LIMIT STATES DESIGN OF R.C. STRUCTURES
INTRODUCTION
3
WORKING STREE METHODS
Where the limit state method cannot be adopted, working stress method
may be used.
Assumption for design of Members:
Based on elastic theory, the following assumption shall be made.
At any cross section, plan section before bending remain plane after
bending.
All tensile stresses are taken up by reinforcement and none by concrete
except as otherwise permitted.
The stress strain relationship of steel and concrete, under working loads is a
straight line.
The modular ratio m has the value 280/36cbc where 60bc is permissible
compressive stress due to bending in concrete in N/mm2
4
LIMIT STATES METHODS
The acceptable limit for the safety and serviceability requirements before
failure occurs.
The aim of design is to achieve acceptable, probabilities that the structure
will not become unfit for the use for it is intended.
Ensure an adequate degree of safety and serviceability
Design should be based on characteristic values for material strengths and
applied loads.
Term characteristic loads means that value of load which has a 95%
probability of not being exceeding during the life of structure.
5
Design Values
Materials fd=f/rm
fd=Design strength of materials
f=characteristic strength of material
rm=Partial safety factor appropriate to material and the limit state being
considered.
Loads
Design Load Fd=F rf
F=Characteristic load
rf=partial safety factors to nature of loads.
6
LIMIT STATE OF COLLAPSE
7
BUILDING MAINTENANCE, COMMON
DEFECTS AND REMEDIAL METHODS
Maintenance plays a vital role in the execution of buildings. Very often difficult problems are
encountered in the maintenance of building than in original work.
Every aspect of maintenance has to be carefully thought out in its entirety aiming at over all
sound ness of structure in all the seasons of the year. Most buildings may develop cracks
usually soon after construction and sometimes later. Much of the early cracking is
superficial, can be easily repaired.
Several factors contribute in producing defects. Before repairs or remedies are sought, one
needs to know the causes of cracking and its effects on the performance of the buildings.
Timely action in mitigating the distress phenomena through repair and rehabilitation is
essential for sustaining performance of such structures. Concrete is basically meant to last
for ever without any major repairs and maintenance. However deleterious agents in the
environment itself often leads to premature deterioration of concrete structures.
8
5. Durability can be achieved by proper maintenance. Therefore maintenance is
equally important as design and construction stages. But, maintenance is always
given a least importance. The importance given to planning and execution of
project is missing in maintenance activities. The more efficient maintenance
results in increase in life of structure and creates good image of the society. The
various problems in maintenance are occurring due to inefficient design/planning
and bad quality of construction. The designer shall use the best quality of
materials by which reduce maintenance problems. Most of the problems in
maintenance are repetitive type and directly affect the durability of structure.
Some of the problem are seepage/leakage, spalling of concrete and corrosions of
steel.
6. Principal causes of occurrence of cracks
1. Forces like Dead, Live, Wind, Seismic etc.
2. Foundation settlement
3. Moisture changes
4. Thermal variation
5. Chemical reaction etc
6. Poor workman ship
9
Main Common Defects:
1. Foundations
2. Walls
3. Concrete/RCC Frame
10
1. Foundation:
a) Engineers need to know the character and magnitude of forces in order to design and
construct structures.
b) One has to study the system of soil below the earth surface at various levels under ground
depending upon the past experience.
c) Repairs to foundations are expensive. Structures should be founded as stable soils.
d) Certain soil deposits wherein wetting of the soil beyond a stress level causes steep
reduction in stiffness resulting from disruption of soil structure.
e) Subject to rate of loading, disruption in soil structures takes place at a faster pace than the
development of new structural bonds which leads to vertical deformation at locations of
higher stress due to disturbance of soil structures.
f) Problems associated with foundation in clay soil are well known. Swelling clays create large
uplift forces on the peripheral wall during rainy season. A reverse situation may arise at
region of moderate rainfall when the central region of a building founded an clay soil is prone
to swelling during dry spells.
a) Differential settlement due to unconsolidated fill.
b) Differential settlement due to uplift of shrinkage soil, shrink and expand with changes in
moisture content. Vertical and diagonal cracks are noticed in external walls.
11
2. Walls
Walls are constructed using a variety of materials such as mud, stone, clay bricks, concrete
blocks, Fal-G Bricks etc. Common burnt clay bricks as per IS 1075-1951, Bricks shall be
hand or machine molded classifying Class1, Class2 Bricks maintaining characteristics like
water absorption to 20% and Efflorescence slight.
