DAY 1 to NIGHT TIME ACTIVITY SAFETY DEVICES (SIGNS AND LIGHTING), MOBILIZE
BACKHOE & DUMP TRUCK, EXCAVATE, INSTALL PIPE,
DAY 2 EXCAV. & PIPE LAYING BACKFILL AND COMPACT , MOVE OUT AND CLEAR THE
AREA.
LONGITUDINAL
SECTION
CROSS
SECTION
10:00 AM 2:00 PM BASE PREPARATION AND
DAYTIME ACTIVITY
DAY 3 TEMPORARY RESTORATION
ASPHALTING THE 3-DAY WORK (22 METER
TRENCH)