Beruflich Dokumente
Kultur Dokumente
8-2
Common Sources of Project Cost
Labor
Materials
Subcontractors
Travel
…
8-3
Types of Costs
8-4
Developing direct labor cost
Total direct labor cost =
= (hourly rate) x (hours needed) x (overhead charge) x (personal time)
8-5
Cost Classifications
Non-recurring
Expedited
Recurring
Variable
Normal
Indirect
Direct
Fixed
Costs
Direct Labor X X X X
Building Lease X X X X
Expedite X X X X
Material X X X X
8-6
Cost estimation
• Clear definition of project costs at the beginning
decreases the possibility of estimation errors.
• With greater initial accuracy the likelihood of
completing within budget estimates is greater.
8-7
Cost Estimation Methods
8-8
Learning Curves
Learning curve theory states that as the quantity
of items produced doubles, costs decrease at a
predictable rate. The unit curve:
Yx aX b
Where :
Yx = time required for the x unit of output
a = time required for the initial unit of output
X = the number of units to be produced
b = learning curve slope = log(learning %)/log(2)
8-9
Problems with Cost Estimation
Lack of definition
Specification changes
External factors
8-10
Budgeting
8-11
Creating a Project Budget
Statement
of WBS The budget is a plan
Work that identifies the
resources, goals and
Project
schedule that allows
Plan
a firm to achieve
Scheduling Budgeting those goals
8-12
Activity-Based Costing
Projects use activities & activities use resources
8-13
Budget Contingencies
The allocation of extra funds to cover
uncertainties and improve the chance of
finishing on time.
Cost variance
negative zero
Schedule
variance
ACWP
Progress report
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6
A 18 60% 8 87% 4 100%
B 16 53% 10 87% 4 100%
C 14 47% 10 80% 0 80% 0 80%
D 12 40% 6 60% 6 80%
E 16 53% 8 80%
F 12 40%
G
H
I
J
BCWS 15000 30000 45000 60000 75000 90000
BCWP 9000 21000 35100 48000 59000 72000
ACWP 10200 22800 37000 50400 62800 75600
Calculate the variances for day 6
Schedule variance in cost terms = BCWP – BCWS
72000 – 90000 = -18000
8-38