Beruflich Dokumente
Kultur Dokumente
Objective of Study
The control schedule process can be broken down into three components, namely
inputs, tools and techniques and outputs. Figure 9 shows the different aspects included
in each of these components. These inputs, tools and techniques and outputs are
briefly addressed below, based on The Project Management Institute’s descriptions
(Project Management Institute, Inc., 2013).
Chapter-3
Case Study and Analysis
Defining activities
Sequencing activities
Estimating activity resources
Estimating activity durations
Developing schedule
Work Break Down Structure of Chindwin Bridge (Homalin) Construction Project
Figure .Work Break Down Structure of Chindwin Bridge (Homalin) Construction Project
Defining Activities and Activities List
Critical path is the sequence of stages where we figure out what the least amount of time is
necessary to complete a task with the least amount of slack. Therefore, the critical path is the longest length of
time it will take to complete the project tasks.
It is required to understand dependencies and other constraint that might impact the start of this
task, earliest finish date, the latest start date. It is required to calculate what the latest finish date is for the same
reason. By having a clear picture of this timeframe, we can better schedule the project to meet its deadline.
Float, also known as slack, is a term that describes how long we can delay a task before it impacts
the planned schedule and threatens the project’s deadline. When we are collecting tasks for the critical path,
they must have zero float.
Crash duration is a term that describes the shortest amount of time that a task can be scheduled. We
can get this by moving around resources, adding more towards the end of the task, to decrease the time needed
to complete the task. This often means a reduction in quality, but is based on a relationship between cost and
time. In this project, in order to catch up some delay, we have to crash some activities.
Figure 3.10 Gantt Chart for the construction plan of Homalin Bridge.
Short Interval Planning
In some phases, execution did not match with planning due to following reasons.
(1) Impractical planning/scheduling
(2) Mistakes in communication of the plan/schedule
(3) Improper translation and implementation of the plan/ schedule.
In some phases, we used three-week interval SIP to track the intangible obstacles to
implementation works according to schedule.
We use S-curve tools for monitoring of Homalin Bridge Project as it is the very useful project management tool that
can track the progress of the project over the time and allow to get quick visual status to determine project
condition.
In the beginning of the project, there was delay in the preparation stage due to delay in land compensation
processes. The gap between actual and plan was narrowed down due to some concurrent activities, in the beginning
of the bore pile works. Then, the gap between actual and plan widen again due to late completion in the Mini bored
pile of H1-H10 works and Mini Pier Shaft works. Then due to multiples concurrent activities and additional resource
utilization between Dec-2016 to Sep-2017 the actual completion trend is catch up again to narrow down the gap.
Finally , the completion rate catch up is speed up further and the project was completed within planned completion
date Mar-2018.
To prevent the wrong interpretation of the project progress, we used three methods for measuring project
completion.
1. Units Completion
For example, foundation works for this project was weighted as 30% of the whole project. There were 128 bored pile
included in the foundation work. Each unit completion of bored pile work was considered 0.234% of the whole
project.
2. Incremental Milestones
For example, we consider preparation works carried 5% of the whole project work, foundation works is 30%, sub-
structure works 30%, super-structure works is 30% and finishing works is 5% of the whole project. Each mile stones
were used to update the job completion amount of the whole project.
3. Experience
For example, each of 3 major parts of the whole project, namely, foundation works, sub-structure and super-
structure works were considered 30% of the whole project. The others works were considered 10% of the whole
project.
Figure S-curve for the construction plan of Homalin Bridge.
3.4 Schedule Control
Lands compensation
. Completion for negotiation with local farmers is unpredictable. In actual, it took 4 more months to come to an
agreement with the local farmers for compensation with the aid of authorities.
To reduce the delay, regional Member of Parliament and prime minister of Sagaing Region helped their best to reach
the consensus with effected land owners.
Tendering processes
The Least Cost Selection Method was used for selection of successful company. There are some delays in procurement
of construction material by tendering as suppliers were forced to use the cheapest transportation method. Most of
them could not deliver as per contract terms deadline. The local contractors for sand and aggregate were also causing
some delay production.
3.4.2 Delay-2 (Delay during Bored Pile Foundation)
JMM Company won the tender for the fabrication of steel truss 120m x 4 span and box girder 60 m x2 spans. JMM also
faced the high volume of order at that time as the other bridge was constructed at the other location on the same river. Due
to JMM factory capacity constraint, one bridge needs to prioritise. The MOC head office decided to fabricate for the other
bridge first. According to the procurement planning, JMM need to complete the fabrication from Jan-2017 to Jun-2017. In
actual, the fabrication process took from April-2017 to Oct-2017. There was three- and half-month delay.
According to original master schedule plan, steel truss erection must begin in Jun-2017 for RP4 and RP5. The remaining
three spans were arranged to erect during September to end of December, 2017. In fact, there was high flood during July
and August 2017 and the river water level and flow rate is very high and not possible for erection activities. In actual, there
was flooding season began early and the erection schedule for the month of June was not able to carry out. The steel truss
erection was begun in September and completed on 25-Jan-2018. There was one-month delay for overall erection
schedule.
3.4.7 Delay-7 (Delay during Overlay works)
Strength
Financial support for the project is strong and sufficient throughout the project. This factor support strongly for all
schedule to execute without delay due to budget.
Most of the locals support to start the project as soon as possible. The regional authorities and parliament
members also support the project to start early.
Weakness
Some of the land owner, whose land were fall within project area were not pleased with the project. There were no
preliminary statistics of locals acceptance on the project.
