Beruflich Dokumente
Kultur Dokumente
Implement Evaluate
changes performance
6 4
Redesign Process
(Revise layout)
5
Figure 7.1
To Accompany
Krajewski & Ritzman
Absolute Locations
Frozen
foods Meats
Dry
groceries
Bread Vegetables
Frozen
Meats
foods
Dry
groceries
Vegetables Bread
Milling
Office machines Foundry
Figure 7.3
To Accompany
Krajewski & Ritzman
Group Technology
One Worker, Multiple Machines Machine
2
Machine
Machine 3
1
Materials in
Finished
goods out
Machine
Figure 7.4 Machine 4
To Accompany 5
Krajewski & Ritzman
Group Technology
Lathing Milling Drilling
L L M M D D
D D
L L M M
Grinding
L L M M
G G
L L Assembly
G G
A A
Receiving and A A G G
shipping
L L M D G Assembly
area
Cell 1 Cell 2 A A
Receiving L M G G
Cell 3
L M D
Shipping
(b) Line flows in a job shop with three GT cells Figure 7.5
To Accompany
Krajewski & Ritzman
Office of Budget
Management
Department Area Needed (ft2)
1. Administration 3,500
2. Social services 2,600
3. Institutions 2,400
4. Accounting 1,600
5. Education 1,500
6. Internal audit 3,400
Total 15,000
3 6 4
100'
1 2 5
Figure 7.6
To Accompany 150'
Krajewski & Ritzman
Office of Budget 3 6 4
Management
100'
1 2 5
150'
To Accompany
Krajewski & Ritzman
Office of Budget 3 6 4
Management
100'
1 2 5
150'
100'
1 5
150'
To Accompany
Figure 7.7
Krajewski & Ritzman
Office of Budget 3 6 4
Management
100'
1 2 5
150'
6 3
100'
1 5
150'
To Accompany
Figure 7.7
Krajewski & Ritzman
Office of Budget 3 6 4
Management
100'
1 2 5
150'
6 2 3
100'
1 4 5
150'
To Accompany
Figure 7.7
Krajewski & Ritzman
Office of Budget 3 6 4
Management
100'
1 2 5
150'
6 2 3
100'
1 4 5
150'
To Accompany
Figure 7.7
Krajewski & Ritzman
Out-and-Back Warehouse
Storage area
3 5 5 6 4 2 7
Dock Aisle
1 5 5 4 4 2 7
Storage area
Figure 7.10
To Accompany
Krajewski & Ritzman
Zone Systems
Zones Zones Control
station Shipping
Tractor
trailer
Tractor
trailer
Feeder Feeder
lines lines Overflow
To Accompany
Figure 7.11
Krajewski & Ritzman
Design Product Layouts: Line
Balancing
Line balancing is the process of assigning tasks to workstations
in such a way that the workstations have approximately the same
processing time requirements. This results in the minimized idle time
along the line and high utilization of labor and equipment.
4 tasks 2 tasks
Worker 1 Worker 2
Bottleneck
60/hr. 60/hr.
1 min. 1 min. 1 min.
30/hr.
2 min. 30/hr.
Parallel Workstations
18
The obstacle
• The difficulty to forming task bundles that have the
same duration.
• The difference among the elemental task lengths
can not be overcome by grouping task.
– Ex: Can you split the tasks with task times {1,2,3,4} into
two groups such that total task time in each group is the
same?
– Ex: Try the above question with {1,2,2,4}
• A required technological sequence prohibit the
desirable task combinations
– Ex: Let the task times be {1,2,3,4} but suppose that the
task with time 1 can only done after the task with time 4 is
completed. Moreover task with time 3 can only done after
19 the task with time 2 is completed. How to group?
Cycle Time
N min
t
Total task time for a product t
OT/D Availabale time for a product CT
I
dle
timeperc
yc
le
P
er
cen
tid
le
tim
e=
(
N)(
CT)
23
Example 1: Precedence Diagram
Precedence diagram: Tool used in line
balancing to display elemental tasks and
sequence requirements
0.1 min. 1.0 min.
a b
c d e
0.7 min. 0.5 min. 0.2 min.
24
Example 1: Assembly Line
Balancing
• Arrange tasks shown in the previous slide
into workstations.
– Use a cycle time of 1.0 minute
• Every 1 minute, 1 unit must be completed
– Rule: Assign tasks in order of the most number
of followers
• If you are to choose between a and c, choose a
• If you are to choose between b and d, choose b
• Number of followers: a:3, b:2, c:2, d:1, e:0
– Eligible task fits into the remaining time and all
25
of its predecessors are assigned.
Solution to Example 1.
Assigning operations by the number
Work-
of
Time
followers
Assign Station
Work- Time Assign Station
Station
Station Remaining
Remaining Eligible
Eligible Task
Task Idle
IdleTime
Time
11 1.0
1.0 a,c
a,c aa
.9
.9 cc cc
.2
.2 none
none -- .2
.2
22 1.0
1.0 bb bb
00 none
none -- 00
33 1.0
1.0 dd dd
.5
.5 ee ee
.3
.3 -- -- .3
.3
.5
.5
- Eligible operation fits into the remaining time and its predecessors are already
assigned
26 .
- What is the minimum cycle time possible for this example?
Calculate Percent Idle Time
0.2 0 0.3
Percent idle time = 0.167 16.7%
(3)(1)
27
Line Balancing Heuristic Rules
• Assign tasks in order of most following
tasks.
