Bay Names
SwitchgearStatus Matrix on built-in, front HMI with
Settable Individual Primary Switchgear Object Names
Visible User Defined Bay Names when setting change is
performed from the built-in, front HMI or PST
ABB Power Technologies AB, 2006

Visible User Defined Switchgear Object Name when


setting change is performed from the built-in,
front HMI or PST

2006-09-25
42
Switchgear Status Monitoring Matrix
ABB Power Technologies AB, 2006

User Settable Switchgear


Switchgear Object
Names Status

2006-09-25
43
Bay-Connections Status Monitoring Matrix

User Internally Connections


Settable Used Bay to internal
ABB Power Technologies AB, 2006

Bay Name FB zones

2006-09-25
44
REB 670 Training

Principle of Operation for the Diff Algorithm


ABB Power Technologies AB, 2006

2006-09-25
45
REB 670 Features Differential Algorithms

Main Features of New Numerical Differential Algorithm:


From all connected feeder currents iin , iout & id are Numerically
Calculated
All values are calculated from instantaneous sampled values
Algorithms not dependent on the number of connected CT inputs

Differential
iin Protection
iout
Zone
ABB Power Technologies AB, 2006

Patented

Regardless of number of connected feeders


id

2006-09-25
46
REB 670 - The operating principles

Physical Meaning of these three quantities


Zone Operating Incoming Current iin Outgoing current iout Relationship
Condition between
iin, iout, & id
Normal Through Load Current to the Load Current from the iin = iout
Load differential zone differential zone Id 0
External Fault Fault Current to the Fault Current from the iin = iout
without CT differential zone differential zone Id 0
saturation
External Fault with Fault Current to the Fault Current from the iin >> iout
CT saturation differential zone differential zone Id iin
Internal Fault Fault Current to the Outfeed current from the iin >> iout
differential zone faulty differential zone Id iin
ABB Power Technologies AB, 2006

(usually negligible in
practice because Zfault <<
Zload)

2006-09-25
47
REB 670 - Description of calculation
Calculation of instantaneous diff current id is made as a sum of all latest
samples from all N feeders connected to the differential zone
jN
id i
j 1
j

Sum of all latest current samples with positive and negative values are made
(i.e. sum of all currents which flow towards the bus & sum of all current which
flow away from the bus)
j M jN
SP i
j 1
()
j SN i
j M 1
()
j

Instantaneous incoming & outgoing currents are then calculated


i _ in max SP, SN
ABB Power Technologies AB, 2006

i _ out min SP, SN

2006-09-25
48
REB 670 RMS calculation
As the instantaneous values change over time, thus RMS values of of
the incoming, diff and outgoing currents are calculated as well
These are calculated over the last power system cycle (20ms long
moving window for 50Hz system)
Thus values for the last 20 samples are stored in the internal memory
Calculated values of I_IN and ID are displayed as service values
So we now have I_IN, I:_OUT, ID & i_in, i_out, id for the algorithms
They are fed into differential and open CT algorithms
It shall be noted as well that the following relationship exist between
these three quantities:

id=i_in - i_out & ID=I_IN - I_OUT


ABB Power Technologies AB, 2006

2006-09-25
49
REB 670 - Open CT detection

If a CT is open circuited by human error or some other reason, the diff relay
may mal-operate and trip the whole bus
RED provided with a phase segregated open CT detection algorithm that
does not depend on the number of connected feeders.
Fast operating logic
Logic based on fact that total through load current is the same before and
after the CT is opened( i.e no big changes 3 secs before open CT
detected)
When one of the CT is opened then:
Iin = Iout one cycle before
Iin remains unchanged
Iout drops for more than set Open CT Level
Id goes above set Open CT Level
ABB Power Technologies AB, 2006

Iout+Id=Iin one cycle before (as in step 1 above)


If all the above are validated, open CT declared, trip of that phase blocked
and alarm issued

2006-09-25
50
REB 670 - Open CT detection

Slow operating logic


Detects most abnormalities in the CT secondary circuits or zone
selection logics but with delay of 1000 power system cycles (i.e 20
sec for 50 Hz systems). Logic based on fact that Iin = Iout at normal
load conditions
To prevent operation for low level noise signals, the through load
current must be > 10% of Diff Oper Level parameter
Logic operates when
No big through load current changes during last five seconds
In>>Iout ( i.e. 0.9*Iin>Iout)

If all the above are validated for more than 1000 cycles, open CT
ABB Power Technologies AB, 2006

declared, trip of that phase blocked and alarm issued

2006-09-25
51
REB 670 - The operating principles
Next slides will try to visualize the behavior of REB 670
terminal during:
Internal Fault
External Fault
Open CT condition
Disturbance always happen at sample No 41 on all of the
following slides
ABB Power Technologies AB, 2006

2006-09-25
52
Quick operation for Internal Fault

Internal Fault

16
14
REB 670 detects that
12
I_IN goes up while
10 I_OUT goes down at i_in
Current

the beginning of the


internal fault and i_out
8 enables fast tripping
I_IN
6 I_OUT
4
When ID>Diff Operation Level
trip is issued
2
0
1
6
11
16
21
26
31
36
41
46
51
56
61
66
71
76
81
ABB Power Technologies AB, 2006

Samples

2006-09-25
53
Proper & secure restrain during External Fault
REB 670 detects this
External Fault short interval when
i_in=i_out (after every
16 fault current zero
crossing) and restrain
properly during external
14 fault

12

10
i_in
REB 670 detects that
Current

I_IN=I_OUT at the i_out


8
beginning of the I_IN
external fault
I_OUT
6

0
1

13

17

21

25

29

33

37

41

45

49

53

57

61

65

69

73

77

81
ABB Power Technologies AB, 2006

Samples

2006-09-25
54
Fast Open CT Algorithm
REB 670 detects that
I_IN doesn't change Open CT
while I_OUT goes
down when some of
1,6 the CTs is open/short
circuited
1,4

1,2

1
i_in
Current

ID>Open CT Level i_out


0,8 Diff Operation Level
second condition I_IN
fulfilled & RED is Must be set to higher value than
0,6 Open CT Level I_OUT
blocked

