Beruflich Dokumente
Kultur Dokumente
Ch 1 -2
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall
Finals Rescheduling
Do IP Project presentation on Dec 12
Exam 3 done asynchronously via Blackboard on Dec
16
Final IP Project Due Dec 18
Activity Float
Activity Descriptor
Basic math
ES + DUR = EF
LF - DUR = LS
LS – ES = AF
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 9-10
Rules for Forward/Backward Pass
Forward Pass Rules (ES & EF)
ES + Duration = EF
EF of predecessor = ES of successor
Largest preceding EF at a merge point becomes ES for
successor
A B
3 4 7
A
7 5 12
C
0 5 5
2 4 2
4 8 12 16 5 21 5 9
0 0 0
Start C I Finish
8 4 1 2 4 2
0 4 4 4 4 8
2 1 5
D E
F J
ES DUR EF
Activity
LS TS LF
A B
6 3 10 10 3 15
C
0 4 4
10 3 15
A
2 2 6 4 5 9
B
6 2 11
8 4 1 2 4 2
0 4 4 4 4 8
2 1 5
D E
F J
0 0 4 8 4 1
1 4 1 2 0 2
2
2 6 1 5
SLACK.xls
cp.mpp
9-21
Examine Critical Path for Reality Check
Is the total duration typical?
Are the durations of the CP activities typical?
Reexamine all CP activity durations
Reexamine assumptions
0 A 5 5 B 15 15 C 18
0 5 5 5 10 15 15 3 18
0 Hammock 18
0 18 18
FIGURE 9.25
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 09-25
Reducing the Critical Path
Eliminate tasks on the CP
Convert serial paths to parallel when possible
Overlap sequential tasks
Shorten the duration on critical path tasks
Shorten
early tasks
longest tasks
easiest tasks
tasks that cost the least to speed up
http://active.boeing.com/commercial/orders/index.cfm?content=displaystandardreport.cfm&Req
uestTimeout=500&optReportType=AnnOrd&pageid=m15521
0 A 6 6 B 11 Lag 4 15 C 22
Spec Design Design Check Blueprinting
6 5 7
15 D 21
Wiring
6
Lag 3
10 A 16 16 B 21 21 C 22
Plumbing HVAC Inspection
6 5 1
30 D 36
Wiring
6
Lag 3
33 B 36 36 C 37
31 A 33 HVAC Inspection
Plumbing 5 1
6
30 D 36
Wiring
6 Lag 3
22 A 28 28 B 33 33 C 34
Plumbing HVAC Inspection
6 5 1
gantt.mpp
Completed Gantt Chart for Project Delta
FIGURE 10.8
FIGURE 10.9
FIGURE 10.10
FIGURE 10.11
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall Table 10.1 10-44
FIGURE 10.14 Time–Cost Trade-Offs for Crashing Activities
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 10-45
FIGURE 10.15 Fully Crashed Project Activity Network
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 10-46
FIGURE 10.16 Relationship Between Cost and Days Saved in a Crashed Project
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 10-47
Activity on Arrow Networks
Activities represented by arrows
Widely used in construction
Event nodes easy to flag
Forward and backward pass logic similar to AON
Two activities may not begin and end at common
nodes
Dummy activities may be required
FIGURE 10.18
FIGURE 10.19
FIGURE 10.20A
Copyright © 2013 Pearson Education, Inc. Publishing as Prentice Hall 10-51
Alternative Way to Represent Activities
with Two or More Immediate Successors
(Wrong)
FIGURE 10.20B
FIGURE 10.20C
FIGURE 10.21
FIGURE 10.22
FIGURE 10.23
FIGURE 10.24