TO

AT
NATIONAL SEMINAR

19th January 2012

1
PRESENTATION ON

By

Vice President - HNPCL Mumbai


19th January 2012

2
GOOD LEADERSHIP IS THE ART OF GETTING
EXTRA ORDINARY WORK DONE THROUGH
ORDINARY PEOPLE

3
PROJECT MANAGEMENT CONCEPT
AS PER BRITISH STANDARD BS 6079 : 1996,
PROJECT MANAGEMENT IS DEFINED AS:

1. PROJECT (CLAUSE NO. 1.3.6)

A UNIQUE SET OF COORDINATED ACTIVITIES,

WITH DEFINITE STARTING AND FINISHING POINTS

UNDERTAKEN BY AN INDIVIDUAL OR ORGANIZATION

TO MEET SPECIFIC OBJECTIVES WITHIN

DEFINED SCHEDULE,

COST AND

PERFORMANCE PARAMETERS.
4
PROJECT MANAGEMENT CONCEPT

2. MANAGEMENT

PLANNING, MONITORING AND CONTROL


OF
THE FUNCTIONS SUPPORTING

THE COMPLETE CYCLE (FLOW) OF ACTIVITIES,


AND
THE ASSOCIATED FLOW OF INFORMATION..

5
PROJECT MANAGEMENT CONCEPT

3. PROJECT MANAGEMENT (CLAUSE 1.3.9)

PLANNING, MONITORING AND CONTROL OF ALL


ASPECTS OF A PROJECT AND THE MOTIVATION OF
ALL THOSE INVOLVED IN IT TO ACHIEVE THE
PROJECT OBJECTIVES ON TIME AND TO THE
SPECIFIED COST, QUALITY AND PERFORMANCE.

6
PROJECT MANAGEMENT CONCEPT

4. PROJECT MANAGEMENT ACTIVITY (PMA)


(CLAUSE 1.3.9)

AN OPERATION, WITHIN A WORK PACKAGE OF A


WORK BREAKDOWN STRUCTURE, THAT IS A SPECIFIC
ACTION TO BE COMPLETED TO AID THE FULFILLMENT OF
THE PROJECT AS A WHOLE.

5. PROJECT MANAGER (CLAUSE 1.3.10)


THE INDIVIDUAL OR BODY WITH RESPONSIBILITY
FOR MANAGING A PROJECT TO ACHIEVE SPECIFIC
OBJECTIVES.

7
PROJECT MANAGEMENT CONCEPT

5. PROJECT MANAGER
THE INDIVIDUAL OR BODY WITH RESPONSIBILITY
FOR MANAGING A PROJECT TO ACHIEVE SPECIFIC
OBJECTIVES.

IT CAN BE ELABORATED AS THE INDIVIDUAL OR BODY


WITH THE RESPONSIBILITY FOR MANAGING A
CONTRACTED PROJECT BY CO ORDINATING PROJECT
MANAGEMENT FUNCTIONS AMONG CUSTOMER,
CONSULTANT, SUPPLIERS, AND PROJECT SITE IN THE
FIELD OF ENGINEERING, MANUFACTURING, SUPPLIES,
ETC FROM CONCEPT TO COMPLETION OF THE PROJECT
IN LINE WITH THE CONTRACT AGREEMENT.
8
PROJECT MANAGEMENT CONCEPT

6. PROJECT LIFE CYCLE (CLAUSE 1.3.8)

THE SEQUENTIAL PHASES THROUGH WHICH A


PROJECT PASSES TO REACH ITS OBJECTIVES.

a) Define phase
b) Plan phase
c) Implement phase
d) Close phase

9
1. DEFINE PHASE

1 DEFINE PHASE-

a) Project strategy – Project (Goal) is defined

If the Goal is -

S pecific
M easurable
A ttractive
R ealistic and it’s
T imeline is clear

then it is a SMART Goal

10
PROJECT MANAGEMENT CONCEPT

SUCCESS IS BEST ACHIEVED WHEN WE


ARE CLEAR ABOUT THE GOAL AND
FLEXIBLE ABOUT THE PROCESS OF
GETTING THERE

11
2. PLAN PHASE

Planning -

Setting a Direction
for

a System
and then

Guiding the systems to follow the Direction

12
2. PLAN PHASE
2 PLAN PHASE-
2.1 a) Product Break down Structure (PBD)

- Decide the Packages / Sub packages


- Group them according to strategy
- Define the scope clearly and award the job

b) Work Break down Structure (WBD)

- Estimate all the works to be done in order to


create the packages / sub packages
- Estimate the duration for each work
- Make mile stone schedule
- Make L-1 schedule
13
2. PLAN PHASE
2.2 PLAN INFRASTRUCTURAL PACKAGES

2.3 IDENTIFY UNREALISTIC DEAD LINE IF POSSIBLE


REMOVE THEM OR HAVE ALTERNATE PLAN TO
NULLIFY THEIR EFFECT.

