Deming Cycle
Identify work
Follow up related
And Review problems
Selection of
1 problem
Regular 2
Implementation
Define the
3 problem
4
Analyze
5
Trial
Implementation 6
9 7
8
Foresee Resistance
And Prepare
Technique-Brainstorming(Group Passing)
Step-1
Identification of Problem 4
Identification of Problem
S.No Problems S.No Problems
1 Lack of sludge disposal system. 26 DCP2&3RC Vertical pump gland leak
2 Manpower required for safe and timelyexecution of maintenance activities. 27 DCP2&3RA ARV valve gland leak
Problems 3
4
Addition pump standby requirement for backwash water pump.
For reutilisation of CT blowdown water additional pipeline required.
28
29
DCP2&3RC Discharge valve gland leak
SP-1 Poor lighting
Bank 5
6
New PLC required for filtration plant.
All pumps ICW/DCW and Scale pit Flow and Pressure display should be on VNCC.
30
31
SP-1 Incomplete barrication
SP-1 Improper ladder for bia-pass valve
7 SSPF Filtration Plant "F" valve malfunctioning. 32 Scale pit 1 Oil collection area slippery
8 Failure of Backwash Pump 33 Scale pit 1 Oil collection tank not functioning properly
9 SP 1,2,3 Vertical pump maintenance area not available for spare pump maintenance. 34 Scale pit 1 Oil Skimmer boom not rotating for maintenance
