Sie sind auf Seite 1von 63

CE70.

44 Communication & Negotiation Skills for PMs


Document Management

Part 2:
ROLE OF DOCUMENT MANAGEMENT IN CLAIM
MANAGEMENT/NEGOTIATION

CE70.44 Communication & Negotiation Skills for PMs 1


COMMUNICATION AND NEGOTIATION

DESIGNER THE EMPLOYER AUTHORITY

CONTRACTOR
Project Design and Finance and
Procurement Document
Management Engineering Site Accounting
Department Controller
Department Department Department

Communication and Negotiation between parties

Communication and collaboration between


SUPPLIERS SUBCONTRACTORS Project Team

Claim/Dispute negotiation

CE70.44 Communication & Negotiation Skills for PMs 2


Impacted Claim Analysis Process

Analyze Analyze
Loss of Impact of Perform
Perform Productivity Specific Fact-finding &
Claim issues
Preliminary Technical
Analysis Analyze Time-Impact Issue
(Delay) Analysis

Determine Prepare Conduct


Summarize
Causation& Claim Report Meetings
&
Assign With To discuss,
Calculate
responsibility Backup & Negotiate,& settle
compensation
Exhibit The claim

CORE PROCESS: Impact Claim Analysis Process

CE70.44 Communication & Negotiation Skills for PMs


1. Perform preliminary analysis

“Get understanding of key project records &


Claim documents”

CE70.44 Communication & Negotiation Skills for PMs


1. Perform preliminary analysis
INPUT PROCESS OUTPUT

Review contract
Contracts
document

Counter parties’ submittal Understand Counter


claims parties’ submittal claims

Identify Hot issues & List of Hot issues &


Staff Interview
damage damages problematic areas

Prioritize issues

Preliminary issue summary Preliminary issue reports

CE70.44 Communication & Negotiation Skills for PMs


Sample of Preliminary Analysis

• Curtain wall Delay


• Difference Site Condition
• Water Leakage
• Veneer Damage

CE70.44 Communication & Negotiation Skills for PMs


2. Analyze Time Impact

“Demonstrate accurately the impact of event


upon the project schedule and overall project
completion”

CE70.44 Communication & Negotiation Skills for PMs


2. Analyze Time Impact (Delay)
INPUT PROCESS OUTPUT

Level of detail in WBS


Analyze/Adjust the
As-planned schedule
baseline schedule
Appropriateness
of logic & duration
Develop As-built
Updated schedule
Schedule

Apply appropriated
delay analysis methodology
Critical path

Identify major-minor
project delay

Determine
Critical delays
critical delays

CE70.44 Communication & Negotiation Skills for PMs


Type Delay Claim

CE70.44 Communication & Negotiation Skills for PMs


Standard delay evaluation techniques

• As-planned vs. As-built


• Impacted As-planned
• Time Impact Analysis

Depend upon the availability of Project


records/Documentation

CE70.44 Communication & Negotiation Skills for PMs


General Delay Analysis Methodology

“Time Impact Analysis” methodology

• The Society of Construction Law (“SCL”) is a noted international


authority which provides guidance on common issues that arise with
construction contracts. The SCL states* that the “Time Impact
Analysis” methodology “is based on the effect of Delay Events on the
Contractor’s intentions for the future conduct of the work in the light
of progress actually achieved at the time of the Delay Event...”

*The Society of Construction Law, Delay and Disruption Protocol: October 2002 (October2004 reprint)@¶4.8 p.47

CE70.44 Communication & Negotiation Skills for PMs 11


General Delay Analysis Methodology
“Time Impact Analysis” methodology
• The SCL provides guidance as to how to perform a “Time Impact Analysis.”
• The SCL states* that the amount of EOT is obtained by using the Updated
Programme and that the steps to be taken are as follows:
• the Programme should be brought fully up to date (as to progress and the
effect of all delays that have occurred up to that date, whether Employer
Delays or Contractor Delays) to the point immediately before the
occurrence of the Employer Risk Event;
• the Programme should then be modified to reflect the Contractor’s realistic
and achievable plans to recover any delays that have occurred, including
any changes in the logic of the Programme proposed for that purpose;
• the sub-network representing the Employer Risk Event should then be
entered into the programme; and,
• the impact on the contract completion dates should be noted.
*The Society of Construction Law, Delay and Disruption Protocol: October 2002 (October2004 reprint)@¶3.2.7 pp.43-44

