Beruflich Dokumente
Kultur Dokumente
PART 7: CONSTRUCTION
MANAGEMENT, PRACTICES AND
SAFETY
BY:-
- P. Bhanu (AH17132)
- R. Aishwarya (AH17138)
- Rishi Ghael (AH17140)
- Sakthi Ramkumar (AH17145)
- Shubham Aggarwal (AH17157)
- Vaibhav Mase (AH17170)
SCOPE
1. SCOPE:-
Construction is a process in which an organization takes on a project, assigns a
team to build it, and provides systems with the team can complete the work.
FLOOR HOLE
An opening measuring less than 300 mm,but more than 25mm in least dimension, in
any floor, platform or pavement ,through which materials but not persons may fall.
Eg:- Belt opening and pipe opening.
FLOOR OPENING
An opening measuring 300 mm or more in its least dimension, in any floor, platform or
pavement through which person may fall.
Eg:- Ladder Opening,pit or large manhole.
TERMINOLOGY:-
GUARD RAILING
A barrier erected along exposed edges of an open side floor opening,wall
opening,ramp,platform or balcony,etc to prevent fall of persons.
PILE RIG
The complete pile driving equipment comprising piling ,frame ,leader, hammer,
extractor and power unit. Pile rig can either be mounted on rafts or mobile unit mounted on
trailers or trucks.
PLATFORM
A working space for persons, elevated above the surrounding floor or ground, such as
balcony or platform for the operation of machinery and equipment.
TERMINOLOGY:-
SCAFFOLD
A temporary structure consisting of standards, ledgers made of bamboo,Ballies,timber or metal
to provide a working platform for workers and materials in course of
construction,maintenance,repairs and demolition and also to support or allow hoisting of workers,
their tools and materials.
TOE BOARD
A vertical barrier erected along exposed edge of a floor opening,wall opening, platform or ramp
to prevent fall of materials or persons.
WALL HOLE
An opening in any wall or partition having height of less than 750 mm but more than 25mm and
width unrestricted.
WALL OPENING
An opening in any wall or partition having both height of at least 750 mm and width of at least
450 mm.
AN OVERVIEW:-
Construction Planning and site management, plays an important role in smooth progress of
a building construction activity.
Repairs, Retrofitting and Strengthening of buildings of both existing and new building.
Habitat and welfare requirements for workers deals with requirements for construction
workers at site.
The objective of universal design and accessibility is to ensure that all users are able to
access all facilities within the built environment.
1. CONSTRUCTION
PROJECT
MANAGEMENT
Project : A project is generally a non-recurring task having a definable
beginning and end, with a definite mission and has a set of objectives and
achievements.
Stakeholder : Stakeholder is a person, group of persons or
organizations who are actively involved in the project or those who have an
interest in the success of a project and its environment.
Construction Project Delivery Models
(a) Traditional design-bid-build,
(b) Design-build with variants,
(c) Turn-key and
(d) Build, operate and transfer and its variants.
9
CONTD...
10
CONTD...
Organizational Structures
11
STAGES OF A CONSTRUCTION PROJECT
Construction planning aspects aim to identify and develop various stages of project
execution on site which should be consistent with the management considerations.
These objectives could relate to the time constraints, cost considerations, quality
standards, safety standards, environmental considerations and health
considerations.
Pre-construction Phase
During preconstruction phase we should adress all the issues related to
the implementation of the design at the site through suitable construction
strategy.
The selection of construction methods, building systems and materials,
components, manpower and equipment and techniques are best done in
the preconstruction phase.
Construction in busy localities of cities needs special considerations and
meticulous planning.
Construction practices in disaster prone areas need specific planning.
Construction practices in hilly regions needs to take into considerations the
problem of landslides.
Resource Planning
Easy access and exit, with proper parking of vehicle and equipment during
construction.
Adequate stack areas for bulk construction materials.
Layout of temporary services (water, power, power suppression unit,
hoists, cranes, elevators, etc).
Adequate yard lighting and lighting for night shifts.
Temporary buildings; site office and shelter for workers (see 14) with
use of non-combustible materials as far as possible including
emergency medical aids.
Cont.
Site Preparation
While preparing the site for construction, bush and other wood, debris, etc.
shall be removed and promptly disposed of so as to minimise the attendant
hazards
Temporary buildings for construction offices and storage shall be so located
as to cause the minimum fire hazards and shall be constructed from
non-combustible materials
Construction of All Elements
It should be ensured that the elements of structure satisfy the
appropriate fire resistance requirements as specified in Part 4
Fire and Life Safety of the Code.
All mechanical, electrical and plumbing (MEP) and other
services in a building shall be installed in accordance with
approved designs.
Quality of building materials/components used shall be in
accordance with Part 5 .Building Materials. of the Code.