2.4 PLAN TAKING INTO ACCOUNT FESTIVALS, HOLIDAYS,


SEASONAL EFFECTS

2.5 IDENTIFY MAJOR MILESTONES TO BE ACHIEVED

2.6 IDENTIFY STATUTORY AND NON STATUTORY


CLEARANCES

14
2. PLAN PHASE

POOR PLANNING DOCUMENTS ARE ONE


IMPORTANT REASON FOR BAD PROJECT
RESULTS IN TERMS OF ADDITIONAL,
UNPLANNED WORK, TIME DELAY AND COST
OVER RUN

15
2. PLAN PHASE

2.6 A) STATUTORY CLEARANCES

1. POLLUTION CLEARANCE WATER GOI / GOS


AND AIR

2. PROJECT IMPORT REGISTRATION MOP, GOI

3 ENVIRONMENTAL CLEARANCE MOEF, GOI

4 AVIATION CLEARANCE AAI, GOI

16
2. PLAN PHASE
2.6 B) NON-STATUTORY CLEARANCES
1 LAND AVAILABILITY AT PLANT AREA

2 FOR TRANSPORTATION OF COAL

3 TRANSPORTATION OF FUEL (SECONDARY FUEL)

4 REAL ESTATE RIGHTS & RIGHT TO ACCESS


AND USE OF SITE, INCLUDING RIGHT OF WAY
FOR ALL CORRIDORS TO THE FACILITY FROM
NEAREST STATE HIGHWAY, R&R

5 MEGA POWER PROJECT STATUS

6 DEFENCE CLEARANCE 17
2. PLAN PHASE
2.6 C) OTHER CLEARANCES
1 APPROVAL AS PER EXPLOSIVES ACT AND RULES

2 APPROVAL AND REGISTRATION OF STEAM


GENERATOR AS PER INDIAN BOILER REGULATION

3 APPROVAL AS PER INDIAN ELECTRICITY ACT


AND RULES FOR ELECTRICAL INSTALLATION

4 APPROVAL AS PER INDIAN PETROLEUM ACT AND


PETROLEUM RULES FOR STORAGE AND
TRANSPORT OF PETROLEUM PRODUCTS

5 APPROVAL AS PER GAS CYLINDER RULES AND


HANDLING AND TRANSPORT OF COMPRESSED
GASES 18
2. PLAN PHASE
2.6 C) OTHER CLEARANCES
6 A) COLLECTION, STORAGE AND DISPOSAL OF WASTE
B) SITE CLEARANCES, SAFE REPORT AND SAFETY
AUDIT

7CONFIRMATION OF COLLECTOR / DIRECTORATE OF


TOWN AND PLANNING FOR THE USE OF THE SITE FOR

THE CONSTRUCTION AND OPERATION OF THE POWER


STATION AND FUEL FACILITY

8 CONSENT OF RELEVANT PANCHAYAT FOR THE


DEVELOPMENT OF PROJECT SITE AND THE
TOWNSHIP SITE

•APPROVAL OF CHIEF INSPECTOR OF FACTORIES OF


19
THE PROPOSED DESIGN AND CONSTRUCTION OF
2. PLAN PHASE
2.6 C) OTHER CLEARANCES
10 ALLOCATION / APPROVAL OF ELECTRIC
SUPPLY FOR BULK CONSTRUCTION POWER

11 NO OBJECTION CERTIFICATE REGARDING AIR &


FUGITIVE EMISSIONS

12 NO OBJECTION CERTIFICATE FOR PLANT LAYOUT


WITH REGARD TO ELECTRICAL EQUIPMENT,
OPERATIONAL SAFETY

13 NO OBJECTION CERTIFICATE FOR STORAGE OF


CONSTRUCTION MATERIALS, ETC. TILL COD OF
THE PROJECT

14 NO OBJECTION CERTIFICATE FOR STORAGE OF


CONSTRUCTION MATERIAL, FUEL OILS AND
CHEMICALS, ETC. IN THE SCOPE OF THE 20
CONTRACTOR, TILL COD OF THE PROJECT
2. PLAN PHASE
2.6 C) OTHER CLEARANCES
15 NOC FOR STORAGE OF DISTILLATE OIL