1. Although the walls are built of reasonably non- porous bricks, the mortar itself is relatively
porous and so rain water penetrate into to the mortar and will be finally sucked up on the
inside surface causing discolouration and dampness. The moisture which was absorbed by
the wall tries to escape by break through plaster, which otherwise reduces the strength of
materials in the wall. Porous mortar than water tight mortar for plaster is advisable.
2. Faulty joints are common cause of entry by rain so that if bricks are adequate for their
purposes, pointing needs to be examined and mortar replaced.
3. Number of causes of failures of brick wall have been reported. High intensity wind causes
masonry walls to collapse due to their in adequate lateral restraint. Quality of bricks
workman ship. Spacing of pilasters, size of wall panels etc. Influence the lateral resistance
of the walls structure.
4. Generally walls constructed with RC columns with in filled brick walls have performed better
during cyclones.
5. Failures of brick masonry walls can be avoided by suitable choice of panel size which in
term would depend on the tensile strength of brick and quality/workman ship. It is advisable
for provide a continuous RC bond beam on top.
12
6. Brick work may become cracked especially at door and window opening as a result of
excessive drying shrinkage. Rich cement mortar rendering, fail because they shrink and
crack. The familiar map pattern cracking is typical of drying shrinkage in renderings.
7. Cement based mortars may be attached by sulphates derived from clay bricks themselves.
Some times from external sources such as sulphates bearing soils or flue gases. The attack
is gradual and occurs when the brick work remain wet for long periods, which produces
various forms cracking and deformation of bricks.
8. Junction of the concrete lintels and masonry walls and junction of RCC. Sun shades and
walls are vulnerable places for the penetration of moisture, as these two different materials
always give rise to their cracks at the junctions, water dripping on the wall surface also
causes dampness.
9. Finished surface of roof should have a slope of 1 in 80.
10. Special attention should be paid to junction of roofs and parapets, outlets to drain out to rain
water to be properly executed. Every 200 sft of roof areas should be provided with one
outlet.
13
3 Concrete and RCC items
The common problems are
1. Seepage/leakage in buildings and their controlling methods: Excessive
dampness in buildings is one of the major problems in recent years. If such
seepage/leakage is allowed to continue unchecked, unhygienic conditions will
prevail and also the building may deteriorate to the extent that ultimately it
becomes uninhabitable. The source of seepage/leakage can be rain water,
leakage in pipe lines condensation or ground water.
Causes of seepage in building:
Seepage mainly occurs from walls and roof ceiling in buildings.
a) The causes of seepage/leakage through the roof are:
1. Lack of proper slope thereby causing stagnation of water.
2. Lack of proper drainage system
3. Lack of goals, coping etc.
4. Poor maintenance of pipe connection and joints.
5. Poor quality of construction.
b) Causes of seepage/leakage through the wall are
1. non provision of damp proof course.
2. lack of plinth protection
3. lack of chajja, facia over openings
4. poor orientation and wind direction
5. lack of stone cladding/water proof plastering and painting.
14
Seepage controlling methods:
Water proffing treatment is necessary especially for areas like, water tanks, sunken slabs,
roofs, terrace gardens, foundations, planters, service floors, etc., As a preventive measure in
recent years a number of water proofing treatment methods are being used by making use
of different water proofing materials.
1. mud phuska with proofing materials.
2. multi layer asphalt treatment.
3. brick coba treatment.
4. chemical injection treatment.
5. polymer modified bitumen based treatment
6. glass fibre tissue based treatment (7 course)
7. lime based treatment
There are different water proofing methods available for pre and post construction stages of
buildings. By good design/planning constructions and maintenance, the problem of seepage
in buildings can be minimized.
15
Spalling of concrete:
This is a common problem being faced by the maintenance engineer. Spalling of concrete
causes in convenience, shabby look and more affects the durability of structure.
Large number of destructive and non destructive tests are available to assess its state of
concrete and techniques are also available to combat various deteriorating causes.