0,4

0,2

0
1

13

17

21

25

29

33

37

41

45

49

53

57

61

65

69

73

77

81
ABB Power Technologies AB, 2006

Samples

2006-09-25
55
REB 670*1.0 Tripping Criteria for Internal Faults
Sensitive Differential protection
Set to On in PCM 600 tSensDiff
&
External Enable Signal

Differential Current Level


Id> Differential Operation level (setting)

RMS Tripping Criteria


Id_mod > 0,53 x Iin

Instantaneous Tripping Criterion >1 Trip


Properties of iin, iout and id &
Zone blocked
ABB Power Technologies AB, 2006

Open CT alarm
(Setting)

Check zone
(Setting)

2006-09-25
56
REB 670 Training

PCM 600 Tool


ABB Power Technologies AB, 2006

2006-09-25
57
Toll => PCM 600 for Whole 670 Series
ABB Power Technologies AB, 2006

2006-09-25
58
PCM 600 => CAP 531 + SMT + PST
ABB Power Technologies AB, 2006

PST

2006-09-25
59
Settings Selecting Presentation Format
ABB Power Technologies AB, 2006

2006-09-25
60
PCM600 Signal Matrix Tool

The Signal Matrix Tool is used to define the mapping (connection)


between the virtual inputs / outputs (analog and digital) and the real
(actual) inputs / outputs (analog and digital)
ABB Power Technologies AB, 2006

2006-09-25
61
PCM600 Signal Matrix Tool = Glue to Hardware

Analog inputs (X=Connection to This Hardware Input)

TRM Card Hardware


ABB Power Technologies AB, 2006

Virtual Analogue Inputs in


CAP 531 Configuration

2006-09-25
62
PCM600 Signal Matrix Tool

Binary inputs (X=Connection to This Hardware Input)

BIM Card Hardware

POSITIONS
QA1-OPEN
QA1-CLOSED
QB1-OPEN
QB1-CLOSED
QB2-OPEN
QB2-CLOSED
QB9-OPEN
QB9-CLOSED
QC9-OPEN
QC9-CLOSED
ABB Power Technologies AB, 2006

Virtual Binary Inputs in


CAP 531 Configuration

2006-09-25
63
PCM600 Signal Matrix Tool

Binary outputs (X=Connection to the Contact Output)

BOM Card Hardware


ABB Power Technologies AB, 2006

Virtual Binary Outputs in

2006-09-25
64
CAP 531 Configuration
PCM600 Signal Matrix Tool

HMI LED

All virtual IN/OUT signals


defined in CAP 531
can be connected to 18 HMI LEDs
ABB Power Technologies AB, 2006

2006-09-25
65
REB 670 Training

IED Software Structure


Function Block Description
ABB Power Technologies AB, 2006

2006-09-25
66
REB 670 Allocation of BBP Software Functionality

Zone Selection Differential Zones


Dynamic Software CT switching High speed tripping for internal
(i.e. no switching in CT secondary
faults. Typical operating time 12
circuits neither interposing CTs
are required) ms
Easy adaptation to different Complete stability for through
substation layouts such as: single faults, with heavy CT saturation,
or double bus (with transfer bus), and a maximum remanence in the
one-and-half or double breaker, CT core at auto-reclosing
etc.
Low CT requirement, only 2
Simple adaptation to buses with milliseconds to saturation needed
only one set of CTs in the bus- for correct operation
section or bus-coupler bays
Intelligent detection for open or
Selective BBP & BFP tripping for
every bay shorted CT secondary circuits and
settable blocking of differential
Merging of the two differential protection zone
zones when required (i.e. during
ABB Power Technologies AB, 2006

load transfer in double busbar Sensitive differential protection


stations) stage for power systems with
Disconnector and/or circuit limited earth-fault current
breaker status supervision

2006-09-25
67
What is done Where for BBP in REB 670

CAP 531- Configuration PST - Settings


Determine Disconnector and Fix CT inputs to one of the
CB positions via a&b contact two zones
Dynamic CT switching Set Disconnector/CB behavior
software logic based on Connect CTs to Check Zone
Disconnector and CB
positions Set Diff Characteristics
BFP & BBP Tripping Scheme Set BFP pickup and time
delays
EnFP Scheme and Tripping
Set OC/EnFP and time delays
Intertripping Scheme

SMT
ABB Power Technologies AB, 2006

Connect required number of bays to I/O modules included in REB 670

2006-09-25
68
REB 670 BBP Software Structure / Function Blocks

Zone Selection Differential Zones


Primary Switchgear Objects Zone A
Status (i.e. disconnector and (Id>, OCT, Sensitive Id>)
breakers) Zone B
Bay (Id>, OCT, Sensitive Id>)
(Interface towards one Check Zone (Id>)
Primary Bay)
Zone Interconnection
(Merging of two zones when
required)

One Basic
ABB Power Technologies AB, 2006

Function in AFL,
Hidden
connections exist

2006-09-25
69
REB 670 Function Blocks

Disable Primary Object Switch Status SS_xx (1/3-Ph)


Status Evaluation Primary Object
Closed

Primary Object
Normally Open Primary Object
(i.e. b ) aux. Contact Open

Primary Object Primary Object Status


Normally Closed Delayed Alarm
(i.e. b ) aux. Contact (i.e. 00 or 11)

Object Status Forced to


Open or Closed via
REB 670 Variant 4 8 12 24 setting parameter
ABB Power Technologies AB, 2006

bays bays bays bays


No of available
Switch Status 20 40 60 96
Function Blocks

2006-09-25
70
Switch Status Settings (Setting Group Controlled)
ABB Power Technologies AB, 2006

2006-09-25
71
Disconnector/CB supervision & alarming

For every disconnector/CB status is determined from the


status of aux contacts (i.e. a & b contacts)
Two schemes available
ABB Power Technologies AB, 2006

Position of a disconnector/CB can be forced to OPEN or


CLOSED by a parameter setting

2006-09-25
72
ABB Power Technologies AB, 2006

73
2006-09-25
Scheme 1 - RADSS
ABB Power Technologies AB, 2006

74
2006-09-25
Scheme 2 - INX
Switchgear Status Monitoring Matrix
ABB Power Technologies AB, 2006

