Beruflich Dokumente
Kultur Dokumente
AT
NATIONAL SEMINAR
1
PRESENTATION ON
By
2
GOOD LEADERSHIP IS THE ART OF GETTING
EXTRA ORDINARY WORK DONE THROUGH
ORDINARY PEOPLE
3
PROJECT MANAGEMENT CONCEPT
AS PER BRITISH STANDARD BS 6079 : 1996,
PROJECT MANAGEMENT IS DEFINED AS:
DEFINED SCHEDULE,
COST AND
PERFORMANCE PARAMETERS.
4
PROJECT MANAGEMENT CONCEPT
2. MANAGEMENT
5
PROJECT MANAGEMENT CONCEPT
6
PROJECT MANAGEMENT CONCEPT
7
PROJECT MANAGEMENT CONCEPT
5. PROJECT MANAGER
THE INDIVIDUAL OR BODY WITH RESPONSIBILITY
FOR MANAGING A PROJECT TO ACHIEVE SPECIFIC
OBJECTIVES.
a) Define phase
b) Plan phase
c) Implement phase
d) Close phase
9
1. DEFINE PHASE
1 DEFINE PHASE-
If the Goal is -
S pecific
M easurable
A ttractive
R ealistic and it’s
T imeline is clear
10
PROJECT MANAGEMENT CONCEPT
11
2. PLAN PHASE
Planning -
Setting a Direction
for
a System
and then
12
2. PLAN PHASE
2 PLAN PHASE-
2.1 a) Product Break down Structure (PBD)
14
2. PLAN PHASE
15
2. PLAN PHASE
16
2. PLAN PHASE
2.6 B) NON-STATUTORY CLEARANCES
1 LAND AVAILABILITY AT PLANT AREA
6 DEFENCE CLEARANCE 17
2. PLAN PHASE
2.6 C) OTHER CLEARANCES
1 APPROVAL AS PER EXPLOSIVES ACT AND RULES
27
3. IMPLEMENTATION PHASE
3.3 PREPARE L-1 NETWORK
28
3. IMPLEMENTATION PHASE
3.9 PREPARE CONTRACT HAND BOOK :
1. ITINDEX
SHALL CONTAIN
MAP THE LOCATION
SHOWING FOLLOWINGOF–THE
PROJECT
(ROAD MAP AS WELL AS RAIL MAP)
4. MILESTONES TO BE MONITORED
33
3. IMPLEMENTATION PHASE
34
Monitoring and Control
A Management process in which -
(1) Actual performance is compared with planned
performance,
(2) Difference between the two is measured,
(3) Causes contributing to the difference are
identified, and
(4) Corrective Action is taken to eliminate or
minimize the difference
35
PREBID
COMML
INVOLVEMENT
PROCESS
MAFG
POST AWARD MAP
UNITS
RECEIVE C I S &
& ENGG
CONT DOC
CENTRES
ORGANISE
ISX KICK OFF MTG
CONSULTANT
CUSTOMER REQUIREMENT
FREEZE SCOPE,
INTERFACES, CUST
TSX
INPUTS & ESTABLISH
CONT COORDN
PROCEDURE
CUSTOMER
PREPARATION OF
ENABLING WORK SCH &
EXPEDITE
MSX
MONITOR PROGRESS,
REVIEW PROJECT /
MILESTONE (PMX-F15)
AND TAKE CORRECTIVE
C U S T O M E R SAT I S F AC T I O N
ACTIONS FOR
DEVIATION
SOX
RESOLVE CUST
COMPLAINT
CONTINUAL
IMPROVEMENT
IN PM PROCESS
CONTRACT CLOSING
36
(FORM PMX-F14)
3. IMPLEMENTATION PHASE
37
4. PROJECT LIFE CYCLE
4 CLOSURE PHASE-
38
39
40
41
42
43
44
45
46
47
48
ACTION PLAN FOR COMPLETING THE
WORK IN SPECIFIED TIME
4. RESOURCE PLANNING ON
- SITE INFRASTRUCTURE
- MAJOR TOOLS AND PLANTS
- CONSUMABLES
51
EXTENSION OF CONTRACT PERIOD
1 PREPARE GROUND FOR GETTING CONTRACT PERIOD EXTENDED
WITHOUT LEVY OF LD
1. DELAY IN ENGINEERING.
4. DELAY IN ORDERING.
53
PROJECT MANAGEMENT : PSWR : NAGPUR
55
56