Beruflich Dokumente
Kultur Dokumente
Architecture
Lecture based on Chap 6 “Distribution Automation
Equipment” of Textbook by Ekanayake
DISTRIBUTION AUTOMATION EQUIPMENT
(CHAPTER NO: 6)
• Power Delivery Steps
6.1 INTRODUCTION (Generation, Transmission
and Distribution).
Power Transmission and Distribution
• Operation of the generation
and transmission systems is
monitored and controlled by
Supervisory Control and Data
Acquisition(SCADA) systems.
Circuit breakers
Power
Generation Customers
▪ These link the various elements through communication networks (for example, microwave and fiber optic circuits) and
connect the transmission substations and generators to a manned control center that maintains system security and
facilitates integrated operation.
Central Control
Generation
▪ In larger power systems, regional control centres serve an area, with communication links to adjacent area control centres. and
Transmission
▪ In addition to this central control, all the generators use automatic local governor and excitation control.
Local Control
▪ Local controllers are also used in some transmission circuits for voltage control and power flow control, for example, using
phase shifters (sometimes known as quadrature boosters).
▪ Local automation functions are used such as on-load tap changers and shunt capacitors for voltage control and circuit
breakers or auto-reclosers for fault management. Distribution
▪ The connection and management of distributed generation are accelerating the shift from passive to active management of
the distribution network due to connection of distributed generators.
▪ Without active management of the network, the costs of connection of distributed generation
will rise and the connection of additional distributed generation may be limited
▪ The connection of large intermittent energy sources and plug-in electric vehicles will lead to
an increase in the use of Demand-Side Integration and distribution system automation.
Old Substation
▪ The name Intelligent Electronic Device (IED) describes a range of devices that perform one or
more of functions of protection, measurement, fault recording and control.
▪ An IED consists of a signal processing unit, a microprocessor with input and output devices, and
a communication interface. Communication interfaces such as EIA 232/EIA 483, Ethernet,
Modbus and DNP3 are available in many IEDs.
▪ Various Devices include:
▪ Relay IED
▪ Meter IED
▪ Recording IED
A typical meter IED measures voltage, current, power, power factor, energy over a period, maximum
demand, maximum and minimum values, total harmonic distortion and harmonic components.
Continuous event recording up to a resolution of 1 ms is available in some IEDs. These records are
sometimes interrogated by an expert to analyze a past event. This fault recorder records the pre-fault
and fault values for currents and voltages. The disturbance records are used to understand the system
behaviour and performance of related primary and secondary equipment during and after a disturbance.
The distribution SCADA system acquires data (measurements and states) of the distribution network
from Remote Terminal Units (RTU).
This data is received by an RTU situated in the substation (referred to here as the station RTU), from the
remote terminal units situated in other parts of the distribution network (referred to here as the field RTU).
The field RTUs act as the interface between the sensors in the field and the station RTU. The main
functions of the field RTU are to: monitor both the analogue and digital sensor signals (measurements)
and actuator signals (status), and convert the analogue signals coming from the sensors and actuators
into digital form. The station RTU acquires the data from the field RTUs at a predefined interval by
polling. However, any status changes are reported by the field RTUs whenever they occur.
Modern RTUs, which are microprocessor-based, are capable of performing control functions in addition
to data processing and communication. The software stored in the microprocessor sets the monitoring
parameters and sample time; executes control laws; sends the control actions to final circuits; sets off
calling alarms and assists communications functions. Some modern RTUs have the capability to time-
stamp events down to a millisecond resolution.
Transmission systems use fast-acting protection and circuit breakers to clear faults within around 100 ms. In
contrast, the time-graded over-current protection of distribution circuits and their slower CBs only clear faults
more slowly, typically taking up to 500 ms.
Short-circuit faults are inevitable in any distribution system and so interruption in function of sensitive load
equipment can only be avoided by doing the following:
Ensuring the load equipment is robust against these transient voltage changes
Adding equipment to mitigate the voltage depressions for example, a Dynamic Voltage Restorer
(DVR)
R
R2
▪ Temporary ▪ Permanent
faults faults
80% 20%
100%
Time
100%
Time
100%
Time
100%
Time
100%
Time
2 mn
Dr. Kashif Imran 6/7/18
Temporary Fault: Two Reclosers
R1
R2
R1
Network A- 50% R2 Network B- 50%
Network B
Time
Dr. Kashif Imran 6/7/18
Permanent Faults
100%
5H – 6H
100% 95%
5H – 6H
Put several
communicating FPIs in
strategic locations
T T
R
T
T
Communicating FPI
S3
S4 S3 1 S2
R 1 1 S2
S1
S3
S4 S3 2 S2
R
2 2 S2
S1
S3
S4 S3 2 S2
R 2 2 S2
S1
2’
Dr. Kashif Imran 6/7/18
Case 5: Recloser and Sectionalizer Load Break
Switches
Permanent fault
S3
S4 S3 S2
R S2
S1
95%
75%
2’ 60’
Dr. Kashif Imran 6/7/18
Overhea Summary of Over-head Networks 1/2
Permanent fault
95%
Case 1
A recloser
6h
95%
Case 2
A recloser
+ FPIs
3h
95%
Case 3
A recloser
+ FPI with Com
1h30
95%
Case 4: A recloser,
70
remote controlled switches %
and FPI with Com
10’ 1h
95%
Case 5
75
A recloser %
and sectionalizers
2’ 1h
▪ Whenever there is a fault on a part of the distribution network, the fault current should be
interrupted rapidly, the faulted section isolated from the healthy network and, then once the
fault has been removed, supplies to customers should be restored. This is achieved through
range of equipment generally known as switchgear.