CE70.44 Communication & Negotiation Skills for PMs 12


Schedule Analysis
AS-BUILT SCHEDULE
Multiple Prime Contractors

CE70.44 Communication & Negotiation Skills for PMs


Schedule Analysis
DELAY RESPONSIBILITY
Curtainwall Installation

CE70.44 Communication & Negotiation Skills for PMs


Disruption Analysis

ASIAN INSTITUTE OF TECHNOLOGY 19 MAY – 01 JUNE 2013

CE70.44 Communication & Negotiation Skills for PMs


3. Analyze Loss of Productivity Claim

“Compare the labor productivity on similar


work during period of No Impact with labor
productivity during period of Claim Impact”

CE70.44 Communication & Negotiation Skills for PMs


3. Analyze Loss of Productivity Claim (Disruption-
Acceleration)
INPUT PROCESS OUTPUT

Level of detail in WBS


Analyze/Adjust the
As-planned schedule
baseline schedule
Appropriateness
of logic & duration
Develop As-built
Updated schedule
Schedule

Apply appropriated
delay analysis methodology
Critical path

Identify major-minor
project delay

Determine
Critical delays
critical delays

CE70.44 Communication & Negotiation Skills for PMs


Disruption Analysis
MEP Planned vs. Actual Man-hours through 31Dec07

Planned Manhours Actual Man-hours by System through 31Dec07

Plumbing
Actual Manhours

Electrical

HVAC

19 MAY – 01 JUNE 2013

CE70.44 Communication & Negotiation Skills for PMs


4. Analyze Impact of Specific Issues

“Change Order, Submittal, and RFI”

CE70.44 Communication & Negotiation Skills for PMs


4. Analyze Impact of specific issues
INPUT PROCESS OUTPUT

Perform change Graphic Change


Change order log
order analysis order analysis

Identify significant Significant Change order


change order caused delay

Perform submittal
Submittal log Submittal Analysis
Analysis

Identify significant Significant submittal


change order caused delay

RFI log Perform RFI analysis Graphic RFI analysis

Identify Significant RFI


significant RFI Caused delay

CE70.44 Communication & Negotiation Skills for PMs


Submittal Analysis- Submittal Response Time

CE70.44 Communication & Negotiation Skills for PMs


Submittal Analysis: Submittal Approval Status

CE70.44 Communication & Negotiation Skills for PMs


Submittal Analysis: Cumulative Drawing Submission

CE70.44 Communication & Negotiation Skills for PMs


Submittal Analysis

CE70.44 Communication & Negotiation Skills for PMs


RFI Analysis- RFI Timeline

CE70.44 Communication & Negotiation Skills for PMs


RFI Analysis

CE70.44 Communication & Negotiation Skills for PMs


5. Fact Finding & Issue Analysis

“Perform based on a list of Hot Issues&


Damage Problematic Area acquired from
the Preliminary Analysis”

CE70.44 Communication & Negotiation Skills for PMs


5. Perform Fact finding & Technical issue analysis
INPUT PROCESS OUTPUT

• Correspondence •Perform fact finding &


• Meeting minute Issue analysis Issue files
• Daily inspection report
• E-mail
• Fax transmittal
• Photo,Video •Perform technical Brief summary of
issue analysis each issue

List of Hot issues & • Cause of Delay


damages problematic areas • Owner directive to
accelerate the work
• Owner disruption
Preliminary issue reports

Significant over-under
resource utilization

Significant Change order,


submittal,RFI caused delay

Critical delays

CE70.44 Communication & Negotiation Skills for PMs


Fact Finding

CE70.44 Communication & Negotiation Skills for PMs


Issue Analysis

Issue Curtain Wall

CE70.44 Communication & Negotiation Skills for PMs


Issue Analysis

#1

ASIAN INSTITUTE OF TECHNOLOGY 19 MAY – 01 JUNE 2013


31

CE70.44 Communication & Negotiation Skills for PMs


6. Assign Responsibilities

“Identify the cause of delay since any


parties involved in construction may be a
source of delay”