User Settable Switchgear


Switchgear Object
Names Status

2006-09-25
75
REB 670 BBP Software Structure / Function Blocks

Zone Selection Differential Zones


Primary Switchgear Objects Zone A
Status (i.e. disconnector and (Id>, OCT, Sensitive Id>)
breakers) Zone B
Bay (Id>, OCT, Sensitive Id>)
(Interface towards one Check Zone (Id>)
Primary Bay)
Zone Interconnection
(Merging of two zones when
required)

One Basic
ABB Power Technologies AB, 2006

Function in AFL,
Hidden
connections exist

2006-09-25
76
REB 670 Function Blocks
Bay CT Input
Bay Function Block (3Ph)
Block Bay Trip Trip to Bay CB
(BBP, BFP, OC, Ext, )
Control Current
towards Zone ZA
Binary Indication that
Bay is connected to ZA
Control Current
towards Zone ZB
Binary Indication that
Bay is connected to ZB
Force CT current
to Zero
after set time delay Binary Connection
Bay Function Block (1Ph) Indication for HMI
Invert CT current
after set time delay
ABB Power Technologies AB, 2006

Ext Zone Trip


(i.e. BFP BackUp Trip)

Ext Bay Trip


(i.e. Bay OC Trip)

2006-09-25
77
Bay Settings (Setting Group Controlled)
ABB Power Technologies AB, 2006

2006-09-25
78
Bay-Connections Status Monitoring Matrix

User Internally Connections


Settable Used Bay to internal
ABB Power Technologies AB, 2006

Bay Name FB zones

2006-09-25
79
Bay = Internal CT Status Logic
tZeroCurrent
ZEROCUR
t
0.0
T
tInvertCurrent F
INVCUR
t
-1.0
T
1.0
F X CurrentBayxx-cont.
X

CTConnection
Connected= 1
NotConnected= 0
ConnInverted= -1

A/D Conversion, Bayxx Current in


Multiplication w ith CT Ratio, Primary Amperes
Taking in account setting
CTStarPoint for TRM
ABB Power Technologies AB, 2006

REB 670
CT Input

2006-09-25
80
Bay = Internal Zone Selection Logic
CTRLZA
5 ms
&
1 t CTtoZoneA-cont.
1
&
CTRLZB
5 ms
&
1 t CTtoZoneB-cont.
1
ZoneSel= &
CtrlIncludes StrtLoadTransfBayxx-
cont.
&
ZoneSel=
CtrlExcludes
ZoneSel=
FixedToZA
ZoneSel= InvertCTtoZoneB-cont.
FixedToZB
ZoneSel=
FixedToZA&-ZB
ABB Power Technologies AB, 2006

2006-09-25
81
Bay = Internal Current Selection Logic
ZoneIntercActive
CurrentToZA-
ZoneSw itching = & T cont.
ForceOut 0.0
F
ZoneSw itching = & 1 &
ForceIn
1
ZoneSw itching = &
Conditionally 1 &

CTtoZoneA X T CurrentToZB-cont.
CTtoZoneB 1 q-2 0.0
F
InvertCTtoZoneB
-1.0
T
1.0
CheckZoneSel = F
Connected
T CurrentToCZ-cont.
0.0
F
CurrentBayxx
CONNZA
CONNZB

BayxxInZA-cont.

BayxxInZB-cont.

tripZoneAFromBayxx-cont.
ABB Power Technologies AB, 2006

TRZONE &

tripZoneBFromBayxx-cont.
&

2006-09-25
82
Bay = Internal Bay Tripping Logic

BayxxInZA
ZATrip &
1
BayxxInZB
ZBTrip &

TRBAY

tTripPulse TRIP
t 1
BLKTR &
ABB Power Technologies AB, 2006

2006-09-25
83
REB 670 Function Blocks
Zone Interconnection ZI (1-Ph)

External Start of Two Zone Interconnection


Zones Interconnection Active Signal

Special Feature to sum


two bay currents during Too Long
Zone Interconnection Zone Interconnection
Alarm Signal

Zone Interconnection ZI (3-Ph)


ABB Power Technologies AB, 2006

2006-09-25
84
Special Feature to Sum Bay Currents During LT

Bay01 Bay02
ABB Power Technologies AB, 2006

Sum BI1+BI2 for Bay01 & Bay02 During LT

2006-09-25
85
Zone Interconnection Settings (Setting Group Controlled)
ABB Power Technologies AB, 2006

2006-09-25
86
Zone Interconnection = Internal Logic

EXTSTART 50 ms
1 t ACTIVE
&

StrtLoadTransfBay01 ZoneIntercActive-cont.

StrtLoadTransfBay02
tAlarm
1 ALARM
...

StrtLoadTransfBaynn

Operation = On
ABB Power Technologies AB, 2006

2006-09-25
87
REB 670 Function Blocks
Block Zone General Zone Trip
Zone ZA (1-Ph) (BBP, BFP, Ext)

Block Id>
Id> Trip

External Zone Trip BFP BackUp Trip

External Zone Trip


Reset Latched
Zone Trip Sensitive Diff Trip

General OCT Alarm


Reset Latched
OCT Alarm Slow OCT Alarm

Fast OCT Alarm


Enable Sensitive
Diff Functionality Id> Alarm
ABB Power Technologies AB, 2006

Iin> Alarm

Iin RMS Current for DR

Diff RMS Current for DR

2006-09-25
88
Diff DFT Current for DR
REB 670 Function Blocks
Zone ZA (3-Ph)
Same signals as for 1-Ph but phase
segregated
ZB is exactly the same
ABB Power Technologies AB, 2006

2006-09-25
89
Diff Zone Settings (General)
ABB Power Technologies AB, 2006

2006-09-25
90
Diff Zone Settings (Setting Group Controlled)
ABB Power Technologies AB, 2006

2006-09-25
91
Diff Zone = Internal Tripping Logic
TRZONE TREXTZ
tripZoneA from Bay01
tripZoneA from Bay02
TREXTBAY
1

...
tripZoneA from Baynn 1

SensDiffOper = On
ENSENS
3s tSensDiff
Iin aa>b t t TRSENS
&
SensIinBlock b

Id a
a>b
SensOperLevel b

BLKST

ZA Diff Algorithm

TRIPLX
1 1
Id &

Iin
OCTBlock & 1
CheckZoneSup = Off
ABB Power Technologies AB, 2006

CZTrip 1

BLOCK tTripHold
& t
Operation = On
& TRIP
& S 1
&
RSTTRIP R

DiffTripOper = Latched ZATrip-cont.