• Assign task in the order of the greatest task
time.
• Assign tasks in order of greatest positional
weight.
– Positional weight is the sum of each task’s
time and the times of all following tasks.
28
Solution to Example 1. Assigning
operations using their task times.
Work-
Work- Time
Time Assign
Assign Station
Station
Station
Station Remaining
Remaining Eligible
Eligible Task
Task Idle
IdleTime
Time
11 1.0
1.0 a,c
a,c cc
.9
.9 aa aa
.2
.2 none
none -- .2
.2
22 1.0
1.0 bb bb
00 none
none -- 00
33 1.0
1.0 dd dd
.5
.5 ee ee
.3
.3 -- -- .3
.3
.5
.5
Eligible operation fits into the remaining time and its predecessors are already
assigned
29 .
Positional Weights
30
Solution to Example 1. Assigning
operations using their task times.
Work-
Work- Time
Time Assign
Assign Station
Station
Station
Station Remaining
Remaining Eligible
Eligible Task
Task Idle
IdleTime
Time
11 1.0
1.0 a,c
a,c aa
.9
.9 cc cc
.2
.2 none
none -- .2
.2
22 1.0
1.0 bb bb
00 none
none -- 00
33 1.0
1.0 dd dd
.5
.5 ee ee
.3
.3 -- -- .3
.3
.5
.5
Eligible operation fits into the remaining time and its predecessors are already
assigned
31 .
Example 2
0.8 0.6
c d f g h
1.0 0.4 0.3
32
Solution to Example 2
a b e
f g h
c d
33
Line Balancing
Example 7.3
Line Balancing Big Broadcaster
Example 7.3
Line Balancing Big Broadcaster
Example 7.3
Line Balancing Big Broadcaster
Example 7.3
Line Balancing Big Broadcaster
Example 7.3
Line Balancing Big Broadcaster
Example 7.3
Line Balancing Big Broadcaster
40 C
50
Example 7.3
Line Balancing Big Broadcaster
Example 7.3
Line Balancing Big Broadcaster
G
Example 7.3 15
Line Balancing Big Broadcaster
G
Example 7.3 15
Line Balancing Big Broadcaster
D
H
B 40
20
30 E
A 6
F
40 C 25
50 I
18
G
Figure 7.12 15
• Desired output rate, r must be matched to the
staffing or production plan.
c = 60 seconds/unit
TM = 5 stations D
Efficiency = 81.3% H
B 40
20
S1 30 E
S3 6
A S4
S2 F
Cumm Idle
Station CandidateS5
Choice Time Time
40 C 25 S1 A A 40 20
50 S2 B,C C
I 50 10
S3 B,F,G B 30 30
E,F,G 18
F 55 5
G
Figure 7.13 15
The goal is to cluster the work elements Green Grass, Inc.
into 5 workstations so that the number of
work-stations is minimized, and the cycle Line Balancing Solution
time of 60 seconds is not violated. Here
we use the trial-and-error method to find
a solution, although commercial software
packages are also available.
D
H
B 40
20
S1 30 E
S3
A S4 6
S2
F S5
40 C 25
50 I
c = 60 seconds/unit
TM = 5 stations 18
G
Efficiency = 81.3%
© 2007 Pearson Education 15
From-To Chart
• Processes:
– X, Y, Z, Q, and R
• Parts that are manufactured through these
processes:
– Part No’s.: 1, 2, & 3
From-To Chart
To X Y Z Q R Total
From
Total
From-To Chart
To X Y Z Q R Total
From
X 1
Y 1
Z 1
R 1
Total
1 2
X
Y 1
Z 2 1
Q 2
R 1
Total
1 3 2
X
Y 1 3
Z 2 3 1
Q 2 3
R 1
Total
1 3 2 3
X
Y 1 3 2
Z 2 3 1 3
Q 2 3 2
R 1 1
11
Total 2 3 3 3 11
Soal 1
Tata letak sebuah rumah sakit ditunjukkan sebagai berikut
Cast-Setting
Ruang Ruang
Lab EKG Room 10’
Operasi Recovery
(5) (8)
(6) (7)
40’
D 0 0 0
Tentukan optimasi tata letak ruang berdasarkan orientasi
proses
Soal 3
4 4
4 4 4 4
(2) (3) (4)
4 4
5 5
(1) (2) (3) 3 8 8
(1) 11 11 (5)
8 13
12 (4)
10 8
(1) Refrigerator
4
14 (2) Counter
(5)
(3) Sink
(4) Storage
(5) Stove
Soal 4
Sebuah industri memiliki target produksi sebanyak 500 unit
perminggu dengan waktu efektif kerja sejumlah 4000 menit
per minggu. Pengerjaan produk tersebut dilakukan melalui
proses (tugas) sebagai berikut
A 5 -
B 3 A
C 4 B
D 3 B
E 6 C
F 1 C
G 4 D,E,F
H 2 G
A 1 -
B 1 A
C 2 A
D 1 C
E 3 C
F 1 C
G 1 D,E,F
H 2 B
I 1 G,H
1 0,1 -
2 0,1 1
3 0,1 2
4 0,2 2
5 0,1 2
6 0,2 3,4,5
7 0,1 1
8 0,1 7
9 0,2 7,8
10 0,1 9
11 0,2 6
12 0,2 10,11
13 0,1 12