16
For repairing such affected areas different materials like cement, polymer, epoxy materials,
polymer modified bitumen are being used. Steps to be taken for repairing the affected areas
as:
1. Remove all loose materials.
2. Clean the areas with compressed air.
3. Remove rust from reinforcement
4. Apply anticorrosive paint.
5. Apply cement/resin/polymer based mortar
Corrosion of Steel:
Corrosion of steel reinforcement in concrete structure is a common phenomenon which
require utmost attention. This occurs because of inefficient design/ drafting and poor quality
construction.
To avoid corrosion of reinforcement, special care has to be taken regarding the following.
1. Design mix
2. Water cement ratio
3. Garding of concrete
4. Cement content.
5. Quality cement, aggregate, water
6. Covert to reinforcement.
7. Compaction, admixtures.
8. Treatment to exposed surfaces.
9. Environmental conditions.
Therefore, it is suggested that the dampness which is the main cause for corrosion
should be avoided by good design and quality construction to achieve dense 17
concrete.
Scope of Investigations/ assessment of structural damage decision of
Restoration.
1. To assess the extent of structural damage to RCC elements of the building
2. To arrive at the residual strength of concrete and reinforcing steel.
3. Report covering the above aspects.
1. Debris insepction
2. Visual inspection of affected members.
3. Institution field testing.
4. Lab test
5. Damage classification of structural member.
2. Structural condition.
a. Spalling.
b. Exposure and condition of main reinforcement.
c. Cracks
d. Distortion
e. Construction joint, honey combing, delimitation
18
A) Condition of plaster and finish:
RC Members rendered with cement mortar which in general (1:3) may be cladded with other
materials (wood/marble etc.) condition of finishs are categorized as 1) unaffected 2) peeling
3) substantial loss 4) total loss.
Delamination of concrete means that a layer of some part of concrete has separated out
from the parent body but still not fallen out, Hallow surroundings etc.
Remedial Measures
Hammer test, Core test compressive strength estimation. Based on the severity of the
damage of the structural members, different types of repairs methods are to be adopted to
restore their structural integrity.
19
Class-I Superficial For repair, use cement mortar trowelling
using cement slurry bonding.
20
BUILDING MAINTENANCE, COMMON
DEFECTS AND REMEDIAL METHODS
1. Generally buildings are constructed in two categories. Framed structure usually
built with column and beam and with one brick thick wall and half brick walls for
above two or more floor structures.
21
The structural design consists of planning the frame work of the structure to
meet the above needs and to carry the loads economically with a design life
suited to the services in view.
a. to determine the loads forces which the frame work will be required to
support.
b. Selection of a suitable structural arrangements and materials of
construction.
c. Analyzing the internal stresses in the frame work.
d. Proportioning the members of the frame work to resist safely and
economically the internal stresses produced.
A structure may be subjected to (1) Dead Loads (2) Live Loads (3) Wind Loads
(4) Seismic forces. For the sake of standardization and legal binding on all
question of properties and working stresses for various materials are covered
by standard specifications. For the design of building in concrete, steel,
masonry, basic considerabations are followed referred to :
(1) I.S.Code 456-2002 Code of practice for plain & RCC structures.
(2) I.S.Code 800-1984 Structural steel in building construction.
(3) I.S.Code 875-1984 Code of practice fro Live loads and Wind Loads.
(4) I.S.Code 1893-1984- Criteria for earthquake resistant design of structures.
(5) I.S.Code 4326-1976- Code of practice for Earthquack resistant design & 22
construction of building
(6) I.S.Code 1904-1986 Code of practice for design and construction of
foundation in slab.
(7) I.S.Code 1905-1980 Code of practice for masonary walls.
(8) I.S.Code 1786 High strength deformed bars and Fe 415 grade.
(9) I.S. Code 269/8112/12269 Code of Cement Grades
(10) I.S. 9103 Code of Practice for Super Plasticizers
(11) I.S. 14687 Formwork
(12) I.S. 2502 - Assembly of Reinforcement
(13) I. S. 10262 Design of Mix
(14) I.S.383 Coarse and Fine Aggregates
(15) I.S. 13920 Ductility Detailing
23
Engineers have been designing the structures primarily on strength and behavior
considerations. Durability and life expiatory of a structure depends upon quality of
basic materials used in the construction, such as Water, Cement aggregate and
admixtures and methods of construction. The designer and builder should ensure
that right type of materials are used which can withstand loads and environmental
forces and other exposure conditions. There is no substitute for good concrete.
BIS has also recommended availability successful use of super plasticisers in
improving the workability without increasing the w/c ratio in strength of concrete.