CE70.44 Communication & Negotiation Skills for PMs


6. Determine causation & Assign responsibilities
INPUT PROCESS OUTPUT

Brief summary Determine causation


& Allocate delay responsibilities Issue files
of each issue

• Owner caused delays


•Significant Change order Analyze concurrent delays
• Contractor caused delays
•,submittal,RFI caused delay & individual delays
• Concurrent delay

Prepare schedule-delay Schedule –delay


Critical delays
analysis in graphic Analysis (Timeline)

This Step could be done concurrently with Time Impact Analysis

CE70.44 Communication & Negotiation Skills for PMs


6. Determine causation & Assign responsibilities
INPUT PROCESS OUTPUT
Disruption Claim
Brief summary Perform Disruption: Cause Disruption: Cause & Effect
of each issue & Effect Relationship Relationship

Significant over-under resource


utilization & loss of productivity

Constructive Acceleration Claim


Brief summary Check with five conditions of proving
a constructive acceleration claim
of each issue

Significant over-under resource


Perform Constructive Acceleration: Constructive Acceleration:
utilization & loss of productivity
Cause & Effect Relationship Cause & Effect

This Step could be done concurrently with Time Impact Analysis

CE70.44 Communication & Negotiation Skills for PMs


Assign Responsibilities
DELAY RESPONSIBILITY
Curtainwall Installation

CE70.44 Communication & Negotiation Skills for PMs


Assign Responsibilities
1996 1997 1998 1999 2000
J A S O N JD F M A M J J A S O N D
J F M A M J J A S O N D
J F M A M J J A S O N D
J F M A M J J A S O N D

PROCUREMENT
Structural Steel
7/19 -49
56 CD ERECT FABRICATE
(GAIN) Structural Steel MEP Penthouse
57 CD -77 -22 -31
(GAIN) PROCUREMENT
Building Curtain Wall
-44 -21 -15 -55 -56 -32 -61 -35
FINISHES
Courtroom Millwork
6/9
ERECT Bldg
Building Curtain Wall Complete
-15 -55 -56 -32 -61 -35 6/16 -5 8/7
36
SUMMARY OF CRITICAL DELAYS TO PROJECT COMPLETION:
DELAYS PARTIES RESPONSIBLE FOR CRITICAL DELAYS
TIME FRAME CRITICAL WORK DESCRIPTION TRADE ISSUES IMPACTS AND (GAINS)
10/08/96 PROCUREMENT OF
STEEL SHOP DRAWING PROCESS 49 CD General Contractor / SS Subcontractor
01/13/97 STRUCTURAL STEEL
01/14/97 STRUCTURAL STEEL EARLY 56 CD
05/07/97
ERECTION OF STRUCTURAL STEEL STEEL
START (GAIN)
General Contractor / SS Subcontractor
CONCRETE PLACEMENT OF BASEMENT MODIFICATION #45 / SLAB 57 CD
05/08/97
SLAB ON GRADE
CONCRETE
ON GRADE (GAIN)
General Contractor / Owner
FABRICATION OF 5TH – 11TH FLR
05/08/97 ERECTION OF STRUCTURAL STEEL STEEL
EAST STRUCTURAL STEEL
99 CD General Contractor / Subcontractor
05/08/98 PROCUREMENT OF BUILDING CURTAIN INABILITY OF METRO PANEL TO
WALL
C/W
KEEP THEIR ENG’G SCHEDULE
65 CD General Contractor / CW Subcontractor
05/09/98
01/08/99
FABRICATION OF PENTHOUSE MEP MEP LATE START OF FABRICATION 31 CD General Contractor / MEPS Subcontractor
05/09/98 PROCUREMENT OF BUILDING CURTAIN
C/W
LATENT BLDG CURTAINWALL &
254 CD
General Contractor / CW Subcontractor
08/08/99 WALL & ERECT COMPLETION INSTALLATION AND REPLACEMENT CONTRACTORS
08/09/99
08/07/00
BULIDING FINISHES FINISHES RETROFIT / FINISH WORK 5 CD General Contractor / Finish Subcontractor
390 CD
12.81 Mos.

