CONSTRUCTION OF ROADS WITH

CATIONIC BITUMEN EMULSION BASED


COLD MIX TECHNOLOGY

Dr. N.K.S. Pundhir


Senior Principal Scientist
E-mail: pundhir.crri@nic.in

CSIR- Central Road Research Institute,


New Delhi-110025
CONVENTIONAL METHOD FOR ROAD
CONSTRUCTION
HOT MIX TECHNOLOGY

Hot Applications
Heating of Binder at 1650c
Heating of Aggregate at 150oc
Production of mix at 1550C
Tack coating at 1600C
Laying of mix at 1300C
Compaction of mix at 1200C
DRAWBACKS OF HOT MIX TECHNOLOGY

Environmental Degradation
High Energy Consumption
Increase in Carbon Footprint
Low Output for Mix Production
Low Laying Work in rains / cold
Limited Construction Period in a yr.
Oxidative Hardening of Binder
Heath / Safety Hazardous to Labour
Emulsion Based Cold Mixes
Overcome
Hot Mix Problems
BITUMEN EMULSION
A liquid product in which a
substantial amount of bitumen is
suspended in a finely divided form
of the size 4-10 microns in water in
presence of emulsifiers

TYPES OF EMULSIFIER
Anionic Emulsifier
RCOOH + NaOH = RCOO - + Na + + H2O

Cationic Emulsifier
RNH2 + HCl = RNH3+ + Cl -
TYPES OF EMULSION
Anionic Emulsion
Cationic Emulsion Emulsified Ions
+ +
+

BITUMEN
DROPLET
+

+
CATIONIC BITUMEN EMULSION
GRADES OF BITUMEN EMULSION
Rapid Set - RS-1 & RS-2
Medium Set - MS
Slow Set - SS-1 & SS-2

RS-1 : Tack-Coating , Penetration Grouting


RS-2 : Surface Dressing,
MS : Premix carpet, Patch Repair
SS-1 : Priming
SS-2 : SDBC, BC, BM, Slurry Seal,
PMB/Latex Emulsion : Micro-surfacing
Bitumen Emulsion Production

Bitumen Water +
+ 2% K.oil emulsifier
Bitumen Emulsion

colloid
mill
dosage dosage
pump pump

emulsion
Pilot Plant in CRRI

Property Value
Binder Grade (Pen) 80-100
Binder Level (%) 65
Emulsifier Level (%) 0.6
pH of Water Phase 2.4
(HCl)
Viscosity Saybolt 108
Furol Viscometer at
25C, Seconds
TESTING OF EMULSIONS (IS: 8887-2004)
Residue on 600 micron IS sieve
Viscosity by Saybolt Furol viscometer
Coagulation at low temperature
Storage stability after 24 hrs.,
Particle charge
Stability to mixing with cement,
Coating ability and water resistance
Residue Test
- Penetration
- Ductility
- Solubility in Trichloroethylene
APPLICATION OF COLD MIX TECHNOLOGY
Construction of BM, PMC, MSS & SDBC
Surface Dressing
Grouting-Penetration Macadam
Priming GSB/WMM & Tack coating
Crack Sealing (Black Seals)
Repair of Pot- Holes & Depression
Repair of Utility Cuts & Bomb Crater
Sub-Base & Base Courses (Sealing)
Slurry Seal Treatment / Micro surfacing
WORLD WIDE CONSUMPTION OF
BITUMEN EMULSION V/S BITUMEN
Country Annual Tonnage Percentage

Emulsion Bitumen

USA 3166000 28000000 11

FRANCE 1200000 2800000 43

SPAIN 440000 1600000 27

BRAZIL 420000 1336000 31

SOUTH 120000 300000 40


AFRICA

INDIA 60000 2250000 2.7


COLD MIX DESIGN FOR
SEMI DENSE BITUMINOUS
CONCRETE USING CATIONIC
BITUMEN EMULSION
COLD MIX DESIGN
Cold mix design of MSS, SDBC / BM :

Evaluation of Bitumen Emulsion

Gradation and Properties of Aggregates

Premixing Optimum Water Content

Preparation of Marshall Specimens

Testing of Marshall Specimens


Evaluation of Bitumen Emulsion
Physico-chemical Properties of Cationic Bitumen Emulsion as per IS:8887- 2004
Properties of Bitumen Emulsion Requirement of IS:8887- 2004
S.No.
RS-1 RS-2 MS SS-2