Mix Proporation - Shall be selected to ensure the workability of the fresh concrete
and when concrete is hardened, it shall have the required
strength, durability and surface finish. (1) Design Mix
(2) Nominal Mix. Design Mix concrete is preferred to nominal Mix
24
GENERAL DESIGN CONSIDERATION
4. Design process- Design including design for durability, construction and use in
service should be considered as a whole. The realization of design objectives
requires compliance with clearly defined standards for materials, production,
workmanship and also maintenance and use of structure in service.
25
LOADS AND FORCES
In structural design, account shall be taken of the dead, imposed and wind loads
and forces such as these caused by earthquake, and effects due to shrinkage,
creep temperature etc., where applicable.
Dead loads shall be calculated on the basis of unit weights specified as per IS code
1911.
Imposed load, wind loads and snow loads shall be assumed in accordance with IS
875 (2), (3), (4) respectively.
Earthquake forces shall be calculated in accordance with IS 1893.
Shrinkage, creep and temperature effects shall be considered as per IS code 875
part (5).
Analysis All structures may be analysed by the linear elastic theory to calculate
internal actions produced by design loads. In liew of rigorous elastic analysis
simplified analysis as given in 22.4 & 22.5 of IS 456 may be adopted. With the
aid of computers using STAAD PRO evaluation of analysis and design of
members has become simple.
Structural Frames- Simplyfying assumption may be used in the analysis of frames.
a. Consideration may be limited to combinations of
1. Design dead load on all spans with full design imposed load on two adjacent
spans and
2. Design dead load on all spans with full design imposed load on alternate span
26
b. When design imposed load does not exceed three fourth of the design load, the
load arrangement may be design dead load and design imposed load on all the
spans.
Substitute Frame- For determining the moments and shears at any floor or roof level
due to gravity loads, the beams at that level together with columns above and below
with their far ends fixed may be considered to constitute the frame.
Where side sway consideration become critical due to unsymmetrical in geometry or
loading, rigorous analysis may be required.
For lateral loads, simplified methods may be used to obtain the moments and shears
for structures that are symmetrical. For unsymmetrical or very tall structures, more
rigorous method shall be used.
Behavior of concrete structures
Earth quakes cause not only large lateral forces on structures but also large lateral In
addition to structure is also subjected to load due to violent ground shaking . The
basic principle of earthquake resistant design is to ensure ductility of the structure so
that it can absorb large deformations by an earthquake without significant damage
the ductility or concrete structures can be ensured by proper ductility the
reinforcement as per the codes of practice IS 13920
27
Quantitatively the base shear force on a single storyed structure is given by
F=a/g x w
a=Ground acceleration
g=acceleration due to gravity
w=weight of structure.
Multistoried- structures with cellard may service earthquakes better than those on
shallow isolated footings
1. Strip foundation.
2. Isolated footing with constant thickness
3. Isolated footing with variable depth.
4. Raft foundation.
28
The Depth of Foundation
The depth of foundation is measured from the ground level to the bottom surface of
the lean cement. The depth of the foundation should be taken so as to avoid any
damage to the foundation concrete and to protect the soil below the foundation and
also depends on to nature of soil.
Design of deep foundation- A deep foundation is one which derives its main strength
and stability from the properly of the depth of foundation and it is classified into
Design of foundation
1. Assume the average thickness of the raft approx. 0.60 mr for the purpose of
calending the self using slabs.
2. The difference in the weight of concrete slab and the soil can be assumed as 10
KN/m3
3. The gross load on the foundation per panel size consists of the load from the one
column + weight of slab + weight of soil over burden.
4. Since the net bearing capacity is given, only the net load on the soil need to be
computed for the purpose of bearing pressure.
Moments and forces- In the case of footing on piles, computation for moments and
shears may be based on the assumption that the reaction from any pile is
concentrated at the centre of pile.
For the purpose of computing stresses in footings which support a round or
octagonal concrete column or pedestal, the face of the column or pedestal shall be
taken as the side of a square inscribed within the perimeter of the round, octagonal
column or pedestal. Bending manent at any section shall be determined by passing
through the section a vertical plane which extends completely across the footing,
and computing and moments of the forces acting over the entire area of the footing
on one side of the said plane.
