Beruflich Dokumente
Kultur Dokumente
Evaluation Techniques
Guidelines for Hazardous Evaluation
Procedures (1992 by AIChE).
Second Edition with Worked Examples.
Center for Chemical Process Safety
(CCPS).
American Institute of Chemical
Engineers (AIChE).
Hazard Evaluation Techniques
1960 - 2001 1960 - 2001 1965 - 2001 1970 - 2001 1972 - 1974 1974 - 2001
Safety Check Lists Relative PHA What if HAZOP
Review Ranking
HAZOP
Review By Documentation Follow-up
Team
Table
Identify existing
safeguards to
prevent deviation
Hazop Pitfalls
Poor understanding by management of the HAZOP procedure
An Ethylene plant has 100 P&IDs, 625 equip't items. 625 items
Consider 5 variables, Pressure, Temperature, Flow
Composition and Function. 5 variables
Consider 6 Guidewords, None, More of, Less of
Part of, More than and Other than. 6 guide words
Questions to be answered = 18750 questions
Consider 5 minutes per question = 5 min./question
Time for ethylene plant HAZOP study = 93750 minutes
4 hour, 240 minutes sessions per day = 250 minutes/day
No. working of days = 375 days
Days per week = 5 days/week
No. of weeks to complete HAZOP for plant = 75 weeks
Other Pitfalls
Inexperienced HAZOP team.
Inadequately trained or in-experienced
leader.
Common Hazop Mistakes
Failing to establish a "safe" environment
for team members.
Consequences of events not carried to
conclusion.
Taking unwarranted credit for
safeguards.
Too little credit given for safeguards.
Hazop Mistakes Contd
Failure to make recommendations as
specific as possible.
Poor record keeping of HAZOPS.
Failure to HAZOP start-up and shut-
down procedures.
P&IDs not up-dated or poorly
constructed.
Hazop Mistakes Contd
A HAZOP is performed in lieu of
properly executed design reviews.
Wrong technique for system being
reviewed (See spreadsheet titled Fig
5.3).
HAZOP Example
To Compressor Inlet
LAH
FV Teams tend to quickly identify alarms, shut-downs
1 and controls, and claim them for safeguards.
Intention The intent is to transfer 150,000 lb/hr of C2/C2= mix at 300 psig and at -30 F for the startup period.
Possible Causes
1 FV-1 Wide open
2 Line break.
3
Consequences
1 High level in KO pot with liquid carry-over to compressor with serious damage to rotor. Potential hydrocarbons release.
2 Potential hydrocarbon release.
3
Safeguards
1 High level alarm LAH-1
2 High - High level alarm HHLA - 1 shutdown.
3 Vessel inspection yearly.
Recommendation / Actions Respib By Date
1 Consider limiting flow orifice, auto SD trip on High-High level, smart check valve. 1 JB 01-Jan-99
2 Determine extent of typical hydrocarbon release. 2 PM 15-Jan-99
3 Set-up vessel inspection yearly. 3 FD 30-Jan-99
Check List Example
1 Changes In Quantity a High Flow 1 Pump racing, delivery vessel pressure lost, Loss of automatic
suction pressurized, scale dislodged, leak in control
heat exchanger
b Low Flow 2 Pump failure, scaling of delivery, presence of Operator error
foreign body, poor suction condition,
cavitation, leak in heat exchanger, drain
leak, valve jammed
c No Flow 3 Pump failure, delivery vessel Failure of joint, pipe,
overpressurized, gas blockage, presence of valve, trap, bursting
foreign body, scale, sediment, suction vessel disc, relief valve.
empty.
d Reverse Flow 4 Pump failure, pump reversed, delivery vessel
over pressurized, poor isolation, gas locking,
surging, back siphoning.
Check List Contd
2 Changes in physical a High or Low 1 Boiling, cavitation, freezing, chemical
condition pressure breakdown, flashing, condensation,
sedimentation, scaling, foaming, gas
release, priming, exploding, imploding.
Changes in viscosity, density. External Fire,
Weather conditions, Hammer.
b High or Low 2 same as 1
Temperature
Check List Contd
3 Changes in chemical a High or Low 1 Changes in proportion of mixture, in water or
condition Conentration solvent content.
b Contaminants 2 Ingress of air, water, steam, fuel, lubricant,
corrosion products, other process materials
from high pressure system, leakage through
heat exchangers. gas entrainment, spray,
mist.