Sie sind auf Seite 1von 3

#Temperature controlled Products in the Yard and WIP

(not putaway) by storage code & hrs since arrival


INBOUND SAAG
Need to consider how much of it must happen
Actual/ Capacity by Shift
within how many hours to be within target:
0-24, 36, 48 hr brackets Total Effort
Invoices to Receive 1000 13
Handling Units to Putaway 1000 34
Planned Capacity Required Capacity
Putaway Cartons/Hr

Shift 1 Shift 2 Shift 3


HUs to Putaway
30
23
20
20 16 Can we add same for Receiving?
12
10
3 Expected Current
0 Putaway Rate Status
0-24hrs +24hrs +36hrs +48hrs Total +24hrs Handling Units/Hr 400
Cartons/Hr 100
Shift 1 Shift 2 Shift 3
Invoices Received 123 123 123
Receiving - Handling Units/Hr 123 123 123
Handling Units Putaway
Exceptions During Putaway 2 3 4
Can we add Receiving discrepancy loads?
(Problem loads in Hold area)
0-24hrs +24hrs +36hrs +48hrs Total +24hrs Total
Trailers in Yard
20 1 1 1 3 23 Putaway Handling Units/Hr
TUs Checked-In
30 1 1 1 3 33 Shift 1 Shift 2 Shift 3
TU’s Checked In = TU’s on the floor? On the floor
and at the doors? Can we add same for Receiving?
Can we add: Deliveries & Cartons Loaded
OUTBOUND SAAG by Shroud vs Loose (WPT types for CA)

Capacity by shift Lines to Pick 1000 Shift 1 Shift 2 Shift 3


Lines Picked 3 4
Cartons to Pick 1000
Cartons Picked 3 4
Load Drops 1000
Full Pallet Picked 3 4
Pallets to Load 1000 Pallets Loaded by Shroud/
Loose 3 4
Trailers to Load 1000 Load Drops Completed
Trailers Planned 1000 (KX) 3 4
Planned Capacity Required Capacity Trailers Loaded 3 4
Held Order Lines 1000
Trailers Completed 3 4
Replenishments
Can we add Deliveries not closed Replenishments (could go
for completed trailers? under Full Pallets)
Total
This is not needed for Outbound
0-24hrs +24hrs +36hrs +48hrs +24hrs Total
Trailers in
Yard 20 1 CA
1 1 3 23

Expected Rate Current Status Picking Cartons/Hr Picking Lines/Hr


Picking - Lines/Hr 400 Shift 1 Shift 2 Shift 3 Shift 1 Shift 2 Shift 3

Picking - Cartons/Hr 100


Loading - Pallets/Hr 12
WIP in Work Centers

+4hrs

0-2hrs
Loading Pallets/Hr HU Moves/Hr
0 2 4 6 8 10 12 14
Shift 1 Shift 2 Shift 3 Shift 1 Shift 2 Shift 3
Handling Units in Work Center Deliveries in Work Center
VAS SAAG

Completed Orders

Yesterday Today
VAS Lines/Hr

Shift 1 Shift 2 Shift 3 Total Shift 1 Shift 2 Shift 3

Completed Orders 3 4
Completed orders & cartons by type of VAS –
we’ll have 3 done here
Due Due Due Due Due
Date Date Date Date Date Total
Open Orders
20 1 1 1 3 23

Open orders by type of VAS – again, 3 types here

For Inbound types (2 of the 3):


VAS Cartons/Hr
#Backorders to process by 1-day, 2-day, >2day
brackets since arrival Shift 1 Shift 2 Shift 3

Das könnte Ihnen auch gefallen