CE70.44 Communication & Negotiation Skills for PMs


7. Calculate Compensation

“Evaluate and Demonstrate that increase


cost were actually been incurred”

CE70.44 Communication & Negotiation Skills for PMs


Treatment of Direct Cost

• Direct Labor
– Direct labor overrun
– Wage Escalation
– Loss Productivity
• Direct Material
• Direct Equipment

CE70.44 Communication & Negotiation Skills for PMs


Direct Labor

CE70.44 Communication & Negotiation Skills for PMs


Total Direct Labor Overrun Calculation

CE70.44 Communication & Negotiation Skills for PMs


1. Direct Labor Overrun
“The additional labor hours expended in performance of the contract which
exceed the labor hours originally estimated for performance”
Causes and Reasons Documents Department Information

Payroll record Human resource

Daily labor report Project Management Additional work hours

Other supporting documents Document control


Owner-caused delay,
Acceleration, directive to Union contract (Wage rate) Finance& Account
Applicable wage rate
perform work outside the Account record (Wage rate) Finance& Account
scope of contract

Labor burden record (Taxes,


Workers’ compensation, Insurance, Finance& Account Labor burden
Benet& Supervisory cost

CE70.44 Communication & Negotiation Skills for PMs


Direct Labor Overrun Calculation
Direct labor cost overrun = Additional labor hours * Applicable wage rate

Sample of Total Direct Labor Overrun Calculation

For example, if additional labor hours are 31,500 hrs and applicable wage rate
is $17.50. Once the hours, wage rates, and labor burdens percentage are
determined, calculating direct labor overrun calculation is as

Direct labor cost overrun = Additional labor hours * Applicable wage rate

Direct labor cost overrun = 31,500 hrs * $17.50/hr = $551,250

CE70.44 Communication & Negotiation Skills for PMs


2.Labor Burdens
“a Cost directly related to the employment of individuals but not reflected in
the employees’ wage”
Causes and Reasons Documents Department Information

Man-loading schedule Project Management Period in which labor


hour were expended
Labor timesheet Construction
Daily report Construction
Actual wage rate
Payroll record Finance& Account
Delay, Changes, Other acts
of the owner which push Union wage rate Project Management
performance of the contract Original wage rate
into a higher rate
Original wage rate Project Management

Labor burden record (Taxes,


Workers’ compensation, Insurance, Finance& Account Labor burden
Benet& Supervisory cost

CE70.44 Communication & Negotiation Skills for PMs


Labor burden Calculation
Labor burden = Direct labor overrun * Labor burden percentage

Sample of Labor Burden Calculation

For example, if employee-related expenses are $627,394 and total labor costs
including burden are &$1,575,000.

Labor burden percentage = Employ-related Expense/ [Total Labor Cost


including burden - Sample of Direct Labor Overrun Calculation] * 100
Labor burden percentage = $627,394/ [1,575,000-$627,394]*100 = 66.21%

Labor burden = Direct labor overrun * Labor burden percentage


Labor burden = $551,250 * 66.21% = $364,983

CE70.44 Communication & Negotiation Skills for PMs


Total Direct Labor Overrun Calculation
Total Direct Labor Overrun = Direct labor cost overrun + Labor burden

Total direct labor overrun = Direct labor cost overrun + Labor burden

Total direct labor overrun = $551,250+$364,983 = $916,233

CE70.44 Communication & Negotiation Skills for PMs


Wage Escalation

CE70.44 Communication & Negotiation Skills for PMs


Wage Escalation
Causes and Reasons Documents Department Information

Man-loading schedule Project Management Period in which


labor hour were
Labor timesheet Construction expended
Daily report Construction
Actual wage rate
Payroll record Finance& Account
Delay, Changes, Other
acts of the owner
which push Union wage rate Project Management
performance of the Original wage rate
contract into a higher Original wage rate Project Management
rate

Labor burden record (Taxes,


Workers’ compensation,
Finance& Account Labor burden
Insurance, Benet&
Supervisory cost

CE70.44 Communication & Negotiation Skills for PMs


Sample of Wage Escalation Calculation
Sample of Wage Escalation Calculation

For example, if additional labor hours after wage increase are $2,500 hrs and
Difference between anticipated and actual rates are $3.5/hr

Wage Escalation Cost = Hours worked after wage increase * Difference


between anticipated and actual cost
Wage Escalation Cost = 2,500 hrs*$3.5/hr = $8,750

