Sie sind auf Seite 1von 15

Construction Planning and Scheduling

Unit 1 Contents
Basic concepts in the development of construction plan
Choice of technology & construction method
Defining work tasks
Precedence relationships among activities
Estimating activity duration
Estimating resource requirement/work
Coding systems

Prepared for the benefit of student community -


1
Srinivasan Kandaswamy
Construction planning Contd.

fundamental and challenging activity It is the necessary fore-runner to scheduling

For management and execution of construction projects


Involves,
i. choice of technology
ii. definition of work tasks
iii. estimation of the required resources
iv. estimation of durations for individual tasks
v. identification of any interactions among the different work tasks
vi. organizational decisions about the relationships between project participants
vii. which organizations (eg. sub-contractors) to include in a project.
Basis for developing the budget and the schedule for work
Result of construction = Facility design

Aspects are
i. generation of required activities
ii. analysis of the implications of activities
iii. choice among the various alternative means of performing
activities

Prepared for the benefit of student community -


2
Srinivasan Kandaswamy
Construction planning

Emphasis Unwieldy

Normative Insidious

Aspects Comprehensive

Sketchy Ad hoc

Explicit Haphazard

Forestall

Fore-runner

Exhaustive

Associate

Hierarchy Task Resource


precedence over time
Prepared for the benefit of student community -
3
Srinivasan Kandaswamy
(i) Choice of Technology and (ii) Construction Method

Critical elements to the success of a project

a) relative costs
b) Reliabilities
c) availability of equipment

Formulation of a number of construction plans


based on alternative methods or assumptions

suggested construction method / alternative construction methods

cost, time and reliability impacts of the alternative approaches

Explicit in bidding process Or by value engineering

a useful approach is to simulate the construction process

Prepared for the benefit of student community -


4
Srinivasan Kandaswamy
Defining Work Tasks a parallel step in the planning process Contd.

Work task – specific & defined items of work


Represents
i. necessary framework to permit scheduling of construction activities
ii. estimating the resources required by the individual work tasks
iii. necessary precedence or required sequence among the tasks
iv. necessary information for application of formal scheduling procedures
The time required to perform an activity is called the duration of the activity
The beginning and the end of an activity are signposts or milestones, indicating the
progress of the project
Clean concrete forms is a sub-activity
Placing concrete on site is an activity In it, there are micro-activities such as
Sub-activities associated with it are i. Transport forms from on-site storage
i. placing forms ii. unload onto the cleaning station
ii. installing reinforcing steel iii. Position forms on the cleaning station
iii. pouring concrete iv. Wash forms with water
iv. finishing the concrete v. Clean concrete debris from the forms
v. removing forms surface
vi. cleaning of forms vi. Coat the form surface with an oil release
agent for the next use
vii. Unload the form from the cleaning station
Prepared for the benefit of studentand transport
community - to the storage location 5
Srinivasan Kandaswamy
Defining Work Tasks define separate work tasks for:
activities which involve different resources
activities which do not require continuous performance
activity "prepare and check shop drawings a task for preparation
a task for checking

Eg. Road works

Prepared for the benefit of student community -


6
Srinivasan Kandaswamy
Defining Precedence Relationships Among Activities

Arrows are called as branches or links and represents a particular activity

Circles at the beginning/end of each arrow are called nodes or events and represent milestone

Example of an Impossible Work Plan


Prepared for the benefit of student community -
Srinivasan Kandaswamy 7
Precedence Relationships Contd.
Some activities have a necessary
technical or physical relationship Some "precedence relationships" are not technically
that cannot be superseded. For necessary but are imposed due to implicit decisions
example, concrete pours cannot within the construction plan. For example, two
proceed before formwork and activities may require the same piece of equipment so
reinforcement are in place. a precedence relationship might be defined between
the two to insure that they are not scheduled for the
Some activities have a necessary same time period. Which activity is scheduled first is
precedence relationship over a arbitrary. As a second example, reversing the
continuous space rather than as sequence of two activities may be technically possible
discrete work task relationships. but more expensive. In this case, the precedence
For example, formwork may be relationship is not physically necessary but only
placed in the first part of an applied to reduce costs as perceived at the time of
excavation trench even as the scheduling.
excavation equipment continues
to work further along in the Concrete might have to cure (or set) for several
trench. Formwork placement days before formwork is removed. This restriction
cannot proceed further than the on the removal of forms activity is called a lag
excavation, but the two activities between the completion of one activity (i.e.,
can be started and stopped pouring concrete in this case) and the start of
independently within this another activity (i.e., removing formwork in this
constraint. case).
Prepared for the benefit of student community -
8
Srinivasan Kandaswamy
Precedence Definition for Site Preparation and Foundation Work Contd.
A. Site clearing (of brush and minor debris) E. Excavation for utility trenches
B. Removal of trees F. Placing formwork and reinforcement for concrete
C. General excavation G. Installing sewer lines
D. Grading general area H. Installing other utilities
Precedence Relations
I. Pouring concrete
Activity Description Predecessors
A Site clearing ---
B Removal of trees ---
C General excavation A
D Grading general area A
E Excavation for utility trenches B,C
F Placing formwork and reinforcement for concrete B,C
G Installing sewer lines D,E
H Installing other utilities D,E
I Pouring concrete F,G
Predecessor Direct Successor All Successor All Predecessor
Activity Activities Activities Activities
A C,D E,F,G,H,I ---
B E,F G,H,I ---
C E,F G,H,I A
D G,H I A
E G,H I A,B,C
F I --- A,B,C
G I --- A,B,C,D,E
H --- --- A,B,C,D,E
Activity-on-branch diagram I --- --- A,B,C,D,E,F,G
All Activity Precedence Relationships
Prepared for the benefit of student community -
9
Srinivasan Kandaswamy
Precedence Relationships

