Beruflich Dokumente
Kultur Dokumente
Part 2:
ROLE OF DOCUMENT MANAGEMENT IN CLAIM
MANAGEMENT/NEGOTIATION
CONTRACTOR
Project Design and Finance and
Procurement Document
Management Engineering Site Accounting
Department Controller
Department Department Department
Claim/Dispute negotiation
Analyze Analyze
Loss of Impact of Perform
Perform Productivity Specific Fact-finding &
Claim issues
Preliminary Technical
Analysis Analyze Time-Impact Issue
(Delay) Analysis
Review contract
Contracts
document
Prioritize issues
Apply appropriated
delay analysis methodology
Critical path
Identify major-minor
project delay
Determine
Critical delays
critical delays
*The Society of Construction Law, Delay and Disruption Protocol: October 2002 (October2004 reprint)@¶4.8 p.47
Apply appropriated
delay analysis methodology
Critical path
Identify major-minor
project delay
Determine
Critical delays
critical delays
Plumbing
Actual Manhours
Electrical
HVAC
Perform submittal
Submittal log Submittal Analysis
Analysis
Significant over-under
resource utilization
Critical delays
#1
PROCUREMENT
Structural Steel
7/19 -49
56 CD ERECT FABRICATE
(GAIN) Structural Steel MEP Penthouse
57 CD -77 -22 -31
(GAIN) PROCUREMENT
Building Curtain Wall
-44 -21 -15 -55 -56 -32 -61 -35
FINISHES
Courtroom Millwork
6/9
ERECT Bldg
Building Curtain Wall Complete
-15 -55 -56 -32 -61 -35 6/16 -5 8/7
36
SUMMARY OF CRITICAL DELAYS TO PROJECT COMPLETION:
DELAYS PARTIES RESPONSIBLE FOR CRITICAL DELAYS
TIME FRAME CRITICAL WORK DESCRIPTION TRADE ISSUES IMPACTS AND (GAINS)
10/08/96 PROCUREMENT OF
STEEL SHOP DRAWING PROCESS 49 CD General Contractor / SS Subcontractor
01/13/97 STRUCTURAL STEEL
01/14/97 STRUCTURAL STEEL EARLY 56 CD
05/07/97
ERECTION OF STRUCTURAL STEEL STEEL
START (GAIN)
General Contractor / SS Subcontractor
CONCRETE PLACEMENT OF BASEMENT MODIFICATION #45 / SLAB 57 CD
05/08/97
SLAB ON GRADE
CONCRETE
ON GRADE (GAIN)
General Contractor / Owner
FABRICATION OF 5TH – 11TH FLR
05/08/97 ERECTION OF STRUCTURAL STEEL STEEL
EAST STRUCTURAL STEEL
99 CD General Contractor / Subcontractor
05/08/98 PROCUREMENT OF BUILDING CURTAIN INABILITY OF METRO PANEL TO
WALL
C/W
KEEP THEIR ENG’G SCHEDULE
65 CD General Contractor / CW Subcontractor
05/09/98
01/08/99
FABRICATION OF PENTHOUSE MEP MEP LATE START OF FABRICATION 31 CD General Contractor / MEPS Subcontractor
05/09/98 PROCUREMENT OF BUILDING CURTAIN
C/W
LATENT BLDG CURTAINWALL &
254 CD
General Contractor / CW Subcontractor
08/08/99 WALL & ERECT COMPLETION INSTALLATION AND REPLACEMENT CONTRACTORS
08/09/99
08/07/00
BULIDING FINISHES FINISHES RETROFIT / FINISH WORK 5 CD General Contractor / Finish Subcontractor
390 CD
12.81 Mos.
• Direct Labor
– Direct labor overrun
– Wage Escalation
– Loss Productivity
• Direct Material
• Direct Equipment
For example, if additional labor hours are 31,500 hrs and applicable wage rate
is $17.50. Once the hours, wage rates, and labor burdens percentage are
determined, calculating direct labor overrun calculation is as
Direct labor cost overrun = Additional labor hours * Applicable wage rate
For example, if employee-related expenses are $627,394 and total labor costs
including burden are &$1,575,000.
Total direct labor overrun = Direct labor cost overrun + Labor burden
For example, if additional labor hours after wage increase are $2,500 hrs and
Difference between anticipated and actual rates are $3.5/hr
Master plan
Project Baseline/Planne
(Baseline/Planned
Management d productivity
productivity)
Actual unit
Supplier’s invoices Finance& Account
rate/Material cost
Amount of time
Payroll records of operating
Finance& Account equipment was being
engineer
operate
Actual cost of
Invoice from third-party vendor Finance& Account
equipment
[Total Contract Billings] / [Total Company Billings for Contract Period] * [ Home Office
Overhead for Actual Contract Period ] = Home Office Overhead Allocable to the
Contract
Select
negotiating team •Negotiating team
Setup meeting
& prepare agenda
Settle
the claim Dispute
• Compensation
Make the deal
• Time of payment