TUTORIAL 2
PROCUREMENT METHODS
Six weeks before Chinese New Year, a fire occurs in the booking hall at KLIA2.
The airport authority is heading towards one of the busiest times of the year and
could suffer a loss of profit, somewhere in the order of RM 500,000 per day if facilities
TIME
• Shortage of time, cannot meet the holiday demand
profit loss will occur.
• Management contractor commence work before
overall design is completed, shorter development
time.
QUALITY
• Specialist for each subcontractor (airport building
structure different)
FLEXIBILITY
• Greater owner flexibility.
MANAGEMENT CONTRACTING
TIME
DESIGN
DEVELOPER
CONSULTANT
TEAM
MANAGEMENT
CONTRACTOR
WORK
PACKAGES
CONTRACTORS
ADVANTAGES
completion
design
RISK
? ?
?
Teamwork of client, Cost uncertainty
consultant team
There must be trust and good until the final account of the last
contracting procurement to be
successful
SCENARIO C – State Government Community
Project
Time
• Time is not the most concern factor in public project
• Exp: Completion deadline is unlikely to be a primary requirement.
• Main objective is towards public accountability
Quality Level
• Community project for social care is more emphasize on
quality
• Funded by government
• Functionality quality of the completed project is important
to the government
Factors that need to be considered
Cost certainty
• Cost is an important aspect for government project
• Minimum risk should be prioritised by getting a certainty in price
• Ensure client can control their financial budget (RM 250 million)
Another advantages:
• Controllable variation
• Can obtain the best price through competitive tendering
• Procedures well known
Negative aspects:
million)
Key Points
million)
DEVELOPER
1. Develop &
Construct CLIENT’S
2. Package Deal CONSULTANT TEAM
DESIGN &
BUILD
CONTRACTO
R
million)
TENDER PERIOD DURATION OF PROJECT PARTIES INVOLVED BUILDING DESIGN