10 CT-1 overflow water optimization. 35 Scale pit 1 No pressure gauge on pump discharge
11 IC-3 diesel pump oil pressure is low. 36 Scale pit 1 pump discharge flow transmitter not working
12 ECRW-1 cable trench height is low. 37 Scale pit 2 Otoklin filter motor shed not available
13 Scale pit 2 online filter backwash water optimization. 38 Scale pit 2 Otoklin filter backwash reading not working
14 ECR W-1 drainage water optimization. 39 Dcp 4RC/D Discharge current get reduced after some interval
15 Scale pit -1 flooding . 40 Scale pit 2 Unwanted material in pump pit
16 No Coupling guard to DCP2&3RA 41 Scale pit 2 Unwanted Material in MCC room
17 No Coupling guard to DCP2&3RA 42 No coupling guard for Dcp 4RC
18 No Coupling guard to DCP2&3RA 43 No coupling guard for Dcp 4RD
19 DCP 2&3RC discharge valve problem 44 Dcp 4RA Pump Heavy gland leakage
20 DCP 2&3RB NRV leak 45 Dcp 4RB Pump Heavy gland leakage
21 Dcp 2&3RA/RC NRV get stuck 46 Dcp 4RC Pump Heavy gland leakage
22 DCP 2&3RA Dischage valve hard to operate 47 Dcp 4RD Pump Heavy gland leakage
23 SP-1 Bia-Pass valve gland Leak 48 Dcp 4RA discharge valve gland leakage
24 DCP2&3RA Discharge valve gland leak 49 Dcp 4RB discharge valve gland leakage
25 DCP2&3RC ARV valve pass 50 Dcp 4RC discharge valve gland leakage
Problems 103
104
DCP1B Discharge valve flange joint heavy leak
DCP1E Pumps Bearing failure
128
129
ICP 1 Pumps discharge valve cannot open 100%
ICP 1 Pumps gland leakage
Bank 105
106
DCP1D/E Header recirculation valve jam
All DCP1 Pipeline are interconnected need isolation according to zone
130
131
ICP 2 Flow/Pressure not available on PLC
ICP 2 Pumps Discharge valve cannot open 100%
107 DCP1C NRV need to be lift 132 ICP 2 Pressure frequent complaint from caster
108 DCP1G Current less in caster break 133 ICP 2B Pumps casing leakage.
109 Pressure Transmitter required for all DCP1 pumps Discharge and suction pipeline 134 No suction strainer in ICP 2D
110 Caster 1/2 all zones individual flow transmitter required 135 ICP 2D tripping Frequently without indication/Alarm
111 DCP 1 Pumps heavy leakage 136 DCP1C High Vibration
112 All DCP Pump current not showing on PLC 137 ICP 2 MM30 display in very low need to bend to take reading
113 DCP 1F Pump not available 138 Filtration plant All Pneumatic valve malfunctioning
114 DCP 2 Pump back pressure in roll change 139 ICP 3 Flow/Pressure not available on PLC
115 DCP 2D Pump Abnormal Noise from NRV 140 ICP 3 NRV Passing
116 DCP 2 Gland Cooling Hose broken from last 2 month 141 ICP 4A Discharge valve problem
117 DCP 2B Discharge valve gear box tight 142 ICP 4 Gland leakage
118 DCP 2 individual and header Pressure Transmitter Required 143 ICP 4 Flow/Pressure not available on PLC
119 DCP 3A Pump starting problem occurs 2 times 144 No suction strainer in ICP 4 Pumps
120 DCP 3A Motor Fan guards damaged 145 No ICP 5 standby Pump available in Higher width casting
121 DCP 3A Pressure complaint from descaler 146 Scale pit 2 Amaid filter motor shed not available
122 DCP 3 Pumps on starting descaler Pump get tripped 147 ICP 5 Flow/Pressure not available on PLC
123 DCP 3 Pumps flow/pressure not available on plc screen 148 ONLINE PH/Turbidity/TSS Meter not Available
124 DCP 4 Flow transmitter Malfunctioning 149 Wash water tank dosing risky
125 DCP 4 Discharge valve cannot open 100% 150 Water sample bottle are not clean
40% 39%
A(Within Dept.)
B(Cross Functional)
C(Management Support)
7% 14%
Problems Solved
D(Delivery)
14%
S(Safety)
13%
3% M(Morale)
0% E(Environment)
Type of Problem No. of Problems
Impact
P(Productivity)
No of Problems
24 Quality Circle 18
Q(Quality) 8
C(Cost) 2 Kaizen 6
D(Delivery) 0
S(Safety)
M(Morale)
8
3
Total 24
E(Environment) 14
Total 59
Step-2 Selection of Problem 18
Problem Summary
Theme Based
Complexity
Categorization for A-type
Complexity No. of Problems Impact No of Problems
A(Within Dept.) 59 P(Productivity) 24
B(Cross Functional) 21 Q(Quality) 8
C(Management 10 C(Cost) 2
Support)
D(Delivery) 0
S(Safety) 8
A-type (Productivity)
M(Morale) 3