2006-09-25
92
Diff Zone = Internal Open CT Logic
Slow OCTOper=Off

Slow OCT Algorithm


tSlow OCT
& t SOCT
Id a S
a>b &
OCTOperLevel b
R

FastOCTOper=Off

Fast OCT Algorithm

Id a & FOCT
a>b & S
OCTOperLevel b
R

100ms
RSTOCT
&

Id a
a>b
DiffOperLevel b
1

Slow OCTOper=
Supervise &

Id a
a>b
OCTReleaseLev b
ABB Power Technologies AB, 2006

OCT
&
FastOCTOper= 1
Supervise &

OCTBlock-cont.
Id a
a>b
OCTReleaseLev b

2006-09-25
93
Diff Zone = Internal Supervision Logic

tIdAlarm
Id a ALDIFF
a>b t
IdAlarmLev b

Iin a ALIIN
a>b
IinAlarmLev b
ABB Power Technologies AB, 2006

2006-09-25
94
REB 670 Function Blocks
Check Zone CZ (3-Ph)

Check Zone 3Ph Trip

External CZ Trip Check Zone Trip L1

Check Zone Trip L2

Check Zone Trip L3

Check Zone CZ (1-Ph)


ABB Power Technologies AB, 2006

2006-09-25
95
Check Zone Settings (Setting Group Controlled)
ABB Power Technologies AB, 2006

2006-09-25
96
Check Zone = Internal Logic

EXTTRIP

CZ Diff Algorithm

Id
1 TRIP
&

CZTrip-cont.
1
Iout

Operation = On
Operation = Off
ABB Power Technologies AB, 2006

2006-09-25
97
REB 670 Training

How to engineer the scheme with REB 670?


ABB Power Technologies AB, 2006

2006-09-25
98
Double Bus Single Breaker Station
ABB Power Technologies AB, 2006

2006-09-25
99
Connections to/from REB 670

Bay / Double Busbar

Q1 Q2

Q0
T1 T5
ABB Power Technologies AB, 2006

2006-09-25
100
Principle Drawing for Double Bus-Single CB Station
Disconnector aux. contact timing
Zone A Main
Open Closed
Zone B contact
Aux. a
Open Closed
contact
ba Aux. b
Closed Open
contact
QB1

SSxx REB 670


DISABLE
CLOSED CZ
NO
OPEN ZB
NC
ALARM
ZA
ba FORCED

QB2

SSxx
DISABLE Set Parameter
CLOSED
NO ZoneSel="CtrlIncludes"
OPEN
NC
ALARM
FORCED

BIM External or Internal


Feeder BFP Backup Bxxx
Trip Command
BLKTR TRIP
CTRLZA
Feeder Backup CONNZA
OC Trip CTRLZB
CONNZB

QA1 CT Input TRZONE


ABB Power Technologies AB, 2006

TRBAY
BI1
1200/1
A/D I3PB1
BOM
QB9
Other
Equipment TRM

Feeder Bay en06000XX01.vsd

BBP & BFP trip command to feeder breaker

2006-09-25
101
Principle Drawing for Double Bus-Single CB Station
Zone A
Zone B Disconnector aux. contact timing
Main
Open Closed
contact
b Aux. b
Closed Open
contact
QB1

REB 670

CZ
ZB
b ZA

QB2

Set Parameter
ZoneSel="CtrlExcludes"

External or Internal
BIM Feeder BFP Backup
Trip Command Bxxx
BLKTR TRIP
CTRLZA
Feeder Backup CONNZA
OC Trip CTRLZB
CONNZB

CT Input TRZONE
ABB Power Technologies AB, 2006

QA1

TRBAY
BI1 A/D I3PB1
1200/1
BOM
QB9
Other
Equipment TRM

Feeder Bay
en06000XX02.vsd

2006-09-25 BBP & BFP trip command to feeder breaker


102
Principle Drawing for Double Bus-Single CB Station
Zone A
Zone B

REB 670 Parameter ZoneSel must


be set to "FixedToZA"

Bxxx
QB1
BLKTR TRIP
CTRLZA
QB2 CONNZA
Other CTRLZB
CONNZB
Equipment TRM

CT Input TRZONE
TRBAY
BI1
2400/1
A/D I3PB1

QA1

BI2 External or Internal OR


2400/1 Bus-Coupler BFP
Backup Trip
Command

Bus-Coupler
Bay Bxxx
Bus-Coupler Backup BLKTR TRIP
OC Trip CTRLZA BOM
CONNZA
CTRLZB
CONNZB

TRZONE
ABB Power Technologies AB, 2006

CT Input
TRBAY
A/D I3PB1

Parameter ZoneSel must


Other be set to "FixedToZB"
Equipment

en06000XX03.vsd

2006-09-25
BBP & BFP trip command to Bus-Coupler breaker
103
Principle Drawing for Double Bus-Single CB Station
Zone A
Zone B

REB 670

QB1

CB Closing
QB2 Signal
ba
t=1s
QA1
t
1
SSxx
DISABLE
CLOSED
NO
OPEN
NC Bxxx
ALARM
BI1 BLKTR TRIP
2400/1 FORCED
BIM CTRLZA
CONNZA
CTRLZB
External or Internal CONNZB
Bus-Coupler BFP ZEROCUR
Bus-Coupler Backup Trip
Command TRZONE
Bay
TRBAY
I3PB1
BOM
Bus-Coupler Backup
OC Trip