16 LOCAL APPROVAL FOR OPERATING THE PLANT

17 LOCAL APPROVAL OF ARCHITECTURAL PLANS


FOR TOWNSHIP

18 CLEARANCE FOR LIFTS

19 APPROVALS / CLEARANCES FOR LABOUR / MAN


POWER LIKE LICENSE FROM LABOUR
COMMISSIONER FOR CONSTRUCTION LABOUR,
REGISTRATION OF WORKERS

20 EXPORT AUTHORISATION (EXPORT LICENSE)

21 CLEARANCE FOR EOT CRANE / OTHER BUILDING


21
CRANES
3. IMPLEMENTATION PHASE

3.1. KICK-OFF MEETINGS-

KICK-OFF MEETING IS THE BEGINNING OF


IMPLEMETATION PHASE.

3.2 A TYPICAL AGENDA FOR KICK-OFF MEETING –

1 Detail scope of works


2 Identification of packages and detail
of respective LOIs
3 List of terminal points of contract
4 List of exclusions in the contract
5 Proposed date of signing of
contract.
22
6 Allocation of works for various mfg
3. IMPLEMENTATION PHASE
3.2 TYPICAL AGENDA FOR KICK-OFF MEETING CONTD….
7 Detail of co ordinators for all the agencies
concerned with postal addresses, contact
persons area wise, phone numbers, fax
number, e-mail address, mobile number etc
8 Contract coordination procedure with
Customer, Consultant, inter units etc.
9 Document numbering and trasmittal
modalities.
10 Data for preparation of L1 / L2 networks
11 List of drawings to be approved by customer
for all the packages. Schedule of submission
and approvals with dates.
12 List of Quality plans to be approved by
customer for all the packages. Schedule of
submission and approvals with dates.
23
3. IMPLEMENTATION PHASE
3.2 TYPICAL AGENDA FOR KICK-OFF MEETING CONTD….
13 List of Sub vendors to be approved by
customer for all the packages. Schedule of
submission and approvals with dates.
14 Nomenculature of auxiliaries like fans, mills ,
pumps etc. ( Numbering from left to right or
from right to left )
15 List of mandatory spares to be supplied
under each package and unitwise allocation
of the same.
16 List of special tools and tackles to be
supplied for each package and unitwise
allocation of the same.
17 List of commissioning spares to be supplied
for each package.
18 List of recommended spares if any
24
3. IMPLEMENTATION PHASE
3.2 TYPICAL AGENDA FOR KICK-OFF MEETING CONTD….

19 List of customer inputs with schedule dates


20 Clarity on Guarantee data schedule.
21 Detail regarding applicability of Liquidated
damages clause.
22 Detail regarding Insurance coverage for
transportation, storage, E&C
23 Clarity on Zero date of contract
24 Clarity on mode of material despatches
25 Address of the customer for despatching the
materials, Name of the Rly siding, List of
transporters available and their addresses
with contact person and phone numbers
26 Project schedule milestone wise.
25
26
3. IMPLEMENTATION PHASE
3.2 TYPICAL AGENDA FOR KICK-OFF MEETING CONTD….

27 Clarity regarding commissioning, trial


operation, final acceptance, defect liability
period etc.
28 Clarity on scope of consumables to be
supplied during and after commissioning.
29 Clarity on taxes and duties
30 Clarity on Terms of payment
31 Site office/ space requirement.
32 Requirement of construction power and
construction water

27
3. IMPLEMENTATION PHASE
3.3 PREPARE L-1 NETWORK

3.4 GET L-2 NETWORK DULY MATCHED WITH L-1

3.5 FINALISE ENGINEERING INFORMATION FLOW


SCHEDULE AND DISTRIBUTE TO CONCERNED

3.6 FINALISE QUALITY PLAN / FIELD QUALITY PLAN


SCHEDULE AND DISTRIBUTE TO CONCERNED.

3.7 FINALISE BROAD BILLING BREAKUP IN LINE WITH


LOA

3.8 FINALISE BILLING BREAK UP FOR INDIVIDUAL UNITS

28
3. IMPLEMENTATION PHASE
3.9 PREPARE CONTRACT HAND BOOK :
1. ITINDEX
SHALL CONTAIN
MAP THE LOCATION
SHOWING FOLLOWINGOF–THE
PROJECT
(ROAD MAP AS WELL AS RAIL MAP)

2. PROJECT INFORMATION – POSTAL ADDRESS,


CONTACT POINTS OF CUSTOMER,
CONSULTANTS,
SITE, FOR TECHNICAL AND FINANCIAL
MATTERS

3. ALLOCATION OF SUPPLIES & SERVICES.

4. MILESTONES TO BE MONITORED

5. LIST OF MAJOR INPUTS FROM CUSTOMER

6. CONTRACT CO-ORDINATION PROCEDURE. 29


30
31
3. IMPLEMENTATION PHASE
3.9 CONTRACT HAND BOOK CONTD…..
7. CORRESPONDENCE/DOCUMENT
TRANSMITTAL PROCEDURE.