Quality Circle 18
THEME SELECTED
Kaizen 6
PRODUCTIVITY
Step-2 Selection of Problem 19
Prioritization of Problem(Rating Method)
Harinarayana
Ashirwad
Prashant
Shirke
Rajam
Amar
Atish
Total
S.No
Ajit
Problems
Project
Quality Cost Productivity Delivery Safety Morale
Classification
Impact:
*Re pe a te dl y fa i l ure of pump NDE be a ri ng
*Non a va i l a bi l i ty of pump ma y ha mpe r producti on proce s s
Goal D C P 1 C V ib ra tio n R e a d in g B e f o r e
25
Characteristic Target date of completion
20
Sl. No. under Current Level Goal
Vibration reading in mm
42491
15 42552
improvement 42644
10 42675
1 2 3 4 5 6 7 8 9 10 11 12
21
Business Excellence Dolvi
PLANNED MONTH
Sr.No STEPS ------ Mar April May June
----- 15/3/2017 22/3/2017 29/3/2017 5/4/2017 12/4/2017 19/4/2017 26/4/2017 3/5/2017 10/5/2017 17/5/2017 24/5/2017 31/5/2017 7/6/2017 14/6/2017 28/06/2017
P
1 Identify Problems
A
P
2 Selection of problem
A
P
3 Define Problem
A
P
4 Analyze
A
P
5 Identify Causes
A
P
6 Identify Root Causes
A
P
7 Data Analysis
A
P
8 Develop Solution
A
P
9 Foresee Resistance
A
P
10 Trial Implementation
A
P
11 Regular Implementation
A
P
12 Follow up and Reviews
A
P-PLANNED Prepared By Rajam S D
A-ACTUAL Approved By Ajit mokal
BOOSTER PUMPS
ZONES 4 TO 8 ZONES 1 TO 3 ZONES 4 TO 8
PRV
SCALE PIT - 3
DC-1R E
D C-1RD DC-1R A/B/C PUMP
PUMP PUMP 665 CuM/Hr
360 CuM/Hr 665 CuM/Hr @ 4.7 b ar
@ 4.5 b ar @ 4.5 b ar
Chart Title
20
15 May-16
Jul-16
Oct-16
Nov-16
Good
10
Satisfactory
0
1 2 3 4 5 6 7 8 9 10 11 12
Monthwise
High Vibration of
HSM CSP Vibration reading Vibration reading
Caster Direct Spray
Utility 1.8mm/sec to 4.5mm/sec 10.74mm/sec
cooling Pump DCP 1C
Problem
Statement • Non Drive End side bearing failure
WHERE
Very High
Vibration
In DCP1C • Over an period of a year
WHEN
Pump
• DCP 1 Caster Spray cooling Circuit
WHO Reduction of
Vibration
Reading from
• Very high Vibration Reading of 10.74mm/sec 10.74mm/sec
HOW
to
3-4mm/sec
31
Brainstorming Points (Identifying possible causes)
1 Unbalanced rotating components 15 Impeller relief hole obstructed/choked
2 Bent Shaft{Shaft Straightness) 16 Debris/Foreign particulates in impeller
3 Sleeve Damage 17 Clogged suction Line
4 High vibration 18 Partially/Plugged strainer
5 Cavitation 19 Insufficient Suction
6 Improper mounting of bearing 20 Pump base shim packing deteriorate
7 Bearing wear out prematurely 21 Improper pump assembly
8 Bearing Housing damage 22 Misalignment
9 Bearing quality 23 Base Frame deteriorate
10 Worn or loose bearing 24 Coupling bushes worn
11 Clearance of bearing 25 Coupling pin hole damaged
12 Internal Recirculation 26 Pipe Strain
13 Impeller Imbalance 27 Pipe Stress
14 Maximum size impeller 28 Pipe Support deteriorate
36
Step-6 Identify Root Cause 37
Validation of possible Causes
Validating
Sr.No Probable Causes Valid Invalid
Techniques
1 Base Frame Deteriorate Observation √
2 Bearing wear out prematurely Data base √
3 Pipe Strain Expert Advice √
4 Frequency of Greasing is low Database √
5 Coupling Damaged Observation √
6 Misalignment Observation √
7 Improper Pump Assembly Database √
8 Bent Shaft Observation √
9 Bearing quality Data base √
10 Cavitation Observation √
11 Contaminated grease Observation √
Step-6 Identify Root Cause 38
List of Validated Cause
Cause Cause
No 4 Rusty shim packing taken out No 1
Cause No 3
Step-6 Identify Root cause 40
Cause
No 6
PUMP SUCTION /DISCHARGE PIPELINE WAS FIND OUT BY 3-4 MM
Pump suction
pipe cutting
done find out Pump discharge
by pipe cutting
approximately done find out by
5mm approximately
6mm
43
DCP#1 Pump bearing failure
25
DCP1A/B/C/D
20
10
No of bearing 5
Year Bearing failure
changed 0
2012 2013 2014 2015 2016
2012 9 DCP-1A/1B/1C/1D/1E
2013 9 DCP-1C/1E
2015 10 DCP-1B/1D/1E
11-Oct-2016 06-Nov-2016
Chart Title
20
15 May-16
Jul-16
Oct-16
Nov-16
Good
10
Satisfactory
0
1 2 3 4 5 6 7 8 9 10 11 12
Monthwise
48
Step-8 Develop Possible Solutions
Sr. Causes
No. Possible solutions
validated
1.1 Rusty portion of frame to be cleaned new
support plates should be welded and painted.