(i) Residue on 600 micron IS sieve 0.05 max. 0.05 max. 0.05 max. 0.05 max.
(% mass)
(ii) Viscosity by Saybolt Furol Viscometer,
seconds
At 250C - - - 30-150
At 500C 20-100 100-300 30-300 -
(iii) Coagulation of emulsion at low Nil Nil Nil Nil
temperature
(iv) Storage stability after 24 hrs. , %, max. 2.0 1.0 1.0 2.0

(v) Particle charge +ve +ve +ve +ve


(vi) Coating ability and water resistance - - Good -
(a) Coating, dry aggregates - - Fair -
(b) Coating after spraying water - - Fair -
(c) Coating, wet aggregates - - Fair -
(d) Coating after spraying water
(vii) Stability to mixing cement, Nil - Nil 2
%coagulation
( viii) Miscibility with water (coagulation) No No No No
Coagulation Coagulation Coagulation Coagulation

(ix) Test on residue : 60 min. 67 min. 65 min. 60 min.


(a) Residue by evaporation, % 80-150 80-150 60-150 60-120
(b) Penetration, 250C/100 gm/5 sec. 50 min. 50 min. 50 min. 50 min.
(c) Ductility, 270C/cm., 98 min. 98 min. 98 min. 98 min.
(d) Solubility In Trichloroethylene, %
(II) Gradation / Properties of Aggregates
Aggregate Blend for SDBC Mix
I.S. sieve 20 mm. 13.2 mm. S.D. Blend S.D.B.C. ( IRC
(mm.) 25% 45% 30% Recommendations
ndations)
22.4 25 45 30 100 100
13.2 12.5 42.85 30 85.35 79-100
11.2 6.25 38.95 30 75.2 68-90
5.6 0.25 12.95 30 43.2 33-55
2.8 0 1.2 30 31.2 22-38
0.71 0 0 17.63 6-22
0.355 0 0 8.5 4-14
0.18 0 0 5.9 2-9
0.09 0 0 2.2 0-5
(ii) AGGREGATE BLEND GRADATION
FOR SDBC MIX
(I.R.C. RECOMMENDATIONS)
Coarse Gradation Fine Gradation Blend Gradation

120

100

80
%age PASSING

60

40

20

0
0.09 0.18 0.355 0.71 2.8 5.6 11.2 13.2 22.4
I.S. SIEVE SIZE (mm.)
(iii) Determination of Premix Water Content
Quantity of emulsion ( P) is determined as :
P = 0.05A+0.1B+0.5C
Where,
A = Percent aggregate retained on 2.8 mm sieve
B = Percent aggregate retained on 90 micron sieve
C = Percent aggregate passing on 90 micron sieve

Fix quantity of emulsion, P,


Prepare cold mix with varying water contents
( 2,3,4,5 %) and visually examined for coating value
and workability
Premix water content is determined as water
content at which coating and workability is maximum
(iv) Preparation of Marshall Specimens
1100g Blended Aggregates
4 % water content Mix for wetting
Addition of emulsion 7,8,9% into
aggregates Mixing for uniform
coating Cold mix in mould

Compaction with 75 Blows on


each face Specimens Marshall
Specimen Curing for 3 days at
400C Testing for Bulk Density,
Stability, flow , Retained Stab. at 250C
TESTING OF COLD MIX
PROPERTIES OF COLD MIX WITH EMULSION (SS-2)

S. No. Properties Bitumen emulsion


Content,%

6.0 7.0 8.0

I Bitumen residue, % 3.8 4.4 4.9

ii Bulk density, gm/cc 2.26 2.27 2.25

iii Air Voids, % 9.1 7.81 7.92

iv Stability, kg. at 250C 480 560 530

v Flow, mm 6 3.5 6.5


OPTIMIZATION OF EMULSION CONTENT
3 day curing (40C oven) 3 day curing (40C oven)
2.23
DRY BULK DENSITY

500

MARSHALL STABILITY
2.22 475
450
2.21
(g/cc.)

