Schedule Design:
The Sequel
Next Assignment:
HW: (HW 3) See Assignment Link
required input for each of the workstations
equipment necessary for each machine
steady state cycle time for each machine
ideal machine assignment for each machine
compute the idle time
unit cost at each workstation
total cost per good unit
square footage for each workstation and the total space required
SQ
F
where: EHR
S is the standard time to perform the operation, per unit
Q is the quota of output units per shift
E is the efficiency of production on the machine, expressed as a
percentage of the standard operation time
H is the hours available for production on the machine during
the shift (or whatever unit of time matches parameter S)
R is the availability (reliability*) of the machine, expressed as %
of the “up time” that the machine is available to work (%H)
Maintainability (serviceability) is a
measure of how long it takes to return
the system to proper operation:
Sum of the times required to:
diagnose the problem
obtain repair parts / tools
repair the failed components
return the unit to operating conditions
MTTR (Mean Time To Repair)
3/12/2018 IENG 471 Facilities Planning 7
Availability
% Availability = MTTF
MTTF + MTTR