Labor burden = Wage Escalation Cost * Labor burden percentage


Labor burden = $8,750*66.21% = $5,790

Total Wage Escalation Cost = Wage Escalation Cost + Labor burden


Total Wage Escalation Cost = $8,750+$5,790 = $14,543

CE70.44 Communication & Negotiation Skills for PMs


Loss of Productivity

CE70.44 Communication & Negotiation Skills for PMs


Loss of Productivity
Causes and Reasons Documents Department Information

Job cost record report Construction

Finance& Actual cost


Pay requisition during impacted
Account
Delays, Change, period (Ex. Work
Acceleration Inspection report Construction
hour per linear
orders, foot/Labor cost
Deceleration per sq. foot)
orders, and Daily job log Construction
weather condition

Master plan
Project Baseline/Planne
(Baseline/Planned
Management d productivity
productivity)

CE70.44 Communication & Negotiation Skills for PMs


Direct Material

CE70.44 Communication & Negotiation Skills for PMs


Claim for Direct Material Cost
• Additional material
• Material Escalation

CE70.44 Communication & Negotiation Skills for PMs


Additional material
Causes and
Documents Department Information
Reasons
Original BOQ & Original
Project
Defective Unit Rate (Bid quantity of
Management
Specification, Estimate) material
Owner- Actual
directed Finance& quantity and
Supplier’s invoices
change Account cost of
material

CE70.44 Communication & Negotiation Skills for PMs


Material Escalation
Causes and Reasons Documents Department Information

Original Unit Rate (Bid Project


Estimate) Management
Original unit
rate/Material cost
Material cost (Engineering Project
Owner-caused delay new record) Management

Actual unit
Supplier’s invoices Finance& Account
rate/Material cost

CE70.44 Communication & Negotiation Skills for PMs


Direct Equipment

CE70.44 Communication & Negotiation Skills for PMs


Claim for Direct Equipment Cost
Causes and Reasons Documents Department Information

Amount of time
Payroll records of operating
Finance& Account equipment was being
engineer
operate

Hour& activities by cost


Equipment timecard (timesheet) Construction code for each individual
piece of equipment
Defective Specification,
Owner-directed change

Project master plan-Equipment Estimated equipment


Project Management
schedule hours

Bid estimate-Internal equipment Internal rate of


Project Management
rate equipment

Actual cost of
Invoice from third-party vendor Finance& Account
equipment

CE70.44 Communication & Negotiation Skills for PMs


Head Office Overhead

CE70.44 Communication & Negotiation Skills for PMs


Head Office Overhead
“Overhead generally consists of all other company costs that
cannot be directly attributable to a particular project. This would
include company management, home office ownership costs or
rent, and home office support staff and functions”

CE70.44 Communication & Negotiation Skills for PMs


Eichley Formula

[Total Contract Billings] / [Total Company Billings for Contract Period] * [ Home Office
Overhead for Actual Contract Period ] = Home Office Overhead Allocable to the
Contract

[ Home Office Overhead Allocable to Contract] / [Actual Days of Contract


Performance] = Daily Home Office Overhead Allocable to Contract

[Daily Home Office Overhead Allocable to Contract] * [ Number of Days of Delay] =


[Extended Home Office Overhead]

CE70.44 Communication & Negotiation Skills for PMs


8. Prepare Claim Presentation

“Claim presentation should be


logically built up, well organized,&
factually convincing”

CE70.44 Communication & Negotiation Skills for PMs


Prepare claim report with backup & exhibit (Claim
presentation)
INPUT PROCESS OUTPUT

Compensation for delay Develop claim


, acceleration, and disruption presentation strategy

Schedule –delay Write claim summary


analysis (Timeline) report & presentation

Prepare backup & exhibit Claim report

CE70.44 Communication & Negotiation Skills for PMs


9. Meeting, Negotiation, and Settle Claim

Determine “What they must have” &


“What they are willing to give”

CE70.44 Communication & Negotiation Skills for PMs


Conduct meetings to discuss, negotiate, & settle claim
INPUT PROCESS OUTPUT

Determine minimum compensation


Claim report required to settle the claim •Negotiating goal

Select
negotiating team •Negotiating team

Setup meeting
& prepare agenda

Present the claim

Settle
the claim Dispute

• Compensation
Make the deal
• Time of payment

CE70.44 Communication & Negotiation Skills for PMs

Das könnte Ihnen auch gefallen