425

(kg.)
2.2
400
2.19 375
2.18 350
2.17 325
300
6 7 8 9 10 11
6 7 8 9 10 11
BITUMEN EMULSION CONTENT (%)
BITUMEN EMULSION CONTENT (%)

3 day curing (40C oven) 3 day curing (40C oven)


9.0
500

MARSHALL STABILITY
475
450
AIR VOIDS (%)

8.0
425

(kg.)
400
375
7.0
350
325
6.0 300
6 7 8 9 10 11 6 7 8 9 10 11
BITUMEN EMULSION CONTENT (%) BITUMEN EMULSION CONTENT (%)
FIELD TRIALS IN DIFFERENT
CLIMATES
Available Specifications for Cold Mixes
IRC: 14-2004 Recommended Practice for Open Graded
Premix Carpets (Third Revision)
IRC:110-2005 Standard Specification and Code of
Practice for Design and Construction of
Surface Dressing
IRC:SP:81-2008 Tentative Specification for Slurry Seal /
Micro-surfacing
IRC: 82-1982 Code of Practice for Maintenance of
Bituminous Surfaces of Highways
IRC: SP: 20-2002 Rural Road Manual

No Specifications for MSS, SDBC, BC & BM with cold


mixes
TEST LOCATIONS OF BRO / LOCAL PWDs
On NH-1A Jammu-Srinagar National Highway
in J&K under snow bound area
On NH-44 near Silchar on Jowai - Badarpur Road
in Assam under high rainfall area
On Hanumangarh-Sangeria Road in Rajasthan
in desert climate
On NH-2 near Agra from km-228-230 in hot climate
On Approach Road to Secratariat, Aizwal in wet climate
Dantaur-Khajuwala Road in Rajasthan-desert climate
By-pass Aizawl, High rainfall ( June,2007)
NH-1A Jammu-Srinagar Road ( Sept., 2007)
Rural Roads in Assam ( Feb. 2012)
CONSTRUCTION OF ROAD WITH COLD MIX
Tack Coating
Bitumen Emulsion of RS-1
Quantity @ 2.5 3.5 kg
per 10 M2 area
Pressure distributor / or
manually
Cleaning of holes with water
when tack coating
discontinued
Spread Cold Mix when Tack
coat turns black from brown
Wetting of road surface
required, in Summer
CHECKING EMULSION FOR CONSTRUCTION

1
Coagulation Test

2
Rolling Drum for Emulsion Mixing
PREPARATION OF COLD MIX IN MIXER

1 2
Charging of Aggregates Wetting of Aggregates

3 4

Bitumen Emulsion for Cold Mix Discharging of Cold Mix


PREPARATION OF COLD MIX IN TRAY

2
1

3 4
LAYING OF COLD MIX FOR PMC / MSS

1 2
Tack coating with emulsion Ferrying of cold mix

3 4
3
Spreading of cold mix Laying of cold mix in rains
PMC Surface Before Seal Coat
SEAL COAT ON PREMIX
CARPET
SAND SEAL COAT
Cold mix of fine aggregates mixture
with emulsion (SS-2)
Spread the mix on open graded
Compact with 8-10 Tonne roller

LIQUID SEAL COAT


Tack coat with emulsion (SS-2 Grade)
@ 12-13kg / 10 m2
Aggregates 6.3 mm(passing)- 180
micron (Retained) was spread
Compacted with 8-10 Tonne road roller
INEXPENSIVE SURFACE DRESSING WITH EMULSION
Preparation of road surface
Pavement surface cleaned of dirt, dust
Pot-holes and minor irregularity ratified
Half width taken for surface dressing
The road was divided into segment of
10 m2 area.
Tack coat
Bitumen emulsion (RS-2) with quantity @
17 kg per 10m2 area was applied with
perforated cans at 3mm hole apart

Spreading of Aggregate
The first layer of aggregate of 19 mm size
was spread over the tack coated area
The aggregate was compacted with 8-10
ton road roller
The newly laid road surface was allowed
to traffic after 4-5 hours.
Two Coat Surface Dressing

Second Coat
Over first coat , Tack coat applied

Tack coat
Bitumen emulsion (RS-2) with quantity @
13 kg per 10m2 area was applied with
perforated cans at 3mm hole apart

Spreading of Aggregate
The first layer of aggregate of 13 mm size
was spread over the tack coated area
The aggregate was compacted with 8-10
ton road roller
The newly laid road surface was allowed
to traffic after 4-5 hours.
CONSTRUCTION OF PMC WITH
MINI HOT MIX PLANT
AIZAWL ( MIZORAM) - May, 2008
13.2 mm & 9.5mm - 2 : 1
FINISHED SURFACE OF WBM