1.2 Base shim packing of brass material to be fitted
to avoid rusting and Deterioration
1 Pipe strain
1.3 Pipe supports fabrication to be done.
1.4 Suction and delivery pipe cutting/welding to be
done properly to Align pipe in line so that stresses
were not developed
2.1 New Coupling to be fitted
Coupling
2 2.2 Coupling Bushes to be replaced with new
Damaged
2.3 Coupling pin hole to be checked regularly in
preventive
3.1 Watermaintenance
Collecting Funnel to be fitted to avoid
Base
water spillage on base platform and foundation bolt
3 Frame
3.2 Proper housekeeping to be maintain
Deteriorate
3.3 Base frame to be painted
3.1 New Rotating Assembly to be Kept ready
4 Bent shaft 3.2 New Bearing to be fitted
3.3 Proper Alignment to be done
Impact
Sr. Cost of Time
No. Solution on Reversibility
implementation Impact
Total
quality
Suction and delivery pipe cutting/welding to
1 8 9 8 6 31
be done properly to Align pipe in line
Rusty portion of frame to be cleaned new
2 support plates should be welded and 3 9 6 9 28
painted
New coupling to be made ready with
3 9 9 9 9 36
boring the hole and keyway
New rotating assembly made ready with
4 9 9 9 9 36
new bearings
Base shim packing of brass material made
5 9 6 8 2 25
ready to avoid rust
Scale-on: 1 for weak relation, 3 for moderate relation, 9 for strong relation.
Step-8 Develop solution 50
STEP-9 FORESEE RESISTANCE AND PREPARE
51
Step-9 Foreseeing Probable 52
STEP-10 TRAIL IMPLEMENTATION
53
Step-10 TRIAL IMPLEMENTATION PLANNING
Start Due
Causes Solutions Resp person Status and Actions
Date Date
To avoid New coupling to be made ready with boring New Coupling fabricated from CRS to avoid
Shirke/Rajam 3/5/2017 10/5/2017
Misalignment the Pinhole and keyway in Central Repair Shop Delivery delay
New rotating assembly made ready with new New Rotating assembly fitted which help to
Bent shaft Shirke 5/5/2017 6/5/2017
bearings and fitted to Pump solve misalignment due to bent in shaft
DCP1C Pump Base shim packing of brass material made Base frame Shim not get rusted so
Shirke/Rajam 07/05/2017 08/05/2017
Alignment ready to avoid rust Alignment Accuracy sustain
DCP1C Pump
Due to funnel Base frame deterioration
Gland leak water collecting funnels fabricated Ashirwad/ Mane 10/5/2017 12/05/2017
avoided and Housekeeping Maintain
spillage
Suction and Discharge Pipe cutted found
To remove Pipe Suction and delivery pipe cutting to Align
Rajam/Mane 14/05/2017 14/05/2017 suction pipe Out by 3mm and Discharge out
Strain pipe in line
by 4mm
Pump Rusty portion of frame to be cleaned new
New Support plate welded to base frame for
foundation support plates should be welded and Shirke/Mane 14/05/2017 14/05/2017
Strengthening
Strengthening painted
To avoid Piping Pipe and Pump Flanges aligned parallel
Pipe and Pump Flanges alignment Shirke/Prashant 14/05/2017 14/05/2017
Strain before tightening the bolts
Patch ring Fabricated and welded to pipe
DCP1C Pump Suction and delivery pipe welding to be
Rajam/Mane 15/05/2017 15/05/2017 joint to avoid stress development in pipeline
Pipeline Strain done properly
due to welding the pipe joint.