TRM Parameter ZoneSel must


ABB Power Technologies AB, 2006

CT Input
be set to "FixedToZA&-ZB"
tZeroCurrent=150ms
A/D

Other
Equipment

2006-09-25
BBP & BFP trip command to Bus-Coupler breaker
104
Principle Drawing for Double Bus-Single CB Station
Zone A
Zone B

REB 670

QB1

QB2

b
t=1s
QA1
t
1

&
Bxxx
BI1 BLKTR TRIP
2400/1
CB Closing BIM CTRLZA
CONNZA
Signal CTRLZB
External or Internal CONNZB
Bus-Coupler BFP ZEROCUR
Bus-Coupler Backup Trip
Command TRZONE
Bay
TRBAY
I3PB1
BOM
Bus-Coupler Backup
OC Trip

TRM Parameter ZoneSel must


ABB Power Technologies AB, 2006

CT Input
be set to "FixedToZA&-ZB"
tZeroCurrent=150ms
A/D

Other
Equipment

2006-09-25
BBP & BFP trip command to Bus-Coupler breaker
105
ABB Power Technologies AB, 2006

106
2006-09-25
1 CB Station
Principle Drawing for 1 CB Station BBP & BFP
REB 670 BFP
OR Remote
End
ZB
Inter-
Bxxx
Zone A ZA Trip
BLKTR TRIP Feeder 1
QA1 Internal BFP CTRLZA
Backup Trip CONNZA
BBP &
Command CTRLZB
CONNZB BFP
TRIP
TRM QA1
QA1 TRZONE
Feeder 1

CT Input
TRBAY Parameter ZoneSel must
BI1 A/D be set to "FixedToZA"
2000/1
I3PB1
Other
Equipment
Bxxx
BFP
BLKTR TRIP TRIP
ZERO- CTRLZA QA2
CONNZA
CT Input ZERO- CTRLZB
QA2 CONNZB
A/D
BI2
2000/1 TRZONE Parameter ZoneSel must
Other OR TRBAY be set to "CtrlIncludes"
Equipment QA2 Internal BFP and CTConnection="Off"
Backup Trip I3PB1
Command

CT Input
Bxxx
Feeder 2

BI3 BBP &


2000/1 A/D BFP
Other BLKTR TRIP
TRIP
QA3 Equipment CTRLZA
CONNZA QA3
CTRLZB
CONNZB
ABB Power Technologies AB, 2006

QA3 Internal BFP


Backup Trip TRZONE
Command
TRBAY Parameter ZoneSel must
be set to "FixedToZB"
Zone B I3PB1
1 breaker BFP
Diameter OR Remote
End
Inter-
BOM Trip
Feeder 2

2006-09-25 en06000XX05.vsd
107
Double Bus-Double CB Station
ABB Power Technologies AB, 2006

2006-09-25
108
Principle Drawing for Double Bus-Double CB Station
REB 670
ZB Bxxx BBP &
Zone A
ZA BLKTR BFP
TRIP
QA1 Internal BFP TRIP
CTRLZA
Backup Trip CONNZA QA1
Command CTRLZB
CONNZB

TRM
QA1 TRZONE
CT Input
TRBAY Parameter ZoneSel must
BI1 A/D be set to "FixedToZA"
1500/1
I3PB1
Feeder

Other
Equipment

BOM

CT Input
BI2 Bxxx BBP &
1500/1 A/D BFP
Other BLKTR TRIP
TRIP
QA2 Equipment CTRLZA
CONNZA QA2
CTRLZB
CONNZB
QA2 Internal BFP
Backup Trip TRZONE
Command
ABB Power Technologies AB, 2006

TRBAY Parameter ZoneSel must


be set to "FixedToZB"
Zone B I3PB1
Double BFP
breaker OR Remote
Feeder
End
Inter-
Trip
en06000XX06.vsd

2006-09-25
109
How to approach REB 670 engineering?

Please Refer to:


REB 670 Application Manual
Section 8: How to approach REB 670 engineering
Station Name & Switchgear Arrangement: Voltage: Used Zones:

Vsters, Double Busbar-Single Breaker Station 400kV ZA=North Bus, ZB=South Bus, CZ=Overall Zone

Number of
Primary Bay Name Bay Func. Type of Switch-Status Switchgear Device
Connected Used Optional
(max 13 characters in Block CT Ratio Switchgear Func. Block Name (max 13 Comment
Primary Functionality
PST) Instance Device Instance characters in PST)
Devices

Bus Disconnector SS01 T1 - QB1


Bus Disconnector SS02 T1 - QB2
Breaker Failure,
Transformer T1 Bay01 250/1 3 Circuit Breaker SS03 T1 - QA1
Overcurrent
NA
NA
Bus Disconnector SS04 AL1-A220-F
Bus Disconnector SS05 AL1-B220-F
Bgeede AL1 Bay02 2000/1 3 Circuit Breaker SS06 AL1-220-B
NA
NA
Bus Disconnector SS07 D89-1
Bus Disconnector SS08 D89-2
ABB Power Technologies AB, 2006

400kV OHL-D Bay03 1500/1 3 Circuit Breaker SS09 D52


NA
NA
Bus Disconnector SS10 89J3-1
Bus Disconnector SS11 89J3-2
Valdivia-J3 Bay04 1250/1 3 Circuit Breaker SS12 52J3
NA
NA

2006-09-25
110
Good Thinks to Know about REB 670

The following slides shows some possible solutions with


REB 670
ABB Power Technologies AB, 2006

2006-09-25
111
How to share binary IO between 1-Ph REB 670 IEDs by LDCM modules

LDCM#1
<= 192 Binary Signals =>
Wire status of
REB 670, B31
disconnectors
from Bays 01- Phase L1

LDCM#2
08 <= 192 Binary Signals =>

LDCM#1
Wire status of
disconnectors REB 670, B31
from Bays 09- Phase L2

LDCM#2
16 <= 192 Binary Signals =>

LDCM#1
Wire status of
REB 670, B31
disconnectors
Phase L3
from Bays 17-24
ABB Power Technologies AB, 2006