32
Shear and Bond- Shear strength of footing is governed by the
a. The footing acting essentially as a wide beam, with a potential diagonal crack
extending in a plane across the entire width, the critical section for this condition
shall be assumed as a vertical section located from the face of column, pedestal at a
distance equal to the effective depth of footing for footings on piles.
b. Two-way action of the footing, with potential diagonal cracking along the surface of
truncated cone or pyramid around the concentrated load. In this case, the footing
shall be designed for shear in accordance with the critical section for shear at a
distance d/2 from the periphary of the column.
34
Short axially load
members in compression:- The member shall be designed by considering the
assumption when the minimum eccentricity does
not exceed 0.05 times the lateral dimension, the
members may be designed by the following
equation.
P = 0.4 fck AC + 0.67 fy Asc
P Axial load on the member.
fck = Characteristic strength of compressive
strength of concrete.
Ac = Area of concrete.
fy = Characteristic strength of compression
reinforcement.
Asc = Area of longitudinal steel for columns.
For design purposes, the compressive strengths of concrete in the structure shall be
assumed as 0.67 times the characteristic strength
35
Members subjected to combined Axial load and unaxial bending using sp16 Design
axials for reinforced concrete to IS456.
Members subjected to combined axial load and Biaxial Bending.
The resistance of a member subjected to axial force and Biaxial bending shall be
obtained on the basis of equilibrium and minimum eccentricity with the neutral axis
so chosen as to satisfy the equilibrium of load and moments about two axes.
Mux1, Muy1= Max Uniaxial manent capacity for axial load of Pu, bending
about x and y axes respectively.
n = related to Pu/Pu2
Puz = 0.45 fck Ac + 0.75 fy Asc
n = = Pu = 0.4fck Ac + 0.67 fy Asc
Pu2 0.45 fck Ac + 075 fy Asc
36
Minimum requirements in column:-
The cross sectional area of longitudinal reinforcement shall be not less than 0.8% not
more than 6% of gross sectional area of column.
Minimum percentage of steel shall be based upon the area of concrete required to
resist the direct stress and not upon the actual area.
Minimum number of longitudinal bars in column shall be four in rectangular and six in
circular columns.
RCc column having helical reinforcement shall have at least six bars of longitudinal
reinforcement.
Spacing of longitudinal bars measured along the periphery of the column shall not be
exceed 300mm.
In case of pedastals in which longitudinal reinforcement is not taken in account in
strength calculation, nominal longitudinal reinforcement not less than 0.15% of the
cross sectional area shall be provided. Pedastal is a compression member, the
effective length of which does not exceed three times the least lateral dimension.
37
Transverse reinforcement:-
A reinforced concrete compression member shall have transverse or helical
reinforcement so disposed that every longitudinal bar nearest to compression face
has effective lateral support against buckling.
Note:- for continuous beams & Frames 1o may be assumed as 0.7 times the
effective span.
Deflection of structure to be limited to span / 250.
(a) Minimum area of tension reinforcement shall not be less than that.
As 0.85
bd fy
As = Minimum area of tension reinforcement.
b = breadth of beam or breadth of web of T-Beam.
d = effective depth.
fy = characteristic strength of reinforcementin N/mm2.
(b) Max. reinforcement:- Max are of tension reinforcement shall not exceed
0.04bd.
Compression reinforcement:-
The Max. area of compression reinforcement shall not exceed 0.04 bd. Compression
reinforcement in beam shall be enclosed by stirrup for effective lateral restraint.
40
Side face reinforcement:-
Where the depth of web in a beam exceeds 750mm side face reinforcement shall be
provided along the two faces. The total area of such reinforcement shall not be less
than 0/1% of the web area and shall be distributed equally on two faces at a spacing
not exceeding 300mm or web thickness whichever is less.
Transverse reinforcement:-
The transverse reinforcement in beams shall be taken around the outer most tension
and compression bars. In T-beam & L-T Beam, such reinforcement shall pass
around longitudinal bars located close to the outer face of the flange.
Minimum shear reinforcement in the form of stirrup shall be provided such that.
41
Where Asv = Total cross sectional area of stirrup legs effective in shear.
Sv = Stirrup spacing along the length of member
43
Slab spanning in two directions at Right Angles:-
Slabs spanning in two directions at right angles and carrying U.D.L may be
designed by using coefficients.
My = y X W X Lx2
B = unit width.