▪ The protection and metering equipment of substation switchgear is housed inside the
substation control room.
Sectionalizer
When the recloser opens, a self-powered control circuit in the sectionaliser increments its
counter. The recloser is reclosed after a short delay to see whether the fault is temporary. If
the fault is temporary and cleared by the recloser, the sectionaliser resets its counter and
comes back to its normal state.
However, if the fault is permanent, when the number of counts in the sectionaliser reaches a
pre-defined number, it opens and isolates the downstream section of circuit. If the fault is
downstream of the sectionaliser, the recloser then restores supply to the upstream section.
This minimises the number of consumers affected by a permanent fault, and a more precise
indication of the fault location is provided.
When there is a fault on the network at the location shown, the over-current protection element in IED1 detects the fault and
opens CB1. This will result in an outage at loads L1 to L5. Since there are no automated components in the network, supply
restoration for a part of the network requires the intervention of a restoration crew and in some areas may take up to 80
minutes.
Supply restoration is normally initiated by phone calls from one or more customers (in the area where outage occurred)
reporting a loss of supply to the electricity supplier. Upon receiving these calls a restoration crew is dispatched to the area. It
will take some time for the team to locate the fault and manually isolate it by opening SD3 and SD4.
The normally open point (NOP) is closed to restore the supply to L5. Load L4 will be without supply until the fault is repaired.
A simple method to reduce the restoration time of loads L1, L2, L3 and L4 is using a pole-mounted recloser and sectionaliser .
When a fault occurs, the recloser trips. Upon detecting the interruption, the sectionaliser, S, increments its counter by 1.
After a short time delay, the recloser closes and if the fault persists, it will trip again. The counter of S increments again and it is
then opened. The recloser then closes successfully.
The operation of the sectionaliser facilitates restoration of supply to L1, L2, L3 and L4 within a couple of minutes. However, the
restoration of supply to L5 requires the intervention of the crew. As this method does not need any communication
infrastructure, it is reliable and relatively inexpensive.
Send a command to
RTU1 to reclose R1. If
Finally, send a
the fault current
command to RTU4 to
prevails, initiate a trip
close R4. As the fault
but as there is no fault
Then send a current flows, a trip
current, R1 remains
Send a command to command to RTU9 to command is initiated
closed. Similarly send
IED1 to close CB1 close the normally for R4. R3 and R4
commands to RTU2, 3
open point. thus isolate the fault
and 4 to reclose R2,
and supply is restored
R3 and R4. When R3
to loads L1, L2, L3
is closed, fault current
and L5.
flows, thus causing R3
to trip and lock-out.
Distribution circuits are subject to voltage variations due to the continuous changes of the network load.
The voltage variations may become severe when distributed generators are connected under light load
conditions, the power flow may be reversed.
Sustained voltages above 10 per cent or below−10 per cent of the nominal voltage may damage or may
prevent normal operation of IT equipment. As many consumers (domestic, industrial and commercial) are
now heavily dependent on this equipment, regulating the voltage within the national limits is very important.
Traditionally, an automatic tap changer and Automatic Voltage Control (AVC) relay, sometimes with line
drop compensation , is used on the HV/MV transformers to maintain the voltages on distribution circuits
within limits. These transformers whose output voltage can be tapped while passing load current are
referred to as having On-Load Tap Changers (OLTCs).
The operation of the OLTC is achieved by operating a tap selector in coordination with a diverter switch
as shown in Figure 6.30 a, b, c ( in upcoming slide)
Automatic OLTC
In automatic arrangements (with a motorized tap changer), an AVC relay is introduced to maintain the MV bus bar
voltage within an upper and lower bounds (a set value ± a tolerance).
The main purpose of introducing a tolerance is to prevent the continuous tapping up and down (hunting effect). A
time-delay relay is also usually employed to prevent tap changing due to short-term voltage variations. In modern
automatic on-load tap changers, the AVC software and time-delay relay are in a bay controller as shown in Figure
6.31.
In the USA, pole-mounted capacitor banks are used in distribution circuits for voltage regulation. They provide
power factor correction closer to load, improve voltage stability, increase the line power, flows are lower and
reduce network losses.
Modern pole-mounted variable capacitors come with current- and voltage sensing devices, data logging facility
and local intelligence.
Variable capacitors are essentially a number of switched capacitors where the number of capacitors that are
switched in is determined by an intelligent controller fixed to the pole.
The location of the capacitor bank that provides reactive power and its value of reactive power support are
critical to achieve the optimum voltage profile while minimizing network losses and maximizing line flows. In
some cases coordinated control of the OLTC transformer, pole-mounted capacitors and any distributed
generators in the network may provide enhanced optimization of different parameters.