PRIMING WITH EMULSION

COLD MIX TO FARRY


SPREDING COLD MIX & TACK
COATING

COMPACTION OF COLD MIX

FINISHED SURFACE OF PMC


PMC COLD MIX

PMC SURFACE
Performance of PMC
FIELD PERFORMANCE EVALUATION

METHODOLOGY

VISUAL INSPECTION

DISTRESS MEASUREMENTS

BINDERs AGING

FUNCTIONAL CHARACTERISTICS

UNEVENNESS OF SURFACING

BENKELMAN BEAM DEFLECTION


PERFORMANCE OF MSS WITH EMULSION on NH-2

10 % Binder economy iis achieved in


MSS, PMC and TCSD

1 2
MSS with Bitumen after 4 yrs Mix Seal Surfacing with 20%
reduced emulsion after 5 yrs
Performance of MSS on NH-2
Service Life of Mix Seal Surfacings with Emulsion and Bitumen

100

90

80

70
Performance Points,%

60

50
MSS R MSS T-20
40
MSS T-15 MSS T-10
30 MSS T-5 MSS T-0

20

10

0
0 1 2 3 4 5 6
Service Life, Years
Pavement Distress with Time in Mix Seal Surfacings

91

81 MSS-R MSS-T-20

71 MSS-T-15 MSS-T-10
Pavement Distress,%

MSS-T-5 MSS-T-0
61

51

41

31

21

11

1
0 1 2 3 4 5 6
Service Life, Years
PERFORMANCE OF PMC WITH EMULSION ON NH-2

1 2
Premix Carpet with 10% reduced PMC with 5 % reduced emulsion
emulsion after 5 yrs service life after 5 yrs service life

3 4
PMC with bitumen PMC with 5 % reduced emulsion
after 4 yrs service life after 5 yrs service life
Performance of PMC with Bitumen and Emulsions

100

90

80

70
Performance Point, %

60

50
PMC R PMC T-20 PMC T-15
40
PMC T-10 PMC T-5 PMC T-0
30

20

10

0
0 1 2 3 4 5 6
Service Life, Years
PERFORMANCE OF COLD TCSD ON NH-2

1 2
TCSD with emulsion After 5 Years TCSD with emulsion After 5 Years

3
TCSD with Bitumen after 4 years
Performance of TCSD with Emulsion and Bitumen

100

90

80
Performance Points, %

70

60

50

40 TCSD T-20 TCSD T-15 TCSD T-10

30 TCSD T-5 TCSD T-0 TCSD R

20

10

0
0 1 2 3 4 5 6
Service Life, Years
Pavement Distress in TCSD with Time

4.5

3.5
Pavement Distress, %

3
TCSD-T-20 TCSD-T-15 TCSD-T-10
2.5

2 TCSD-T-5 TCSD-T-0 TCSD-R

1.5

0.5

0
0 1 2 3 4 5 6
Service Life, Years
PERFORMANCE OF ROADS WITH EMULSION ON NH-44

1 2
SDBC with emulsion after PMC emulsion after 4 yrs
4 yrs

PMC with emulsion after 5 yrs

3
PERFORMANCE OF ROADS WITH EMULSION ON NH-1A

Premix Carpet with Bitumen Premix Carpet with Emulsion


after 5 yrs service life after 5 yrs service life

SDBC with emulsion after 5 yrs


service life
PERFORMANCE OF ROADS
WITH EMULSION

Surface condition before


construction

SDBC after 4 yrs on NH-44


SDBC with emulsion after construction
PERFORMANCE OF ROADS WITH EMULSION ON NH-44

SDBC with emulsion after PMC emulsion after 4 yrs


4 yrs

PMC with emulsion after 5 yrs


PERFORMANCE OF PMC ON H-S ROADS
(RAJASTHAN)

1 2
PMC with emulsion on H-S Rd PMC with emulsion after 5 yrs
after 2 yrs
Performance of Test Section on N.H. 44 (Assam)
in High Reinfall Area

Semi Dense Bituminous Concrete with Emulsion

Visual Inspection Pavement Distress

FIG 10 : PERFORMANCE OF TEST SECTIONS (SDBC) ON NH-44 FIG 12 : CRACKED AREA IN SDBC WITH SERVICE LIFE ON NH-44

100 50
SDBC (Emulsion)
90 SDBC (Bitumen)

% CRACKED AREA
40
PERFORM ANCE, %

80
30
70
60 20
50
(Emulsion) 10
40 (Bitumen)
30 0
0 1 2 3 4 5
20
SERVICE LIFE IN YEARS
0 1 SERVICE
2 LIFE IN YEARS
3 4 5
Performance of Test Section on N.H. 1A (J&K)
in Snow Bound Area
Premix Carpet Specification
Semi Dense Bituminous Concrete