45
RCC BUILDING ELEMENTS
BY
N.KRISHNAM RAJU
ADVISOR TO APHB
46
Structural Planning:- In case of framed structures,
1.The most important aspect of structural planning is the arrangement of columns and
beam. The size of column, beams and slabs depend upon the spacing and
arrangement of the frame.
2. For taller building cross bracing either with RCC wall or bracing girder is essential.
47
RCC Elements
Foundation:
48
3. Beams:- A horizontal bracing member connecting the columns to take care of load
and moments
4. Slabs:- RCC slabs are most commonly used in floor and roofs of building.
Thickness is small compared will the other dimensions. Steel is compared will the
other dimensions. Steel is provided to minimize shrinkage, temperature effects
and cracking.
5. Stair case:- To provide access between various floors.
49
6.Shear walls: RC walls designed to take care of lateral forces and stability.
7 Choice of Mix:- Based on the number of floors and flexural stresses for
beam, slabs, and footing, predominant stresses in compression for column
members.
8.Assembly of reinforcement a) Reinforcement shall be bent and fixed in
accordance once IS 2502. b) Barbending schedule for reinforcement wall
9.Expansion joints:- To allow variation is temperature, expansion joints in
frames are essential normal @ 45 meters length and shape of building.
10.Construction Joints:- To comply with IS 11817. To provide at accessible
locations.
50
Concepts
Introduction:- The important characteristics of soil one should know in the design of
RCC foundation
1. Type of Soil
2. Bearing capacity
3. Settlement at different pressures
4. Water Table
5. Friction angle.
b. Bearing capacity of the soil is governed by its shearing resistance. If stress due
to shear exceeds what the soil can bear, failure occurs.
c. SBC of soil to be ensured based on the soils in the location duly conducting soil
exploration and necessary lab tests.
d. Foundation:- That part of the structure which is in direct contact and transmitting
loads to the ground.
51
Raft Foundation:- A foundation continues in two direction. Covering an area
other foundation
52
General considerations for design conforming to IS 1904
1. Loads on Foundation: a Dead load + Live Load
b Dead Load + Live Load + W L + E Q F
53
Type of Foundation
a. Spread foundations
b. Strip Foundation
c. Steel grillage foundation
d. Raft Foundation
e. Pier foundation
f. Pile Foundation
Selection of type of foundation:- As per site conditions and soil met with and safe
bearing capacity of soil.
54
a.Spread Foundation: The area of the footing which has the largest percentage of
live load to total load should be determined. By total load/allowable soil pressure
b.Strip Foundation: Where the width of foundation required exceeds the width of
spread of load at the level of foundation transverse reinforcement is necessary and
ship foundations of suitable design shall be adopted.
c.Steel crollage foundation: In designing grillage a method that assures of flexibility
in both the base plate of the column and the reload steel beams may be used.
d.Raft Foundations: Are used where the bearing power of the soil is so low. A raft
shall be so shaped and proportioned that the centre of area of the ground bearing
shall be vertically under the centre of gravity of the imposed load. The soil usually a
raft shall be protected from alternate shrinking and swelling due to moisture changes
e.Pile foundation: The principal uses of piles is to transit loads taro soft or unstable
surface soils to harder soils.
55
General design consideration
Piles shall be spaced sufficiently far apart to ensure that zones of sois
surrounding them, do not over lap, spacing of piles shall be not less than
100 cm.
The edge of caps shall extend at least 15cm beyond edge of pile. The caps
will not be less the 60 cm thick
Piles and pile caps shall be designed for all column loads.
56
5.Reinforcement of to pile shall be carried into cap and anchored into it just as the
reinforcement of column is anchored to develop full tension value .top of all piles
shall be embedded in caps not less than 7.5 cm.