8. EXTRACT OF SALIENT TERMS &


CONDITIONS OF CONTRACT.

9. LIST OF SPARES TO BE SUPPLIED.

10. TRIAL OPERATION DETAILS AS PER


CONTRACT.

11. GUARANTEED PARAMETERS FOR PG


TEST.

12. TESTS TO BE CARRIED OUT

13. LD / PENALTY / BONUS DETAILS


32
3. IMPLEMENTATION PHASE
3.9 CONTRACT HAND BOOK CONTD…..

14. LIST OF EXCLUSIONS

15. STATUTORY APPROVAL DETAIL

16. L-1 NETWORK

17. FACILITIES TO BE PROVIDED BY


CUSTOMER

18. CONSIGNEE ADDRESS

19. INDEX OF TENDER / OFFER DOCUMENTS

20. LIST OF TERMINAL POINTS

33
3. IMPLEMENTATION PHASE

3.10 REVIEW PROGRESS ON INFRASTURE, EXPEDITE AND


FOLLOW UP ENABLING WORKS

3.11 EXPEDITE SUPPLY OF ERECTION DRAWINGS


QUALITY PLANS TO SITE

3.12 EXPEDITE MATERIAL SUPPLY TO SITE

3.13 MAKE A ROLING PLAN OF 3 MONTHS MATERIAL


REQUIREMENT.

3.14 ORGANISE MONTHLY REVIEW MEETING TO MONITOR


AND CONTROL PROGRESS AS PER L-2 SCHEDULE

34
Monitoring and Control
A Management process in which -
(1) Actual performance is compared with planned
performance,
(2) Difference between the two is measured,
(3) Causes contributing to the difference are
identified, and
(4) Corrective Action is taken to eliminate or
minimize the difference

35
PREBID
COMML
INVOLVEMENT
PROCESS
MAFG
POST AWARD MAP
UNITS
RECEIVE C I S &
& ENGG
CONT DOC
CENTRES

ORGANISE
ISX KICK OFF MTG
CONSULTANT
CUSTOMER REQUIREMENT

FREEZE SCOPE,
INTERFACES, CUST
TSX
INPUTS & ESTABLISH
CONT COORDN
PROCEDURE
CUSTOMER

PUR PREPARATION OF L-1


SCH & CHB . RECEIVE L-
2s AND WITH L-1

PREPARATION OF
ENABLING WORK SCH &
EXPEDITE
MSX

COORDN FOR ENGG, QP


APPRL, VENDOR APPRL,
PROCUREMENT,
TESTING, X-PORTN OF
CRITICAL PKGS
QLY

MONITOR PROGRESS,
REVIEW PROJECT /
MILESTONE (PMX-F15)
AND TAKE CORRECTIVE

C U S T O M E R SAT I S F AC T I O N
ACTIONS FOR
DEVIATION
SOX

RESOLVE CUST
COMPLAINT
CONTINUAL
IMPROVEMENT
IN PM PROCESS
CONTRACT CLOSING
36
(FORM PMX-F14)
3. IMPLEMENTATION PHASE

3.15 PREPARE PHYSICAL AND FINANCIAL TURN OVER


FOR THE ENTIRE CONTRACT PERIOD AND MONITOR
THE SAME

3.11 PLAN, MONITOR AND CONTROL OF


INFRASTRUCTURE AND ENABLING WORKS.

37
4. PROJECT LIFE CYCLE

4 CLOSURE PHASE-

a) Finalise documentation “As build” / “As


done”

b) Collect and evaluate all lessons learnt.


Data Banking
It will be useful for next project

c) Close the project officially

38
39
40
41
42
43
44
45
46
47
48
ACTION PLAN FOR COMPLETING THE
WORK IN SPECIFIED TIME

USE OF INTEGRATED PROJECT MGMT. SYSTEM

1. PROJECT MANAGEMENT FROM


CONCEPT TO COMMISSIONING.
2. USE OF LEVEL 1, LEVEL 2 AND LEVEL 3
NETWORKS FOR MANUFACTURING,
ERECTION & COMMISSIONING.
3. EXPEDITING INTERFACE
REQUIREMENTS FOR CUSTOMER’S
SCOPE OF WORKS.
49
ACTION PLAN FOR COMPLETING THE
WORK IN SPECIFIED TIME