LDCM#2

2006-09-25
112
How to share trip between 3 1-Ph REB 670 IEDs

Share trip between three


GOOSE for ZoneA IED in order to start

Port (OEM)
IEC 61850
ZoneA Trip
Breaker Failure in all three
IED 670 GOOSE for ZoneB
phases for BBP operation
ZoneB Trip

by wiring between three


towards IED #1 and IED #3
Same GOOSE from IED #2

50 ms
IEDs
Port (OEM)
IEC 61850
Ext ZoneA Trip
Sw itch
by using GOOSE
IED 670
messages when IEC
towards IED #1 and IED #2
Same GOOSE from IED #3

50 ms
Ext ZoneB Trip
61850-8-1 is used

50 ms
by using LDCM
Port (OEM)
IEC 61850

Ext ZoneA Trip


communication module
IED 670

Ext ZoneB Trip


50 ms This shall be done between
t

all three IEDs (i.e. three


ABB Power Technologies AB, 2006

times)

2006-09-25
113
Position of Line Disconnector ???

ZA GIS stations / AIS stations


parallel lines zero sequence
ZB mutual coupling
QB1 QB2 stored energy in the HV cable
will be discharged through the
earthing switch at the moment
QA1 of its closing

QC1
QB9

BI1
ABB Power Technologies AB, 2006

2006-09-25
114
Principle Drawing for Position of Line Disconnector
Disconnector aux. contact timing
(a aux contact timing only important when Scheme2_INX is used)
Zone A Main
Open Closed
Zone B contact
Aux. a
Open Closed
contact
ba Aux. b
Closed Open
contact
QB1

SSxx REB 670


DISABLE
CLOSED CZ
NO
OPEN ZB
NC
ALARM ZA
ba FORCED

QB2

SSxx
DISABLE Set Parameter
CLOSED
NO ZoneSel="CtrlIncludes"
OPEN
NC
ALARM
FORCED

BIM SSxx
DISABLE Bxxx
CLOSED
QA1
NO BLKTR TRIP
OPEN
NC CTRLZA
ALARM CONNZA
CTRLZB
FORCED CONNZB
BI1
1200/1
CT Input TRZONE
ABB Power Technologies AB, 2006

TRBAY
A/D I3PB1
BOM
QB9 Set Parameter
OperMode="Scheme1_RADSS"
TRM
ba

Feeder Bay

BBP & BFP trip command to feeder breaker

2006-09-25
115
Silent REB 670 Features

Bay out of service feature (via HMI or external signal)


Selective Zone Blocking (via HMI or external signal)
Block only all Bay Trip signals (via HMI or external signal)
All three features are prepared in the preconfigured
solutions!
ABB Power Technologies AB, 2006

2006-09-25
116
REB 670 Training

Detailed info about Summation Principle for REB 670


ABB Power Technologies AB, 2006

2006-09-25
117
REB 670*1.0; 1-ph version Summation Principle

Buses up to 24 bays per zone


REB 670; 1 Ph Single Busbar
2 Zones (A & B);
1 Breaker Systems
24 Bays
Double Busbar
Same applications possible as for 1Ph solution
Software Driven Zone Selection
+ N times BFP ???
OCP (EnFP) ???
DR, ER, EL ???
Cost effective Solution
ABB Power Technologies AB, 2006

N 8

2006-09-25
118
Possibility to use Summation Principle

Auxiliary Summation CT *)
Three one-phase Single one-phase
type SLCE 8; 1/1A, 2/1A or 5/
REB 670 IED REB 670 IED
1A

REB 670 REB 670


REB 670 with 1A + Up to 18 pcs
REB 670 CT inputs auxiliary CTs

*) One SLCE 8 per main CT

Auxiliary Sumation CT = ASCT


ABB Power Technologies AB, 2006

2006-09-25
119
Summation Principle overall Schematic
LA LB LX

IA1 IB1 IX1

Main CTs

A-bus

L1 L2 L3 N L1 L2 L3 N L1 L2 L3 N

IA2 IB2 IX2

Summation CTs

CT1 CT2 ... CT24

REB 670
ABB Power Technologies AB, 2006

w ith 1A
CT inputs

2006-09-25
120
Auxiliary Summation CTs

Auxiliary Summation CT
type SLCE 8; X/1A

P1
N1
S1
P2

P3
N2 N4

P4

P5
N3
S2
P6 Three types of CT available
en03000118.vsd
ASCT for three bays mounted on one plate
ABB Power Technologies AB, 2006

2006-09-25
121
Summation Principle End Connection

Main CT Auxiliary Summation CT


2000/1A or 2000/5A type SLCE 8;
or 2000/2A 1/1A or 5/1A or 2/1A
IL1
L1
P1 ISUMM
REB 670 w ith 1A CTs
IL2 N1
L2 S1
P2 X401
Other 5

relays P3 AI03
N2 N4
IL3 6
L3
P4

N P5
N3
IN S2
P6

Please Note the following:


1) All ASCTs within one station have to be connected
ABB Power Technologies AB, 2006

in the same way (i.e. all end connected)


2) Always use 1A REB 670 for summation design

2006-09-25
122
Summation Principle Through Connection
Main CT Please Note the following:
2000/1A
or 2000/5A 1) All ASCTs within one station have to be connected
or 2000/2A in the same way (i.e. all end connected)
L1 L2 L3 N 2) Always use 1A REB 670 for summation design
Other
relays Auxiliary Summation CT
type SLCE 8; 1/1 or 5/1A or 2/1A
IL1
P1 ISUMM
REB 670 with 1A CTs
N1
S1
P2 X401
5
P3 A103
N2 N4
IL3 6
P4
P5
N3
IN S2
IL1 IL2 IL3
P6
ABB Power Technologies AB, 2006

Other
relays

IN

2006-09-25
123
CT Zone Selection, Basic Solution
Disconnector aux. contact timing
(Aux. contact a timing is only crucial when Scheme2_INX is used)
Zone A Main
contact Open Closed
Zone B
Aux. a
Open Closed
contact
ba Aux. b
Closed Open
contact
QB1
SSxx
REB 670
DISABLE CLOSED
NO
OPEN
NC
ALARM
ba
FORCED

