Beruflich Dokumente
Kultur Dokumente
Documents
Group 4
CORDERO, Drundle
DE LARA Ricard
MANUEL, Ira Joshua
TECHNICAL SPECIFICATION
What is Technical Specification
• Are documents that defines a set of
requirements for the erection of a structure
• Contains detailed technical provisions related
to installation or construction of work and
materials
• Purpose:
– Is to highlight the necessary information which
cannot be obtained from drawing plans.
– To show strength of construction material or
construction work.
Categories for Technical Specification
1. General Requirements
2. Site work
3. Concrete
4. Masonry
5. Metals
6. Wood and Plastics
7. Thermal and Moisture Protection
8. Doors and Windows
9. Finishes
10. Specialties
11. Equipment
12. Furnishings
13. Special Construction
14. Conveying Systems
15. Mechanical
16. Electrical
General Requirements
• Processing and Securing of Permits and
Insurance
– Contractor shall be responsible for securing all
necessary permits related to the project.
• Building Permits, Occupancy Permits, etc.
• Contractor’s All Risk Insurance (CARI), other insurances.
Site Work
• Focus on the completion of the following:
a) Site Clearing
b) Temporary Site Facilities
c) Storage and Filing of Materials
d) Excavation
e) Backfilling
f) Compacting
g) Soil Treatment
Concrete
• The work includes the provision of cast in
place concrete.
• Submittals:
– Shop Drawings
– Contractor Mix Design
– Certified Laboratory Test Reports
– Certificate of Compliance
– Catalog Data
Masonry
• Covers the completion of works on Reinforced
Masonry
Metal
• The work includes the fabrication, erection
and shop painting of structural steel in
accordance with the AISC “Manual of Steel
Construction”
• Submittals:
– Shop Drawings
– Erection Plan
– Certificate of Conformance
– Certified Test Reports
Wood and Plastics
• Finish Carpentry
– Covers the supply and furnishing of materials
including equipment and performing labor
necessary to complete the installation of all finish
carpentry works as shown on drawings.
– Submittals
• Shop Drawings
• Certificates of Grade
Thermal and Moisture
• Covers the furnishing of materials including
equipment and performing labor necessary to
complete the following:
– Dampproofing
– Building Insulation
– Roof Insulations
– Sealants and Caulking
Doors and Windows
• Covers the complete installation of all steel
doors and frames as shown on drawings and
schedule.
– Submittals:
• Catalog Data
• Shop Drawings
• Certificates of Conformance
Finishes
• Covers the completion of the following:
– Epoxy Coating
– Granite & Ceramic Tiles
– Vinyl Flooring
– Carpet Tile
– Floor Hardener
– Plastering
– Plasterboard
– Painting
– Etc..
Specialties
• Covers the completion of the following:
– Toilet Compartments
– Toilet Accessories
– Security Barriers
– Blinds
Furnishing
• Covers the completions of furniture and its
accessories
Special Construction
• Covers the completion of the following:
– Lighting Protection
– Fire Protection Systems
Conveying System
• Samples of the coverage of a conveying
system:
– Elevators
– Escalators
– Baggage Handling System
Mechanical
• Covers the completion of Plumbing and HVAC
Systems of a structure.
• HVAC: (samples)
– Noise and Vibration Control
– Mechanical System
– Ventilation and Exhaust System
• Plumbing: (samples)
– Plumbing Works and Fixtures
Electrical
• Covers the completion of the Electrical System
of a structure.
Project Organization Structure
Project Specification
Progress Report
Inspection Procedure
Time Scheduling
Cash Planning
Quality Control Plan
Variation Order & Time Extension
Progress Payment
Project Organizational Structure
Project Organization
Structure
• Defines the human infrastructure
Project Specification of the project
Progress Report
Inspection Procedure • This task is designed to define:
Time Scheduling
– The project organization chart
Cash Planning
Quality Control Plan – The roles
Variation Order & Time
Extension
– The relationships of the team
Progress Payment
Sample Organizational Structure
Project Specification
Project Organization
Structure • It is a broad description of the
Project Specification
Progress Report
objectives for a progress
Inspection Procedure project.
Time Scheduling
Cash Planning • Describes the materials and
Quality Control Plan
Variation Order & Time workmanship required for a
Extension
Progress Payment
development.
Progress Reports
Project Organization
Structure • Tackled on weekly meetings.
Project Specification
Progress Report • Progress Reports should be
Inspection Procedure
Time Scheduling
address to the owner,
Cash Planning construction manager, and
Quality Control Plan
Variation Order & Time architect of the project.