3.5.2 Analysis for bored pile
Strength
Most of the project team members were very experienced in bored pile drilling operation for many years.
The changing of construction method and resource mobilisation for bored piling is quick enough to recover the delay due
to machine shortage for 1.5m diameter bored pile to 0.8m diameter bored pile of the approached bridge foundation. Mini
bored pile machine for 0.8m diameter size were available abundantly in the market.
Weakness
Proper machinery equipment for bored pile drilling is not sufficient in the organisation. The current stock of the
machinery are very old model.
Availability and transportation for machine spare parts were very tough due to old model and remote project area.
Recommendation
The machinery stock of the organization should be replaced with new models. The number of machinery also should be
increased. Spare parts inventory management should be improved and closely liaised with OEMs (Original equipment
Manufacturers).
3.5.3 Analysis for pile cap
Strength
All the pile cap construction works were able to complete before river water level raise above the cap level. Therefore,
we are able to avoid the costly construction form works such as water tight cage. Construction materials and working
labour force were easily available at the nearby town. The transportation facilities such as Z craft and crane were
available with reasonable price.
Weakness
There should be enough buffer for the scheduling of pile cap construction and influence of river water level on the
construction process is severe. The flooding level cycle is also tough to predict precisely.
There was shortage for teak supply for the form works of pile cap construction process due to sudden ban on the teak
production due to environmental concern. Planner should consider alternative way of getting supply of form works since
beginning.
Recommendation
Project managers should provide detail working schedule for all work breakdown structures and should communicate
with all stake holders to understand the important of each step-in working schedule, weekly & daily schedule. Also need
to monitor, review and update schedule for all work packages and especially should provide short interval program (SIP)
and taking comment & suggestion from all levels.
3.5.4 Analysis for Pier Shaft and Cross Beam construction
Strength
The project members has the ample amount of working experience related to construction of Pier Shaft and Cross Beam
construction. There was more than sufficient working force were available at that point of time. Construction activities were
carried out with two shift adopting crashing strategy.
Weakness
Construction materials such as angle iron for formwork of pier shaft and cross beam were delivered late.
Recommendation
Project managers should apply integrated schedule management for future projects and need to solve immediately if
schedule problems will be occurred and take prompt action to update schedule with appropriate resource allocating
simultaneously.
3.5.5 Analysis of Fabrication and Transportation of Steel Truss
The planner was schedule at the right time for steel truss delivery time. There was originally sufficient lag in scheduling.
Strength
The schedule of this part does not fall in the critical part. There is about free float about one month originally and there
was lag caused by earlier. Therefore the delay in this schedule did not impact fully to overall project duration. This situation
reduced the dependency to supplier delivery condition to some extent.
Weakness
The steel trusses were purchased from J & M Steel solution which is joint venture of MOC and JFE Company. The deal was
made between internal companies. Therefore, liquidated damage and compensation clauses were not very clear and
effective.
Recommendation
There are no competitive suppliers when it comes to steel fabrication for superstructure of the bridge. JMM is joint venture
business with MOC. Therefore, there is no competition and service level is not sufficient. For the long term, to create
competitive market environment, MOC need to attract more steel suppliers for superstructure of the bridge
3.6 Lesson Learnt
Seasonal Effect
After sequencing the activities, we estimated duration of as shown in the below figure.
Season factor has the influence on the duration of the activities. For the steel truss erection works of RP5-RP4 was
planned to carry out from end of the May-2017 to end of the Jun-2017, the beginning of the flooding season. This is also
the first span of erection. We reserved two months buffer for this activity. Steel truss another three span (3x 120m) and
steel box girder (2 x 60m) scheduled to carry out form Sep-2017 to Dec-2017 (4 months). However, the raining season
for this year is started earlier and more raining than usual, the first span (RP5-RP4) erection works could not started as
planned.
The lesson learnt is to reserve more buffer time for seasonal dependent works because the predictability of
the weather and seasonal timing is less accurately lately.
Machinery
Machineries with sufficient capabilities were vital pillar for project execution according to schedule plan and
predictability for the control. Flexibility and good communication between project team and design department is really
helpful. In this project, we successfully revised the design in the foundation part to adapt the real ground situation faced
by project team. It allowed to increase the machine capacity which helped a lot to accelerate the project. MOC
machineries stock need to be expanded and upgraded further. There are also plan to acquire more machineries and their
related service through open tendering process and it is considered positive move.
Land Acquisition
The land compensation processes the project should not be under estimated in planning. Without land clearance,
project cannot be started and compensation agreement could be messed up uncontrolled if the management is not
smart enough. Negotiation and mediation power of regional authorities and representatives. Land acquisition evaluation
should be included in the feasibility study of the project.
Conclusion
Homalin Bridge is the important segment for transportation infrastructure in the upper Sagaing Region.
There is a lot of unexpected delay, difficulties encountered during the construction phases, and eventually project
team can overcome all the difficulties and obstacles with the aid of project scheduling and control tools , team works,
and experiences
The flooding historical data was incorporate in the project scheduling planning to avoid seasonal delay
due to flooding such as mid-river pile cap construction works were completed before the flooding season begun. There
were multiple delays occurred throughout the projects.
Project schedule planning and controlling played very important role in the Homalin Bridge with multiple
impacts on project cost, quality and time. Proper tools such as Gantt chart was utilized in the planning together with
activities list, WBS and CPM for the analysis.
In a positive note, the project also highlight the area for improvement in procurement, machineries,
tendering process, land compensation, steel truss sourcing for the future projects.