Visual Inspection

PERFORMANCE OF TEST SECTIONS PERFORMANCE OF TEST SECTIONS (SDBC) ON


(PMC) ON NH-1A NH-1A
100

PERFORM ANCE, %
100 90
PERFORMANCE, %

90 80
80 70
70
60
60
50
50 (Emulsion)
40 40
(Bitumen)
30 30
20 (Emulsion) 20
10 (Bitumen) 0 1 2 3 4 5 6 7
0
0 1 2 3 4 5 6 7 SERVICE LIFE IN YEARS
SERVICE LIFE IN YEARS
1-d

PMC with emulsion and bitumen


80 30

% CRACKED AREA
70 SDBC (Bitumen)
% CRACKED AREA

PMC (Bitumen)
25
60 SDBC (Emulsion)
PMC (Emulsion) 20
50
15
40
10
30
20 5
10 0
0 0 1 2 3 4 5
SERVICES LIFE IN YEARS
0 1 2 3 4 5
SERVICE LIFE IN YEARS

Fig. 1: Performance of PMC and SDBC with service life in years on J-S Road (NH-1A):
a) PMC with emulsion and bitumen; b) SDBC with emulsion and bitumen ; c) Pavement
distress in PMC with emulsion and bitumen; d) Pavement distress in SDBC with emulsion and
bitumen

FIG 14 : PERFORMANCE OF SDBC ON H-S ROAD


100
PERFORMANCE, %

90

80

70

60
(Emulsion)
50 (Bitumen)

40
0 1 2 3 4 5

SERVICE LIFE IN YEARS


Effect of Aging on Binder
120

100
Penetration, dmm

80

60

40

20

0
1 2 3 4 5

Service Life in Years


Materials and Energy Requirement for
Different Type of Renewals
Specification Aggregat Bitumen Energy
e (Kg.) (Kilo /Cal108)
(cu.m.)
Hot Col Hot Cold Hot Cold
d
Two Coat Surface 85 70 9800 7280 0.99 0.74
Dressing
Premix Carpet + Seal 116 116 9100 8645 1.02 0.91
Coat
Mix Seal Surfacing 95 95 8700 8580 1.16 0.92
Semi-Dense 134 134 11000 11000 1.63 1.32
Bituminous Concrete
Comparative Cost of Bituminous Surfacings
With Emulsion vis-a-vis Hot Bitumen

S. N. Specification Thickness, Binder Cost / m2,


mm Rs.

1 SDBC 25 Bitumen 324.08


2 SDBC 25 Emulsion 276.21
3 PMC 20 Bitumen 168.84
4 PMC 20 Emulsion 104.76
CONSTRUCTION OF
RURAL ROADS WITH
COLD MIX TECHNOLGY
IN NORTH EAST REGION
1

Work Shop at Agartala on 4 / 5.02.2012


REPAIR DEMO IN AGARTALA ( Feb. 5, 2012)

1 2

3 4
CONSTRUCTION OF RURAL ROAD (PMGSY) IN
ASSAM- Feb. 2012

1 2

3 4
PERFORMANCE OF RURAL ROADS WITH COLD MIX-
Under PMGSY IN BONBOIGAON (2012)

1 2

4
3
MECHANISED CONSTRUCTION
OF BM, SDBC & MSS
IN VARYING CLIMATES

Desert (Rajasthan)
High Rainfall (High Rainfall)
Cold & Snow Bound (J&K)
Gradation of BITUMINOUS MACADAM
Proportioning of Mineral Aggregate Blend
Sieve Size, Specified mid
mm gradation

Combined
% passing % passing % passing gradation of
20mm 10mm stone dust blended agg
40% 45% 15% 40:45:15
40 45 15 100
26.5 100 100
45 95
19 40 15 100 90-100
44 72
13.2 19 15 78 56-88
24
4.75 0 1.5 15 17 16-36
11.5
2.36 0 0 15 15 4-19
6
0.300 0 0 6 6 2-10
4
75 0 0 2 2 0-8
PRODUCTION OF COLD MIXES WITH HMP

1 2
Adding Pre-mix Water Adding Emulsion in Drum Mixer

3 4
Cold Mix on Conveyer Belt Discharge of Cold Mix to Dumper
LAYING ROAD WITH COLD MIX IN RAJASTHAN

1 2

3
4
LAYING OF ROAD WITH COLD MIX IN J & K

1 2

3 4
Laying of Road with Cold Mix in Mizoram

1 2

3 4
Laying of Road with Cold Mixes

2
1

4
3
PERFORMANCE OF
SDBC &MSS IN RAJ.
SDBC with Emulsion After Two Year Service Life