1.Types of construction
1. Load bearing construction (upto 2 to 3 floors)
2. Composite construction (upto 5 to 6 floors)
3. Reinforcement concrete framed construction (any floor)
4. Steel framed construction (for economy of space and quicker program of
construction)
57
58
59
60
61
BUILDING CONSTRUCTION IN STAGES
Specifications
1.Earth Work:
1. Excavation of foundations
2. Filling in foundation
3. Filling in Basement
4. Pile foundation
62
2 Concrete
3 Steel Reinforcement
4 Brick Masonry
5 Stone Masonry
6 Flooring
7 Roofing and ceiling
8 Plastering, painting etc
9 Wood work
10 Painting & varnishing
Construction Stages
1.BC1 a Site examination
b Soil exploration
c Marking & set out
d Earth work excavation
e Antitermite treatment
f Mortars and Masonry
g Brick work and stone masonry
63
2 BC2 a Damp proof and work proofing
b Timber and plywood
c Word work
d Steel work
e Roof and Roof coverings
f Stairs, Lifts & Elevators
65
CONSTRUCTION STAGES
1 EXCAVATION OF FOUDNATION
2 FILLING IN FOUNDATIONS
3 FILLING IN BASEMENT
4 PLAIN CEMENT CONCRETE PCC FOR FOUNDATION
5 FORM WORK (CONFORMING TO IS 14687)
6 REINFORCEMENT
7 WATER
8 PLACING OF CONCRETE
COMPACTION
SLUMP TEST
9 MASONARY (CRS)
10 BRICK WORK
11 PLASTERING
12 SUMMARY
66
CONSTRUCTION PRACTICES
Placing of concrete (As per clause No. 13.2 of IS 456/2000)
1. Design mix to be obtained.
2. The concrete to be deposited as nearly as practicable in its final position.
3. Avoid lengthy handling and segregation of mix.
4. The concrete shall be placed and compacted before initial setting of
concrete.
5. Avoid segregation or displacement of reinforcement form work.
67
CONSTRUCTION PRACTICES
Compaction (As per clause No. 13.2 of IS.456/2000)
1. Concrete to be compacted with pan vibrators for slabs and pin vibrators for
beams/columns
68
CONSTRUCTION PRACTICES
Slump Test (As per clause No. 13.2 of IS 456/2000)
1. For concreting of lightly reinforced sections, mass concreting with very low
and low degree of workability, the slump is to be between 25 to 75 mm.
2. For concreting with heavily reinforced sections with medium degree of
workability the slump is to be between 50 to 100 or 75 to 100 as directed by
Engineer-in-charge.
69
CONSTRUCTION PRACTICES
Stone masonary
1. Coursed rubble stone masonry
1. The face stones shall be squared on all joints with beds horizontal.
2. They shall be set in regular courses of uniform thickness fom bottom to
top throughout.
3. No face stone shall be less width in plan than 150 mm for walls of 400
mm thick 200 mm for walls of 450 mm thick and 250 mm for walls of 600
mm thick and above.
4. The face stones shall be laid headers and stretchers alternatively so as
to break joints.
5. The stones shall be solidly bedded, set in full mortar with joints not
exceeding 12mm and extend back into the hearting.
6. The height of the stone shall not exceed breadth at face nor the length
inwards.
2. Through stones and Headers
1. In all the works upto a width of 600mm, bond stones running though the
wall to be provided at an intervals of 2 m in each course.
2. For walls thicker than 600mm, a line of headers each headers each
header overlapping by 150mm minimum shall be provided from front to
back at 2 m intervals in each course.
3. The position of the stones shall be marked on both the faces.
70
CONSTRUCTION PRACTICES
Brick work
1. The thickness of joints in case of masonry with first class brigcks shall not be
more than 10mm.
2. In case of masonry with second class bricks joints shall not be more than 12
mm.
3. The bricks shall be thoroughly soaked in clean water.
4. The cessation of bubbles when the bricks are immersed in water is an
indication of thorough soaking of bricks.
5. The bricks shall be laid with joints full of mortar.
6. The face joints shall be racked by jacking tool when the mortar is green.
7. The wall construction shall be taken up truly plumb.
8. All courses shall be laid truly horizontal.
9. All vertical joints shall be truly vertical.
10. The thickness of brick course shall be kept uniform and with their frogs kept
upward.
71
CONSTRUCTION PRACTICES
Plastering
1. Water the brick wall before start of plastering.
2. Chicken mesh at joints of brick wall and R.C.C member to be provided.
3. Dry mixing of cement and sand is to be done on impervious platform.
4. Holes provided for scaffolding are to be closed along with plastering.
5. Level marking must be done in advance form time to time.
6. Chip off concrete surface before starting plastering.
7. Gaps around door window frames to be filled.
8. Base coat of plaster to be checked before application of finishing coat.
72
SUMMARY OF QUALITY CHECKS TO BE DONE ON BULLDINGS WORKS.
73