Beruflich Dokumente
Kultur Dokumente
• Causes of delays.
• References.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 2
CONSTRUCTION SCHEDULE DELAYS
“An Event or a condition that that results in finishing the project later than stipulated
in the contract.” Mubarak (2005)
“The time during which some part of the construction project has been extended or
not executed owing to an unexpected event.” Callahn (1992)
“T o make something happen later than expected or to not act timely.” Trauner (2009)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 3
CAUSES OF DELAYS
Following are 10 most significant causes of delays in UAE construction industry (Source: Faridi and Al Sayegh. 2006)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 4
CAUSES OF DELAYS
Summary of previous studies on causes of delays (Source: Lo at el . 2006)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 5
CAUSES OF DELAYS
Summary of previous studies on causes of delays (Source: Lo at el . 2006) (Continued)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 6
TYPES OF CONSTRUCTION DELAYS
Critical or Non-Critical
Excusable or Non-Excusable
Compensable or Non-Compensable
Concurrent or Non-Concurrent
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 7
Critical or Non-Critical Delays
Critical Delays
Affecting project finish date.
Non-Critical Delays
Not affecting project finish date.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 8
Excusable and Non-Excusable Delays
Excusable Delay
Caused by unforeseeable even beyond contractor’s control.
Non-Excusable Delay
Caused or not caused by the contractor but should have been foreseen by the
contractor.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 9
Excusable Vs. Non-Excusable
• Lack of action by government bodies, such as building inspection. • Late delivery of the contractor's furnished materials and equipment.
• Illness or death of one or more contractors.
• Epidemics
• Quarantine restrictions.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 10
Excusability Vs. Compensability
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 11
Excusability Vs. Compensability
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 12
Concurrent and Non-Concurrent Delays
Concurrent Delays
Combination of two or more independent delay events occurring within the same
time frame.
Non-Concurrent Delay
Delays events that occur independently & separately without overlapping.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 13
SCHEDULES TO BE USED IN DELAYS
As-Planned Schedule
The As-Planned schedule is a graphical representation of the contractor’s original intention for the
completion of the project. It shows different critical paths as well as planned activities and their
sequence.
As-Built Schedule
The As-Built schedule shows the actual sequence and progress of activities in the project as they
occurred in real life, including the slowdowns, work stoppages and accelerations.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 14
SCHEDULE DELAY ANALYSIS TECHNIQUES
Impacted
• PROSPECTIVE 1
• RETROSPECTIVE As-Planned
As-Planned
Vs 4
As Built
Collapsed
5
As-Build
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 15
1- Impacted As Planned
As-Planned Schedule
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 16
1- Impacted As Planned
Delay Event-1
As Planned Completion
Delay = 3 Days
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 17
1- Impacted As Planned
Delay Event-2
Previous Completion
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 18
1- Impacted As Planned
Delay Event-3
Previous Completion
Delay = 1 Day
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 19
1- Impacted As Planned
Delay Event-4
Previous Completion
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 20
1- Impacted As Planned
Delay Event-5
Previous Completion
Delay = 1 Day
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 21
1- Impacted As Planned
Delay Event-6
Previous Completion
Delay = 4 Days
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 22
1- Impacted As Planned
Delay Event-7
Previous Completion
Delay = 3 Days
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 23
1- Impacted As Planned
Delay Event-8
Previous Completion
Delay = 1 Day
Current Completion
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 24
1- Impacted As Planned
Impacted As Planned-Results
Chronology of Activity ID Delay
delays Type Duration Impact (Days)
1 D1 NN 3 3
2 D2 EC 7 0
3 D3 NN 1 1
4 D4 EC 1 0
5 D5 EC 8 1
6 D6 EC 5 4
7 D7 NN 3 3
8 D8 EC 8 1
TOTAL -- -- 36 13
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 25
1- Impacted As Planned
Strengths
1. Simple to conduct
2. Clear view of cause and effect
3. Useful where no as-built data exists
4. Clearly communicated
5. Good for repetitive or sequential projects
Weaknesses
1. Theoretical results
2. No account of mitigation or acceleration
3. Relies (and maintains) the as-planned programme throughout
4. Noted as being ‘fundamentally flawed’
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 26
2- Time Impact Analysis (TIA)
Prospective Retrospective
(Before Delay) (After Delay)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 27
2- Time Impact Analysis (TIA)
As-Planned Schedule
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 28
2- Time Impact Analysis (TIA)
1. First Update (As-Built fed in)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 29
2- Time Impact Analysis (TIA)
3. Prepare a Delay fragnet for depicted delay
Schedule
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 30
2- Time Impact Analysis (TIA)
5. Evaluate effect of delay event#1 on project finish date
Delay: 1D
6. Change order is issued for Roof Structure design and is estimated to take 5 extra days
to finish roof structure
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 31
2- Time Impact Analysis (TIA)
7. Prepare Delay Fragnet for Change Order
Schedule
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 32
2- Time Impact Analysis (TIA)
9. Evaluate effect of delay event#1 on project finish date
Delay: 6 Days
1. Factual
2. Identifies contemporary situation at the time of the delaying event
3. Prospective and retrospective
4. Very strong when combined with an as-built critical path
5. Demonstrates concurrency, mitigation, acceleration and re-sequencing
Weaknesses
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 34
3- Windows analysis
Start Window (As Planned Schedule)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 35
3- Windows analysis
Window-1 (Day 10)
Delay: 1 Days
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 36
3- Windows analysis
Window-2 (Day 21)
Delay: 1 Days
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 37
3- Windows analysis
Window-3 (Day 32)