Activity-on-branch diagram

Activity-on-node diagram
Prepared for the benefit of student community -
10
Srinivasan Kandaswamy
Estimating Activity Durations Contd.
Activity Predecessor Duration (Days)
Excavate trench --- 1.0
Place formwork Excavate trench 0.5
Place reinforcing Place formwork 0.5
Pour concrete Place reinforcing 1.0

Effect of learning on productivity – Learning curve


Weather effects
As a simple example, an activity might require As a crew becomes familiar with
ten days in perfect weather, but the activity an activity and the work habits of
could not proceed in the rain. Furthermore, the crew, their productivity will
suppose that rain is expected ten percent of the typically improve.
days in a particular month. In this case, the
expected activity duration is eleven days
including one expected rain day.
Prepared for the benefit of student community -
11
Srinivasan Kandaswamy
Estimating Activity Durations

Beta and Normally Distributed Activity Durations

Estimation Framework for Masonry Construction


Prepared for the benefit of student community - 12
Srinivasan Kandaswamy
Estimating Resource Requirements for Work Activities

For large concrete pours on horizontal slabs, it is important to plan the activity so that the
slab for a full block can be completed continuously in a single day.

i. Resources required for pouring the concrete depend upon the technology used.
ii. For example, a standard crew for pumping concrete to the slab might include a
foreman, five laborers, one finisher, and one equipment operator.
iii. Related equipment would be vibrators and the concrete pump.
iv. For delivering concrete with a chute directly from the delivery truck, the standard
crew might consist of a foreman, four laborers and a finisher.

The number of crews would be chosen to insure that the desired amount of concrete
could be placed in a single day.

In addition to the resources involved in the actual placement, it would also be necessary
to insure a sufficient number of delivery trucks and availability of the concrete itself

Prepared for the benefit of student community -


Srinivasan Kandaswamy 13
Coding Systems Secondary Divisions for Site Work
Major Divisions in the Uniform Construction Index
02-010 Subsurface investigation
0 Conditions of the contract 9 Finishes 02-012 Standard penetration tests
02-016 Seismic investigation
1 General requirements 10 Specialties
02-050 Demolition
2 Site work 11 Equipment 02-060 Building demolition
3 Concrete 12 Furnishings 02-070 Selective demolition
02-075 Concrete removal
4 Masonry 13 Special construction 02-080 Asbestos removal
5 Metals 14 Conveying system 02-100 Site preparation
6 Wood and plastics 15 Mechanical 02-110 Site clearing
02-115 Selective clearing
7 Thermal and moisture prevention 16 Electrical 02-120 Structure moving
8 Doors and windows 02-140 Dewatering
Seventeenth division for conditions of the contract for a constructor 02-150 Shoring and underpinning
Code: 16-950-960 – meaning Electrical Equipment Testing 02-160 Excavation supporting system
02-170 Cofferdams
The first two digits represent one of the sixteen divisions for work 02-200 Earthwork
02-210 Grading
Third digit is added to indicate a subdivision within each division 02-220 Excavating, backfilling and compaction
02-230 Base course
Extended code: 0534.02220.21.A.00.cf34 02-240 Soil stabilization
02-250 Vibro-floatation
The first four digits indicate the project for this activity 02-270 Slope protection
02-280 Soil treatment
The next five digits refer to the MASTERFORMAT secondary division 02-290 Earth dams

The digits 21 in this example might refer to excavation of column footings MASTERFORMAT
The next character refers to the block or general area on the site that the activity will take place
in this case block A
The digits 00 could be replaced by a code to indicate the responsible organization for the activity
The characters cf34 refer to the particular design element number for which this excavation is intended;
in this case, column footing number 34 is intended
Prepared for the benefit of student community -
14
Srinivasan Kandaswamy
Courtesy/Source
http://pmbook.ce.cmu.edu/

Construction Project Management


K K Chitkara
Tata McGraw-Hill Education

Prepared for the benefit of student community -


15
Srinivasan Kandaswamy

Das könnte Ihnen auch gefallen