DCP1C Pump
Alignment to be done of Pump Suction and Helps to Know the Actual deflection in two
Pipeline Shirke/Prashant 15/05/2017 15/05/2017
Discharge Pipe Pipe joint
Alignment
New fabricated Coupling with New Bushes
To avoid New coupling with New Bushes to be fitted to
Shirke/Prashant 16/05/2017 16/05/2017 fitted which helps to maintain Alignment
Misalignment Pump & Motor
Accuracy
DCP1C Pump
Final Alignment to be done of Pump & Motor Shirke/Prashant 17/05/2017 17/05/2017 final Alignment done
Alignment
10/5/2017
11/5/2017
12/5/2017
13/5/2017
14/5/2017
15/5/2017
16/5/2017
17/5/2017
3/5/2017
4/5/2017
5/5/2017
6/5/2017
7/5/2017
8/5/2017
9/5/2017
Sr
.No
Activity
Pump suction
pipe cutting
done find out Pump discharge
by pipe cutting
approximately done find out by
5mm approximately
6mm
Support Painted
Support Rusted New Support Pipe Welded
Step-10 Trial Implementation 59
PUMP ALIGNMENT DONE BEFORE AND AFTER WELDING OF PROPOSED
SOLUTION
SUCTION &DISCHAGE PIPELINE
No 4
Copper shim
fitted to base
plate for
Alignment
Copper shim
fitted to base
plate for
Alignment
To avoid gland water leakage spillage
water collecting funnels fabricated
2
a Coupling condition a Pump flow
b Coupling gap b Pump pressure
1 c Coupling Bushes condition c Motor current
d Gland follower status d Pump Noise
e Gland leak if change gland e Pump Vibration
f While gland replacement check sleeve condition Shutdown Check
g Pump/Motor foundation bolts a Pump Alignment
3
h Suction and Discharge valve operation b Pump Base Shim condition
i Flange joint bolts c Bearing Condition
64
28-Jun-2017
25
Vibration Analysis of DCP1C After QC
Vibration reading mm/sec
20
May-16
15
Jul-16
Oct-16
10 Nov-16
Good
Satisfactory
5 Jun -17
0
1 2 3 4 5 6 7 8 9 10 11 12
Readings
5
Vibration reading after QC
4.5
4
Vibration Reading in mm
3.5
2.5 Good
Satisfactory
2
Jun-17
1.5
0.5
0
1 2 3 4 5 6 7 8 9 10 11 12
Readings
Vibration Reading in mm
20
Vibration reading in mm
20 May-16
May-16 15 Jul-16
15 Jul-16 Oct-16
Oct-16 10 Nov-16
10 Nov-16 Good
Good 5 Satisfactory
5 Satisfactory Jun-17
#REF!
0
0 1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12 Readings
Readings
Vibration Reading was very High Max 10.74 mm /sec Vibration Reading is Satisfactory below Max 4.5 mm/sec
Saving
@21.5 lacs
Deming Wheel
C & E Diagram
4W-1H /5W-1H
Validity Chart
Flow Diagram
Pareto graph
Check Sheet
Graphs
Sr.
Problem solving Steps
No
1 Identification of Probem
2 Selection of Problem
3 Define the problem
4 Analyze the problem
5 Identification of causes
6 Root Cause Analysis
7 Data Analysis
8 Development of the solution
9 Foreseeing prob. Resistance
10 Trial impl/Check performance
11 Regular Implementation
12 Follow up/Review
71
Project Completion sheet
QC Circle Project Completion Sheet
Name o f the QC Circ le : Missio n
Te am Time plan
Sl. No . Name De ptt. Ro le Sl. No . Ste p Start Date End Date
1 M r. A jit S. M o kal U t ilit y F aci l i t at o r 1 D e f i ne 15.03.2017 29.03.2017
2 M r. S.D.Rajam U t ilit y Le a d e r 2 O b ser vat i o n 05.04.2017 12.04.2017
3 M .M .Shirke U t ilit y M e mb e r 3 A na l y s i s 19.04.2017 03.05.2017
4 M r. Harinrayan U t ilit y M e mb e r 4 A ct i o n 03-05-2017 17.05.2017
5 M r. A t ish B ho ir U t ilit y M e mb e r 5 C he c k 24.05.2017 31.05.2017
6 M r. A shirvad Pat il U t ilit y M e mb e r 6 S t a nd a r d i z a t i o n 28.06.2017 28.06.2017
7 M r. Prashant M o kal U t ilit y M e mb e r 7 C o nc l us i o n 28.06.2017 28.06.2017
Tre nd o f ac hie ve me nt, Be fo re A fte r graph
A c hie me nt:Id ent if y Perf o rmance o f DCP# 1 p ump s f o r Cast er d irect sp ray co o ling , f o und t hat it s
b earing f ailure and hig h vib rat io n d ue t o d et erio rat io n o f p ump s b ase f rame and p ip e st rain , So st ud y t he
vib rat io n read ing and t ake t he d ecisio n t o rep air b ase f rame and p ump shim rep lacement as well as remo ve t he
p ip e st rain, result b reakd o wn o f DCP# 1 p ump s is red uced .