Delay: 2 Days
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 38
3- Windows analysis
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 39
3- Windows Analysis
Strengths
1. Factual
2. Easy to understand
3. More division in windows, increases accuracy.
4. Consider dynamic nature of CP.
5. Accepted by researchers, experts, courts and boards.
Weaknesses
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 40
4- As Planned Vs. As Built
Chronology Activity ID D9Delay
of delays Type Duration
As-Planned
1 D1 NN 3
2 D2 NN 1
3 D3 EC 7
4 D4 EC 1
5 D5 EC 4
6 D6 EC 2
7 D7 NN 5
8 D8 EC 4
9 D9 NN 3
10 D10 EC 3
As-Built
Sum of Contractor Caused Delay= ∑ NNi = 3+1+5+3 = 12 D
Sum of Owner Caused Delay = ∑ ECi = 7+1+4+2+4+3 = 21 D
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 41
4- As-Planned Vs As-Built
Strengths
1. Factual
2. Simple and cost effective
3. Clear and simple (generally)
Weaknesses
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 42
5- Collapsed As-Built
1 D1 NN 3
2 D2 NN 1
7 D7 NN 5
9 D9 NN 3
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 45
MAIN PRINCIPALS FOR ANALYSING SCHEDULE DELAYS
1. As-Planned Schedule (Baseline) should be available and approved by owner
3. As-Built Schedule (Updated Schedule) should be prepared to analyze changes on the project.
4. While analyzing delays, chronological order should be adopted from the beginning of the project.
7. While inserting delays, original logic should not be removed and should be kept intact, even if it has become redundant.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 46
MAIN PRINCIPALS FOR ANAYSING SCHEDULE DELAYS
10. Activities representing delay should have special ID and Clear Description of delay.
11. It is acceptable to add a delay as a successor to an activity when in fact, that delay occurred during the activity and
12. It is also acceptable to split the existing delayed activity into two activities, with one representing the portion of the
planned work to be performed before the delay, and the other portion of the planned work after the delay, as long as the
combined durations of the split activities equals the original duration of that activity.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 47
SELECTION OF DELAY ANALYSIS METHODOLOGY
• Terms of Contract
• Availability of as-built data such as Daily Reports, MOM’s, Inspection Reports, Payment Details etc.
• Type of Work
• Nature of delay
• Status of Project/Time of Analysis
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 48
Mapping of DAT’s
Extensive
Data & Effort
TIA
WA
CAB
Unreliable Reliable
IAP
AP Vs AB LEGENDS
TIA : Time Impact Analysis
IAP: Impacted as planned
AP Vs. AB: As-Built Vs. As-Planned
Non-Extensive CAB: Collapsed As-Built
Al Muhaidib Contracting Co. 49
Data & Effort WA: Windows Analysis
COMPONENTS OF A GOOD EOT CLAIM
1. Description of Project.
2. The details of the parties.
3. The details of the contract particulars.
4. Brief detail of Delay Event on which EOT is based.
5. Definitions used in contract and in EOT document.
6. Establishing EOT entitlement (Contract Review).
7. As-Planned Schedule.
8. As-Built Schedule.
9. Complete & Detailed Delay Analysis.
10.Overall effect on completion date.
11.Evidences of delays.
12.Clear Statement of Extension of Time requested.
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 50
References
• AACE International’s Recommended Practice for TIA.
• “Prospective & Retrospective Time Impact Analysis” by Building Briefings Magazine. (Research Paper)
• “Construction Delay Analysis Techniques” by MDPI OPEN ACCESS Publishing. (Research Paper)
• “Delay Analysis and Problems with Methodologies” by David Barry (Research Paper)
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 51
QUERY SESSION
Al Muhaidib Contracting Co. Training : Construction Schedule Delays and Delay Impact Analysis Techniques. 52
THANK YOU