QB2
SSxx
DISABLE CLOSED Set Parameter
ZoneSel="CtrlIncludes"
NO
OPEN
NC ALARM
FORCED

BIM External or Internal


Feeder BFP Backup Trip Bxxx
Command BLKTR TRIP
CTRLZA
Feeder Backup CONNZA
OC Trip CTRLZB
ASCT CONNZB
ABB Power Technologies AB, 2006

QA1 CT Input TRZONE


TRBAY
BI1 A/D
1200/1 I3PB1
BOM
QB9
TRM

Feeder Bay BBP & BFP trip command to feeder breaker

2006-09-25
124
Advantages of the Summated Principle

Cost effective solution


Simple summation CTs ordering (1/1A, 2/1A or 5/1A)
ASCT end-connected or series-connected
Main CT ratio mismatch fixed by a parameter setting
Simple scheme engineering
ABB Power Technologies AB, 2006

2006-09-25
125
Limitations of the Summated Type

Only one measuring circuit is utilized for all fault types


(i.e. no redundancy for multi-phase faults)
Primary fault sensitivity varies depending on the type of fault and on
the faulty phase
The load currents in the healthy phases might produce the
stabilizing current when an internal, single phase to ground fault
occurs. However this is typically no problem for solidly earthed
systems with high earth-fault currents
No clear indication about faulty phase in case of an internal fault
Not possible to fully utilize Open CT detection feature built-in in
REB 670 terminal
ABB Power Technologies AB, 2006

2006-09-25
126
Varying Sensitivity for Internal Faults

Type of fault L1-Gnd L2-Gnd L3-Gnd L1-L2 L2-L3 L3-L1 L1L2L3

ASCT end
0.434 0.578 0.867 1.732 1.732 0.867 1.0
connected

ASCT series
1.732 0.867 0.578 1.732 1.732 0.867 1.0
connected

Example:
The minimal differential operating current level in REB 670 terminal is set to 1250A.
All ASCTs are series connected. What is the theoretical primary pickup value in case of L3-Gnd fault?

Answer #1:
According to the Table, pickup coefficient for this type of ASCT connection and this type of fault is 0.578. Therefore:

I Pickup ( L3 Gnd ) 0.578 1250 722.5 A


ABB Power Technologies AB, 2006

2006-09-25
127
REB 670 Features with Summation Design
ABB Power Technologies AB, 2006

2006-09-25
128
REB 670 Features with Summation Design
ABB Power Technologies AB, 2006

2006-09-25
129
REB 670 Training

Optional Functions in REB 670


Breaker Failure for Every CT input
4-stage OC for every CT input
End-fault protection
Two autoreclosing functions
ABB Power Technologies AB, 2006

2006-09-25
130
Breaker-failure protection (RBRF)

Issues a back-up trip of adjacent breaker in case of


failure to operate of the breaker to the protected
object
in most cases open local breakers
in some rare cases must transfer trip be used to open
breaker at remote end
Common used when bus bar protection is installed
ABB Power Technologies AB, 2006

2006-09-25
131
Breaker-failure protection (BFP)
Time sequence
General trip
Normal Re-trip adjacent CB
Fault occurs CB opening CB opening opening

Current det. Current det.


drop out dropout
Protection Breaker Breaker Breaker
Marginal Marginal
time opening time operating time operating time
10 30 ms 40 - 80 ms 20 ms 40 - 80 ms 20 ms

<10
ms
BFP timer t1 <10
BFP ms
time

BFP timer t2 BFP


time
ABB Power Technologies AB, 2006

Start BFP Total BFP fault clearing time

2006-09-25
132
Current Based Breaker-failure protection

Current detector
ASD
Current & Back-up trip
RMS-value (Busbar)

t2
t
Start
&

t1
Retrip of own
circuit breaker
ABB Power Technologies AB, 2006

2006-09-25
133
Breaker Failure Protection (RBRF)
Complete CB failure protection within REB 670*1.0 with:
1ph and/or 3ph starting
Re-trip (i.e. first time delay)
Backup trip / bus-strip (i.e. second time delay)
Short rest time of 15ms
Trips correctly only associated CBs via busbar disconnector replica
available inside REB 670
Settable RBRF trip pulse duration
CB Faulty feature
Function Operating Mode:
Current
Contact
ABB Power Technologies AB, 2006

Current & Contact

2006-09-25
134
Phase Overcurrent function (TOC)

Four, non-directional phase


overcurrent stages
IF Each stage can be Definite or
Inverse time delayed.
19 IEC/ANSI curves
Logarithmic inverse
3I> Taylor made curve is available
Each stage can be separately
4 blocked with second harmonic
4th stage can be used for end fault
protection
ABB Power Technologies AB, 2006

2006-09-25
135
End Fault Protection

CB=Clearing Boundary

CT=Measuring Boundary Busbar


Protection
Busbar
Protection

Feeder
Protection
Feeder
Protection

When feeder CB is Over-Trip


Zone
open, stop When feeder CB is
measuring open, extend
boundary at the measuring
Under-Trip
open CB contacts Zone boundary to the
ABB Power Technologies AB, 2006

in order to avoid open CB contacts


over-trip and in order to avoid
activate fast OC under-trip
protection to trip
remote end only

2006-09-25
136
Autoreclosing Function (AR)

Only used in certain markets in order to try to


re-energize the bus after BBP trip
One AR function per Differential Zone is available
ABB Power Technologies AB, 2006

2006-09-25
137
REB 670 Training

Monitoring Functionality in REB 670


Disturbance Report Includes
Disturbance Recorder
Event Recorder
Trip Value Recorder
IED Internal Event List
Indications
Automatic DR evaluation in PCM 600
Basic Functionality (always included)
ABB Power Technologies AB, 2006

2006-09-25
138
Disturbance Report General

Includes a number of sub-functions: DR, ER, EL, TR, IND


Storage capacity: max 100 recordings
Time resolution: 1 ms
Supports IEC 61850, IEC 103 & LON
Disturbance recorder function
Fault Locator
Comtrade files
Disturbance Recording Files follows Comtrade standard
Communication
ABB Power Technologies AB, 2006