MSS with Emulsion After Two Year Service Life


PERFORMANCE OF BM +PMC AFTER 5 yrs ON
NEW APPROACH ROAD AIZAWL

1 2

3 4
Reasons for Durable Road

There is chemical interaction


between emulsion / aggregate

The Cationic Emulsion is


positively charged
Surface of Siliceous
aggregates is having
Negative Charge
The strong bond formed
between emulsion-Aggregate
Emulsion contain Anti -
stripping agent which reduces
water damages
Benefits of Emulsions Based Cold Mixes
Environment Friendly and Energy Efficient
Construction feasible in rains/wet and cold
weather
Extends construction period During a year
Fast Production of Cold Mix
4-5 times Faster Construction by Cold Mix
15-20 % Cheaper Roads
Contain in built ant-stripping agent
Prevent oxidative hardening
Consume targeted Budget in time
Labour Intensive - Creates Jobs for Villagers
- MNREGA
Labour Friendly Technology- Health, Safety
GHG Emission Per Ton Laid Material
Energy Consumption Per Ton Laid Material
REPAIR OF POT- HOLE
Make rectangular shape
Clean the pot- hole area
Track coating the edge and area
Prepare cold mix
Charge the aggregate 11 mm down in
concrete mixer
Add 2 % Water and mix
Add 5-6% emulsion & mix uniformly
Pour mix in pot hole/depression
Compact with road roller
PREPARATION OF COLD MIX FOR REPAIR

1 2

3 4
PROCESS OF REPAIR WITH COLD MIX

11 22

4
3
REPAIR DEMO IN MUMBAI ( Jan. 9, 2012)

1 2

4
3
REPAIR DEMO IN AGARTALA ( Feb. 5, 2012)

1 2

3 4
APPLICATION OF SLURRY SEAL ON

DISTRESS ROADS- CRACKED

VIP ROADS
What is Slurry Seal
The slurry seal shall consist of :

cationic bitumen emulsion(SS-2)


mineral aggregate
water
Grading of Aggregates
Sieve Size % Passing (Minimum Layer Thickness)
Type I (2-3 mm) Type II (4-6 mm) Type III(6-8 mm)
9.5 mm 100
6.3 mm 100 90-100
4.75 mm 100 90-100 70-90
2.36 mm 90-100 65-90 45-70
1.18 mm 65-90 45-70 28-50
600 micron 40-65 30-50 19-34
300 micron 25-42 18-30 12-25
150 micron 15-30 10-21 7-18
75 micron 10-20 5-15 5-15
APPLICATION OF SLURRY SEAL
PERFORMANCE OF SLURRY SEAL

6 MONTHS 6 MONTHS
SIGNING OF MOA FOR TRANSFER OF COLD MIX TECHNOLOGY for N.E.
REGION TO M/S BITCHEM. ASPHALT TECHNOLOGIES GUWAHATI ON
27.12.2011
SIGNING OF MOA FOR TRANSFER OF COLD MIX TECHNOLOGY FOR
EAST PART TO M/S BITCHEM. ASPHALT TECHNOLOGIES GUWAHATI
ON 13.6.12
WORK SHOP JORHAT 19 SEPT. 2011
TRANSFER OF TECHNOLOGY FOR
SDBC & BM AT GUWAHATI ( MAY-2012)

11 2
Adding Pre-mix Water Cold mix for belt

3 4
Cold Mix on Conveyer Belt Cold Mix in Dumper
LAYING OF COLD SDBC IN GUWAHATI

1 2

3 4
LAYING OF SDBC WITH COLD MIX

2
1

4
3
LAYING OF BM WITH COLD MIX
Drafted Specifications for Development of Cold Mix
Technology and under IRC consideration

Proposed Tentative Specification For Semi-dense Bituminous


Concrete Using Cationic Bitumen Emulsion

Proposed Tentative Specification of Mix Seal Surfacing


(Dense-Graded Premix Carpet) With Cationic Bitumen Emulsion

Proposed Specification for Bituminous Macadam (Base & Binder


Course) with Cationic Bitumen Emulsion

Guidelines for Construction of Roads with Emulsion Based Cold Mix


Technology

Guidelines for Patch and Pot hole Repair with Emulsion Based Cold
Mix Technology
Production of Half Warm Mix at Rajkot
Production of Half Warm Mix at
Temperature 80-90oC
Laying of Test Section with Half
Warm Mix at Rajkot on NH-27
THANK YOU