4. RESOURCE PLANNING ON
- SITE INFRASTRUCTURE
- MAJOR TOOLS AND PLANTS
- CONSUMABLES

5. EXPEDITING FEEZING OF DRWINGS,


DOCUMENTS & MANUALS.
6. MONITORING & EXPEDITING BOUGHT
OUT ITEMS.
7. MONITORING AND CONTROLLING
PROGRAMMES.
50
ACTION PLAN FOR COMPLETING THE
WORK IN SPECIFIED TIME

8. CONSTRUCTION PLANNING AT SITE.


9. WORKING OUT PROPER SEQUENCES OF
ERECTION
10. MANAGEMENT INTERVENTION &
FOLLOW UP
11. WORKING ON PARALLEL ACTIVITIES.

51
EXTENSION OF CONTRACT PERIOD
1 PREPARE GROUND FOR GETTING CONTRACT PERIOD EXTENDED
WITHOUT LEVY OF LD

2 REASONS FOR DELAY BY CUSTOMER, CONSULTANTS AND


MANUFACTURING UNITS TO BE RECORDED WITH DOC. EVIDENCE
3 REASONS FOR DELAY BEYOND CONTROL OF CONTRACTOR OR
OWNER TO BE RECORDED WITH DOCUMENTARY EVIDENCE LIKE –
A. NATURAL CALAMITY – FLOOD, DROUGHT, EARTHQUAKES,
EPIDAMICS, CYCLONE, HURRICANE, NUCLEAR DISASTER ETC
B. ACTS OF ANY GOVT. DOMESTIC OR FOREIGN – DECLARED
OR UNDECLARED WAR, EMBARGOES ETC
C. REBELLION, REVOLUTION, USURPATION OF CIVIL OR MILITARY
GOVT. CONSPIRACY AND TERRORIST ACTS
D. FAILURE OF ANY LOCAL, STATE OR NATIONAL GOVT
AUTHORITY IN PROTECTING THE PROJECT
4 ANY ACTION BY CUSTOMER OR CONSULTANTS WHICH RESULTED
IN ANY INCREASE IN COST TO BE RECORDED WITH DOC. EVIDENCE
TO GET COMPENSATION 52
PROJECT MANAGEMENT : PSWR : NAGPUR

STATISTICAL ANALYSIS SHOWS DELAY IN CONTRACT CLOSING


IS DUE TO THE FOLLOWING WHICH NEEDS TO BE ADDRESSED :

1. DELAY IN ENGINEERING.

2. DELAY IN ENGINEERING AND APPROVALS OF


DRAWINGS FOR B.O.Is.

3. DELAY DUE TO LATE RESOLUTION OF ENGINEERING


INTERFACES BETWEEN UNIT TO UNIT, UNIT TO VENDOR
AND DIFFERENT PRODUCT GROUPS.

4. DELAY IN ORDERING.

5. DELAY IN PIPING ENGINEERING.

53
PROJECT MANAGEMENT : PSWR : NAGPUR

STATISTICAL ANALYSIS SHOWS DELAY IN CONTRACT CLOSING


IS DUE TO THE FOLLOWING WHICH NEEDS TO BE ADDRESSED :

6. DELAY IN PREPARATION OF CABLE SCHEDULE


AND
TERMINATION DETAILS.
7. DELAY IN APPROVAL OF VENDOR DRGS & DATA
SHEETS.
8. DELAY IN INSPECTION.

9. EXTRAORDINARY DELAY IN RETIREMENT OF


DOCUMENTS FOR BOIs

10. DELAY IN COMPLETION OF TRIAL OPERATION

11. DELAY IN CONDUCTING PG TEST.

12. DELAY IN SUBMISSION OF TIME EXTENSION


CASE. 54
PROJECT MANAGEMENT : PSWR : NAGPUR

STATISTICAL ANALYSIS SHOWS DELAY IN CONTRACT CLOSING


IS DUE TO THE FOLLOWING WHICH NEEDS TO BE ADDRESSED :

13. DELAY IN RECONCILIATION OF MAIN SUPPLIES.

14. DELAY IN HANDING OVER OF INITIAL SPARES TO


CUSTOMER AND RECONCILIATION THEREOF.

15. DELAY IN HANDING OVER OF SPECIAL TOOLS & TACKLES

16. DELAY IN SUBMISSION OF DRAWINGS , DOCUMENTS


O&M MANUALS AND AS BUILT DRAWINGS.

17. DELAY IN LIQUIDATION OF PENDING POINTS.

18. DELAY IN COMPLETION OF STATUTORY REQUIREMENTS.

55
56