Local HMI
Front/Rear connection (Ethernet, TCP/IP)

2006-09-25
139
Disturbance Recorder Inputs
40 analog channels (4 function blocks)
flexible analog configuration
voltages and/or currents (30 channels via AIM, LDCM or -block)
derived analog signals (10 channels)
copes different cycle time
setting possibilities:
be recorded or not
trig disturbance recording
96 binary channels (6 function blocks)
any internal or external (via BIM) binary signal
these 96 signals are logged into IED internal Event List
setting possibilities:
ABB Power Technologies AB, 2006

be recorded or not
trig disturbance recording and trigger mode
be included in Indications
activate the red local HMI LED

2006-09-25
140
Disturbance Recorder Triggers

Manual trig
from local HMI, from PCM600 or via station bus (IEC 61850)
Binary signal trig
on raising or falling
Analog signal trig
threshold level, both over and under function
Retrig
trig during post-fault period may or may not initiate new recording
ABB Power Technologies AB, 2006

2006-09-25
141
Disturbance Report Recording times

t pre tf t post
t lim

t pre Pre-fault time (0.05 - 0.30 s)


tf Fault time
t post Post-fault time (0.1 - 5.0 sec)
ABB Power Technologies AB, 2006

t lim Time limit for total post triggering recording (0.5 - 6.0 sec)
N max Maximum of simultaneous recordings due to retrig (3)

2006-09-25
142
Processed Information

Automatic generation of
disturbance reports
Reports adapted for different
subscribers
Notification by e-mail or SMS
message
COMTRADE format
Time scheduled uploading

ABB adds value to


your investment
ABB Power Technologies AB, 2006

2006-09-25
143
Handling Events
Even t s \ Even t List
The event buffer can store and
2004 - 12 - 15
12 : 17 : 54 . 711 054 TR I P - T R L 1 on show on display up to 1000
53 . 611 012 TR I P - T R I P on
. 611 066
. 611 079
ZM3 - S T L 1
CB 1 - C LOSE
on
on
events on a FIFO principle
12 : 16 : 58 . 711 096 ZCOM - CS of f
57 . 611 012
. 611 011
TR I P - T R I P
TOC 1 - T R I P
on
on The events are time tagged with
2004 - 12 - 14
12 : 17 : 56 . 711 054
55 . 611 012
TR I P - T R L 1
TR I P - T R I P
on
on
a resolution of 1 ms
. 611 066 ZM3 - S T L 1 on
. 611 079
12 : 16 : 58 . 711 096
CB 1 - C LOSE
ZCOM - CS
on
of f
The user can choose in having
57 . 611 012 TR I P - T R I P on
. 611 011 TOC 1 - T R I P on the last event on top or the last
2004 - 12 - 13
12 : 17 : 56 . 711 054
55 . 611 012
TR I P - T R L 1
TR I P - T R I P
on
on
event on bottom
. 611 066 ZM3 - S T L 1 on
. 611 079
12 : 16 : 58 . 711 096
CB 1 - C LOSE
ZCOM - CS
on
of f Events can be defined as a part
57 . 611 012 TR I P - T R I P on

2004 - 12 - 12
. 611 011 TOC 1 - T R I P on of the Disturbance Report
12 : 17 : 56 . 711 054 TR I P - T R L 1 on
55 . 611 012
. 611 066
TR I P - T R I P
ZM3 - S T L 1
on
on
Upload event list to PC
. 611 079 CB 1 - C LOSE on
2004 - 12 - 17 08 : 37 No r t h Co n n e c t i o n
Event list sorting facility
ABB Power Technologies AB, 2006

2006-09-25
144
REB 670 Training

REB 670 is fully compliant with IEC 61850


ABB Power Technologies AB, 2006

2006-09-25
145
Communication

Front connection:
RJ45 Ethernet port
Protocol: TCP/IP (transparent
SPA)
Rear Communication
IEC61850
IEC103
SPA
LON
ABB Power Technologies AB, 2006

2006-09-25
146
Communication
Capabilities A Breakthrough for Substation Automation

One world
One technology
One standard

IEC 61850
ABB Power Technologies AB, 2006

Combining the best properties in a new way...

2006-09-25
147
Communication
Capabilities Designed for IEC 61850

Remote control (NCC)


MicroSCADA Pro
SMS & PCM
Station Via TCP/IP
Gateway WAN or modem

Utility LAN
TCP/IP
Station bus
Protection
IEC61850-8-1 Control Protection Protection Control
& Control
ABB Power Technologies AB, 2006

2006-09-25
148
REB 670 Training

What is not Available in REB 670


Exercises
ABB Power Technologies AB, 2006

2006-09-25
149
Not Available in REB 670*1.0

VT inputs (i.e. TRM=12I only!)


Voltage Based Functions (U<, U>, f<, f>, V/Hz)
P, Q, f, V measurement
Switchgear Control
SLD on the built-in, front HMI

Open Version !!!


ABB Power Technologies AB, 2006

2006-09-25
150
Example 1 Single Line Diagram
Line 1 Line 2

2000/1 2000/1

CB1 CB5

BS1 BS2
500kV

CB2 CB3 CB4

1000/1 500/1 500/1


ABB Power Technologies AB, 2006

Gen 1 Gen 2 Gen 3

2006-09-25
151
Your Task

Propose solution with 3Ph Version


(How many terminals, 4-bay or 8-bay?)
Propose solution with 1Ph version
(How many terminals, 12-bay or 24-bay?)
Which disconnector/CB status you need for station replica?
Do you need trip relays (i.e. RXMS 1) to trip circuit breakers?
ABB Power Technologies AB, 2006

2006-09-25
152
ABB Power Technologies AB, 2006

153
2006-09-25
Example 2
ABB Power Technologies AB, 2006

154
2006-09-25
Example 3
ABB Power Technologies AB, 2006

155
2006-09-25
Example 4
ABB Power Technologies AB, 2006

156
2006-09-25
Example 5
REB 670 Power System Simulator
ABB Power Technologies AB, 2006

2006-09-25
157
ABB Power Technologies AB, 2006

158
2006-09-25