Extension
Progress Payment • Includes:
– Progress photographs
– Logbook
Sample Logbook
Inspection Procedure
Project Organization
Structure • Focus on testing, inspection of
Project Specification materials and works, and giving
Progress Report
Inspection Procedure
permits to perform task.
Time Scheduling
• To check the quality of the work
Cash Planning
Quality Control Plan done on the project
Variation Order & Time
Extension
Progress Payment
Test Report on Compressive Strength of Concrete
Cylindrical Specimen
Request for Concrete Pouring
Time Scheduling
Project Organization
Structure • It is a viral part for on-time
Project Specification
Progress Report
accomplishment and delivery
Inspection Procedure of the project.
Time Scheduling
Cash Planning • Methods used:
Quality Control Plan
Variation Order & Time – Bar Chart
Extension
Progress Payment – CPM Schedule
CPM Scheduling
Cash Planning
Project Organization
Structure • Two methods:
Project Specification
Progress Report
– Cash Flow - Is the incoming and
Inspection Procedure outgoing of cash, representing
Time Scheduling the operating activities of an
Cash Planning
Quality Control Plan
organization.
Variation Order & Time
Extension
Progress Payment – S-Curve – defined as a display
of cumulative costs, labor
hours or other quantities
plotted against time.
Quality Control Plan (QCP)
Project Organization
Structure • The documentation of the
Project Specification process for delivering the level
Progress Report
Inspection Procedure of construction quality required
Time Scheduling
Cash Planning
by the contract.
Quality Control Plan • It is a framework for the
Variation Order & Time
Extension contractor’s process for
Progress Payment
delivering quality construction.
• Outlines how the results or
outcome will be achieved.
Sample Quality Control Plan
Variation Order & Time Extension
Project Organization
Structure
• This are the changes or addition in
Project Specification plan and this will be made due to
Progress Report encountered unforeseen obstacles
Inspection Procedure and errors in the actual application
Time Scheduling
Cash Planning
of the plan.
Quality Control Plan • Will serve as an option to catch to
Variation Order & Time
Extension
their target accomplishment.
Progress Payment • Shows the detailed changes in the
plan and it is supported with
documents showing the location of
the errors they encountered.
• Common causes of Variation Order:
– Insufficiency of the materials
– Problems/Errors while performing the actual plan
– Replacement of materials used
– Changes on the Specifications
Request for Change of Order
Request for Time Extension
Progress Payment
Project Organization
Structure • Are partial payments for the
Project Specification
Progress Report
accomplishment of work
Inspection Procedure done in a period of
Time Scheduling
Cash Planning construction, usually
Quality Control Plan
Variation Order & Time
monthly.
Extension
Progress Payment
• The Quantity Surveyor
prepares the Progress
Billings/Payment.
Project Plan
• Is an approved document used to gide both
project execution and project control.
• Primary uses: to document
– Assumptions and conculsion
– Statement and document accepted scope
– Cost and schedule
Materials Procurement
• Bill of Materials (BOM)
• Material Costing
• Purchase Order
PROJECT DOCUMENTS
PROGRAM & PLANNING
• Project Information
Primary Stake Holders
General Information
Location / Vicinity Map
• General Assumptions
Project Calendar
• Project Schedule Activity ID
• Target Productivity
• Gantt Chart Schedule
• Milestone and Key Dates
• Time Location Diagram
• Equipment Loading Schedule
SAFETY PROCEDURE AND
INSPECTION
• Precautionary Duty
• Role and Responsibilities
Project Manager / Project in Charge – Overall responsible for all EHS
matters in the project
EHS Officer – Conduct routine inspection on equipment, work places,
hazardous materials, etc.
Field Supervisors / Engineers – Responsible for maintaining safe working
condition and practices for the safety of all men under his supervision
Equipment head – Monitor and keeps record of equipment maintenance
Nurse / First –Aider – Administer first-aid treatment for serious injuries and
illnesses.
Workers – Take all precautions so as not to endanger his/her self or co-
workers
• Safety and Health Requirement (Codes and Laws)
• Disciplinary Policy
• Accident Investigation
• Work Permits
QUALITY ASSURANCE / CONTROL
INSPECTION PROCEDURES
• Safety Guidelines
• Waste Management Program
RISK MANAGEMENT
• Emergency Preparedness Guidelines
Medical
Fire
Weather
Structural Accident
Extend Power Loss
• Evacuation Routes
• Training