Low Income Housing
For low income housing, appropriate planning and selection of
building materials and techniques of construction have to be
judiciously done and applied in practice. Requirements of low
income housing specified in Part 3.Development Control Rules
and General Building Requirements. of the Code shall be
followed.
Use of New/Alternative Construction Techniques
The Authority may approve any such alternative, such as,
ferrocement construction
Pre-engineered steel structures with reinforced concrete
expanded polystyrene core based panel/other in-fill walls
Light gauge steel framed structures with suitable water
resistant wall panels like cement bonded particle board.
Urban Roads/City Roads Planning and Construction
City roads/streets have been under constant development.
Footpaths of various widths and heights are required to be provided.
The objective should be to create urban streets/roads that are efficiently
planned, safe for vehicles as well as pedestrians, universally user friendly,
and sustainable.
The elements required in an efficiently planned street, such as, kerb stones;
kerb channels; kerb ramps; tactile ground surface indicators; silt chambers
with manhole cover; drain cover slabs; drain manhole covers; service
pipes; manhole covers for electrical services; manhole covers for telecom
services; cycle tracks (NMV); bollards across pedestrian paths; tree
gratings etc.
Elements to be Integrated at Planning Stage
Road cross-section planning based on land-use with emphasis
on smooth vehicular movements.
Design of road intersections, fixing of geometrics of roads,
providing provision of entry and exits from the service roads.
Standardization of access manhole covers for various utilities.
Integration of bus queue shelters with the footpath.
Properties integrated with the road through the footpath in
front.
Adequate provision of public conveniences and dust bins.
Low height plantation on central verges , avoiding
plantation of trees.
And many such provisions.
TEMPORARY WORKS
The person organizing the temporary works should be aware of
the problems that can occur at each stage of the process and how
to prevent these.
The cost of any temporary works is generally included in the
build-up of the tender.
Temporary works are often taken from site to site and re-used
and it is important to consider the robustness of components
in their design. However, temporary works that are designed
only to be used during construction shall not be removed until
the satisfactory safety criteria for their use has been met.
Proper planning and co-ordination should be done in respect
of sequence and timely execution of temporary works, as
also for ensuring that they are correctly installed, used, 36
Scaffolding
Tower Cranes
Falsework-Temporary structure used to support
other permanent structures.
Formwork
Scaffolding
Tower Cranes
Falsework
Formwork
STORAGE, STACKING AND HANDLING
PRACTICES
12.Finishes
Painting, Polishing and other finishes Only the quantity required should be kept at work
spot. 5 kg dry powder fire extinguisher.
Checking and repairing gas pipes, water pipes and plumbing services
Rebuilding non-structural walls, smoke
Re-plastering of walls, as required
Rearranging disturbed roofing tiles
Relaying cracked flooring at ground level
Structural Repairs/Restoration
Prior to taking up of the structural repairs for restoration of original strength
and any strengthening measures, it is necessary to conduct detailed
damage assessment to determine, the structural condition of the building
to decide whether a structure is amenable for repair;
whether continued occupation is permitted; to decide the structure as a
whole or a part require demolition, if considered dangerous;
if the structure is considered amenable for repair then detailed damage
assessment of the individual structural components (mapping of the crack
pattern, distress location; crushed concrete, reinforcement
bending/yielding, etc). Non-destructive testing techniques could be
employed to determine the residual strength of the members
Seismic Strengthening
The main purpose of the seismic strengthening is to upgrade the seismic resistance
of a damaged building while repairing so that it becomes safer under future
earthquake occurrences. This work may involve some of the following actions
Increasing the lateral strength in one or both directions by increasing column and
wall areas or the number of walls and columns.
Giving unity to the structure, by providing a
proper connection between its resisting elements, in such a way that inertia
forces generated by the vibration of the building can be transmitted to the
members that have the ability to resist them. Typical important aspects are the
connections between roofs or floors and walls, between intersecting walls and
between walls and foundations.
Cont.
eliminating features that are sources of weakness or that produce
concentration of stresses in some members. Asymmetrical plan distribution of
resisting members, abrupt changes of stiffness from one floor to the other,
concentration of large masses and large openings in walls without a proper
peripheral reinforcement are examples of defects of this kind.
Strengthening or Retrofitting Versus Reconstruction:
Replacement of damaged buildings or
existing unsafe buildings by reconstruction is, generally, avoided due to a
number of reasons, the
main ones among them being,
a) higher cost than that of strengthening or retrofitting;
b) preservation of historical architecture; and
c) maintaining functional social and cultural environment.
6.HABITAT AND
WELFARE
REQUIREMENTS FOR
WORKERS
Habitat site selection criteria
Design of the habitat
Specifications of the living area
Fire and safety requirements
First aid and medical requirements
Security
Waste management
Habitat inspection and monitoring
HABITAT SITE SELECTION CRITERIA