Objective
• Present one example of waste handling plant
which works according to the new corporate
procedure.
PROCEDURE (extract)
All converting plants must properly destroy all printed
and unprinted packaging material waste, and make
this waste available for Market Companies within
the Cluster to develop and continuously support
local recycling capacity for post-consumer cartons.
Deadline: All converting plants must ensure by no later than
December 2006 that all printed and/or laminated material is
shredded.
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
Balers
Shredder
Guillotine Roll Splitter
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
Guillotine
Roll Splitter
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
Installed power kW 15
Weight Roll Splitter daN 4500
Sound level – maximum dB(A) 85
Approach cost US$ 135.000
Contact P.O. Box 154 SE-271 24 YSTAD
SWEDEN - +46 411 64 300
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
Equipment: Presona Hydraulic Baler
Unit LP40 EH1 LP50 LP50 EH2
EH1
Eletric motor kW 15 22 37
Feed Opening mm 1250 1250 1250
Press force T 40 50 50
Specific Pressure Kp/ 5,2 6,5 6,5
cm²
Press chamber volume Max 2,2 2,2 2,2
(real) m³
Bale size HxW mm 720 x 720 x 720 x
1100 1100 1000
No of strapping wires 5 5 5
Oil tank capacity L 600 600 600
Weight T 14 14 14
Weight of packs Kg 350 350 350
Approach cost EURO 99.800
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
VM Apr/2005
WCM Environment Master Pillar Ponta Grossa Solid Waste Plant
Contact information
For additional information on the actual case, please contact:
Valéria Michel
valeria.michel@tetrapak.com
+55 19 3879 8204
Tetra Pak Monte Mor
VM Apr/2005